Title: OPTIMISATION OF OPERATIONS FOR ONSHORE AND OFFSHORE WIND FARMS
1OPTIMISATION OF OPERATIONS FOR ONSHORE AND
OFFSHORE WIND FARMS
EWEC 2006, Athens, 1 March 2006 Colin Morgan
ltcolin.morgan_at_garradhassan.comgt
2Optimisation?
Onshore 97 30k/machine/annum (typical!)
- Of what?
- Availability
- Cost of OM
Offshore ? ?
3Onshore OM costs
- OM costs have weak influence on project
economics - NPV approx. 10 of CAPEX
- But represent a high proportion of operational
cashflows - Decision-driver on retrofits in-house
servicing re-powering
4The offshore differences ..
5The offshore differences ..
6The offshore differences ..
7O2M Structure
8Outputs
- Availability
- Production and Lost Production
- Costs, resource and spares usage
9Example Wind Farm (onshore / offshore)
- 100 x 3MW units
- Representative assumptions on
- Unit costs
- Revenue assumptions
- Failure / alarm shutdown profiles
- Offshore and onshore made as comparable as
possible - OM crewing optimised in both situations to give
minimum OM cost - Offshore-specific
- Wave climate moderate (long-term Hs 1.29m)
- Access limit Hs lt 1.5m
- Transit time to site 2hrs (including
mobilisation etc)
10Findings - costs
Offshore vs. onshore Sensitivity of cost to
failures
11Findings - downtime
Offshore vs. onshore Sensitivity of availability
to failures Serial failure situation not
modelled Value of warranty
12Summarising
- Onshore OM
- Worth more attention than it often gets but
experience and trial and error can lead to
reasonable optimisation of any given project or
portfolio - Offshore OM
- Shortage of relevant project experience
- Much reduced scope for trial and error
- Higher stakes
- Common factor is turbine reliability