Title: Calgary ICI Construction
1Calgary ICI Construction
November, 2005
21944
3Membership
500 members involved in the ICI sector
General Contractors Trade Contractors Manufactur
ers and Suppliers Allied Professionals
14
45
37
4
4CCAs 2005 Executive
President Kees Cusveller, MBA
Sr. Vice President Grant Simon Vice
President Rob Bromberg Vice President
Dave Kinley Treasurer David Hamilton,
C.A. Past President Malcolm
Holbrook Executive Vice President Dave Smith
5Mission Statement
The Calgary Construction Association will
Create Opportunities
Deliver the best leading edge services
Be the effective voice for the local construction
industry
6Government Lobby
Voice of the Construction Industry
7Plans Room
Alberta
CONSTRUCTION OPPORTUNITES ON-LINE NETWORK
www.COOLNet.ab.ca
8Standard Forms of Contract
9Gold Seal Certification
Estimator, Superintendent, Project
manager
10Education
Kelsey Hoffos Youth Employment Coordinator
11(No Transcript)
122004
13(No Transcript)
14(No Transcript)
15History
- 1926 Roots
- 1985 Employee owned
- 1995 Head Office established in Calgary
- 2000 Canadas 50 Best Managed Private Companies
- 2001 Top 10 Canadian Construction Companies
16Locations
17On-Site Magazine 2004 Top 40
18Pine Creek
19Glenmore/Elbow/5th Street Interchange
20Brick Warehouse
21Deerfoot Meadows
22Princeton Grand, Waterfront City View
23IBM Office Complex Phase 2
Architects Rendering
24- Current Construction Climate
- MYTHS!
- No Labour!
- No Material!
- No Equipment!
- No Contractors!
- No Work Capacity!
25- Current Construction Climate
- FACTS!
- Low Unemployment
- Some Material Shortages/Rationing
- 2005 Year of Rain Delays
- Oil at 60.00
- Private Sector, Public Sector spending on major
capital projects
26 27- Current Climate
- Impacts to Owners
- Cost
- Schedule
- Quality
28- Mitigation Strategies
- Fair Contracts
- I dont trust you so why wont you trust me?
29- Mitigation Strategies
- 2. Realistic Schedules
- Price my job by next Thursday, I will award
within 2 months and you need to start the day
after we award and finish quickly
30- Mitigation Strategies
- 3. Pay Bills
- I know the last few invoices were paid late and
I jerked you around with numerous revisions, but
why do you only have 3 men on-site when you
promised me 5?
31- Mitigation Strategies
- 4. Good Documents
- The design is close enough to being done, well
let the contractors figure it out and issue
addenda as required, so why dont you want to
price my project?
32- Mitigation Strategies
- 5. Alternate Forms of Contracting
- I really want you to build my project, but have
to invite 5 other companies to keep you honest!
33- Mitigation Strategies
- 6. Contractors are People Too
34- Summary
- Fair Contracts
- Realistic Schedules
- Pay Bills
- Good Documents
- Alternate Forms of Contracting
- Contractors are People Too
35