Title: Roundup Power Project
1Roundup Power Project
2(No Transcript)
3(No Transcript)
4Development Participants
(Banks independent consultant)
5Bull Mountains MineLocation
- Bull Mountains Mine is located in Musselshell and
Yellowstone Counties, Montana - Southeast of the town of Roundup
- Approximately 35 miles north of the city of
Billings, Montana
6Mine Status
- Mining began in August 2003
- Contracts in place
- First shipments in September 2003
- Test burns at major utilities
- Additional mineral rights purchased
7Technical Description of Roundup Power Project
8Roundup Power ProjectBasic Characteristics
- Mine mouth power generation facility
- 2 x 350 MW (net) units
- Pulverized coal, subcritical (2400
psi/1000F/1000F) - Pollution control
- Dry scrubber for SOx control
- Selective catalytic reduction for NOx control
- Baghouse for particulates
- Air-cooled condenser
FGS Associates, LLC
9Roundup Power ProjectBasic Characteristics
- Water supply from well field (3 wells _at_ 400 gpm
each) - Water collected and recycled zero discharge
- 35-mile transmission line to Broadview substation
- Coal transported by conveyor from mine wash plant
directly to the power plant. - Two 175-meter stacks
FGS Associates, LLC
10Performance Data andMaterials Requirements
- 386 MW gross, 350 MW net per unit (9.3 aux.
power) - 9,840 Btu/kWh net plant heat rate (full load,
including allowance for operating degradation) - Coal consumption
- 165 tons/hour/unit (full load)
- 1.31M tons/year/unit (90 capacity factor)
- Air emissions (values for permitting, two units)
- SOx 0.12 lb/MBtu (2160 tons/year/unit)
- NOx 0.07 lb/MBtu (1260 tons/year/unit)
- Particulates 0.015 lb/MBtu
- CO2 211 lb/MBtu
FGS Associates, LLC
11(No Transcript)
12Plant Area
13(No Transcript)
14(No Transcript)
15Air Pollution Emissionsin Permit Application
- Pollutant Emissions Control Technologies
- Nitrogen Oxides 0.07 lb / MBtu Selective
catalytic reduction 90 overall
reduction Overfire air Low NOX burners - Sulfur Dioxide 0.12 lb / MBtu Low sulfur coal
- 94 Overall Reduction Dry scrubber
-
- Particulate Matter 0.015 lb / MBtu Pulse-jet
baghouse - 99.8 overall reduction
-
-
FGS Associates, LLC
16(No Transcript)
17(No Transcript)
18Source US EPA Environmental Scorecard 2000 Feb.
2002 Clear Skies Administration
Proposal US DOE 2002 Annual Energy Outlook
19Other Permits
- Water Rights
- FAA
- Letter from COE no permits required
- Others routine maximum 30 day lead time
20Key Milestones
- Began permitting July 2001
- Submitted air permit January 14, 2002
- Draft air permit issued August 12, 2002
- Record of decision January 31,2003
- Final awards major equipment packages Oct 2004
- Unit 1 boiler hydro test Mar 2007
- Commercial service for Unit 1 March 2008
- Commercial service for Unit 2 July 2008
FGS Associates, LLC
21Overall Process - Traditional
- Permitting
- Final Engineering
- Construction
- Operation
22Overall Process - Current
- Permitting
- Lawsuits
- Final Engineering
- Construction
- Operation
23Permitting Status
- Permit filed 1/14/02
- Responded to questions from FLMs (issue is
regional haze) - Completion letter from MDEQ received on 8/1/02
- Draft permit issued 8/12/02
- Record of Decision 1/31/03
24Air Permit Appeal
- Filed 2/15/03
- Usual enviro groups
- Kitchen sink approach
- No new issues
- Hearing on June 4 6, 2003
- Board dismissed virtually all items in appeal
25Permit Lawsuit
- Filed 11/26/03 in Musselshell County
- Challenges Board of Environmental Review appeal
decision - Interventions in our behalf by WETA, and AFL-CIO
- Record is clear on all issues
- Court ruled strongly in favor of the permit on
March 31, 2004
26MACT Letter Appeal
- Filed in December 2003
- BER appointed Hearing Examiner to hear appeal
- Stated issue is mercury control
- Another vehicle to try to stall the project
- Hearing held on April 20 21, 2004
- Hearing officer recommended denying all portions
of the appeal. - BER denied petition 7-0 on June 4, 2004
27EIS Status
- Not required under Montana rules
- Volunteered to do EIS
- Approved EIS for mine includes plant property
- Scoping Hearing 4/4/02
- EIS supplement submitted 5/21/02
- EIS draft to be issued 11/15/02
- Hearing 12/5/02
- Record of Decision 1/31/03
FGS Associates, LLC
28EIS Lawsuit
- Filed in Lewis Clark County
- Motion to change venue to Musselshell County by
MDEQ, BMDC1 and intervenors (WETA AFL-CIO)
approved - Court date set for 11/29/04
29DOI Lawsuit
- Filed October 29, 2003 by Nat. Parks Conservation
Assoc., Greater Yellowstone Coalition, Wilderness
Soc., private individual - Objects to DOI finding of no significant impact
- BMDC1 to enter as intervenor
30Construction
- Engineering released in April
- 1st package to be released for bids in June
- Start late August
- 2nd package to be released for bids in August
- Start October
31Economic Impact of Roundup Power Project
- Taxes on 2.7 million tons/year of coal used
- Property and school taxes on 800 million
investment - Transmission taxes on 5.5 m Mwh/year
- Payroll and income taxes on 150 employees at
about 40,000/year additional temporary
maintenance activities - Several million in direct local purchases and
contracts - Ripple or multiplier effect of payroll and local
purchases ( 50m/yr)