Program Managers Report Construction Activity - PowerPoint PPT Presentation

1 / 14
About This Presentation
Title:

Program Managers Report Construction Activity

Description:

duct bank throughout the site. CONSTRUCTION STATUS. Project 5D (Louetta Regional Water Plant) ... for the Central Harris County Regional Water Authority. ... – PowerPoint PPT presentation

Number of Views:21
Avg rating:3.0/5.0
Slides: 15
Provided by: barbar163
Category:

less

Transcript and Presenter's Notes

Title: Program Managers Report Construction Activity


1
Program Managers Report Construction
Activity April 2009
2
Construction Activity
  •  Project 16
  • Construction complete and
  • acceptance on this evenings
  • agenda
  •  

3
  • CONSTRUCTION STATUS
  • Project 1A-3 Contract 2 involves work in
    Charterwood
  • MUD, Harris County FWSD 52, Harris County 119
  • and Northwest Harris County MUD 24
  •    
  • Activity
  • - Notice To Proceed effective March 2, 2009.
  • - Contractor mobilized and started
    installing water
  • line at the Charterwood MUD water plant.

4
CONSTRUCTION STATUS
Project 2, Spears Road Regional Pump Station
  • Activity
  • Contractor completed the tensioned wire
    wrapping of
  • ground storage tank (GST) 1 and continued
    the
  • tensioned wire wrapping of GST 2.
  • Contractor completed the installation of the
    structural
  • steel for the pump and chlorine buildings.
  • Contractor continued installation of the
    electrical
  • duct bank throughout the site.

5
CONSTRUCTION STATUS
  • Project 5D (Louetta Regional Water Plant)
  • Activity
  • Contractor completed excavation of the
  • detention pond.
  • Contractor began excavation of the foundations
  • for the GSTs.

6
CONSTRUCTION STATUS
  • Project 7C-4
  • Contract 1 -- involves connection related work
  • on nine water plant sites
  • Activity - Contractor has completed the
    connection
  • to the GST on five water
    plant sites. - Contractor began work on
    the flow control
  • and metering stations
  • Contract 2 -- involves the installation of the
    connection
  • lines to three water
    plants.
  • Activity - Contractor installed 305 feet of
    16-inch water line and metering
    stations

7
CONSTRUCTION STATUS
  • Project 7C-3 Part 2 includes the line to the
    proposed
  • Bridgestone MUD elevated storage tank and
  • supplemental pumping facilities.
  • Activity
  • - Contractor mobilized and initiated
  • trenchless construction.
  • Project 10B
  • Project finalization ongoing.

8
CONSTRUCTION STATUS
  • Project 14B
  • Contractor completed meter and flow control
  • stations and the tank connection
  • Contractor is working on site restoration.
  • Project 17, Segment 1
  • Contractor working on site restoration.
  • Project 17, Segment 2
  • Contractor continued installation of pipe and
  • began site restoration.

9
WATER LINE INSTALLATION DURING REPORTING PERIOD
Total 13,392
10
WATER LINE INSTALLED  An additional 13,392 feet
of pipe was installed during the reporting period
bringing the total footage of water line
installed in the Authoritys system to 276,162
feet, approximately 52.3 miles. Additionally,
approximately 3,863 feet have been installed for
the Central Harris County Regional Water
Authority.
11
  • GROUNDWATER TRANSFER PROGRAM
  • Provided administrative oversight of the GTP
  • systems.
  • Systems continue to be reliable, responsive,
  • and function effectively.
  • Provided approximately 3.25 MGD of water
  • to the Buyer districts.

12
  • MAJOR ACTIVITIES
  • Continued oversight of engineering efforts.
  • Provided construction administration services
    and
  • project representative services on
    Projects 1A-3
  • Contracts 1 and 2, 2, Construction Packages
    No. 1 and
  • 2, 4C, 5D, 6B-2, 7C-3 Part 2, 7C-4 Contracts
    1 and 2, 11,
  • 14A, 14B, 15B and 17 Segments 1, 2, 3, and 4,
    and
  • construction administration services on
    Projects 7C-3,
  • 10B and 16.
  • Supported and facilitated the acquisition of
    easements
  • for Authority projects.

13
  • MAJOR ACTIVITIES
  • Provided oversight of Severn Trent
    Environmental
  • Services, Inc.s activities and its contract
    to operate the
  • Authoritys GTP systems.
  • Responded to inquiries from districts
    concerning the
  • conversion to surface water and the
    conversion to
  • chloramines disinfection.
  • Assisted the Authority in the definition of the
    basic
  • components of the proposed Water Reuse
    Incentive
  • Program.
  • Completed the Draft Drought Contingency Plan
    for
  • Groundwater Transfer Program.
  • Updated status of districts efforts concerning
    the
  • conversion to chloramines disinfection.

14
CHLORAMINATION UPDATE
Write a Comment
User Comments (0)
About PowerShow.com