Title: Lake Powell Pipeline Project


1
Lake Powell Pipeline Project
  • Environmental Studies Update
  • November 10, 2009

2
Environmental Field Studies Completed
  • Air Quality Study
  • Geology and Soil Resources
  • Paleontological Resources
  • Noise Study
  • Recreation Resources
  • Special Status Vegetation Species and Noxious
    Weed Assessment
  • Visual Resources
  • Vegetation Resources
  • Wildlife Resources

3
LPP Field Studies
LPP Field Studies 11/10/09
11/10/09 Field Study Status
4
Environmental Field Studiesin Progress
  • Archaeological and Historic-Era Resources
  • Special Status Wildlife Species
  • Wetland and Riparian Resources
  • Ethnographic Resources

5
Coordination and Research with Tribes
  • Meetings with 6 Native American Tribes
  • Research study proposals accepted from Hualapai
    and Zuni Tribes
  • Research study proposals pending from Hopi and
    Navajo Nations
  • Meetings with Kaibab Band of Paiute Indians,
    Paiute Indian Tribe of Utah
  • Contacts with 23 Native American Tribes
  • Informal consultation/research by UDWR

6
Other Environmental Studies
  • Surface Water Resources
  • Surface Water Quality
  • Groundwater Resources
  • Aquatic Resources
  • Special Status Aquatic Species and Habitats
  • Land Use Study
  • Transportation Study
  • Socioeconomics/Water Resource Economics
  • Water Supply and Climate Change
  • Alternatives Development

7
Initial Study Reports
  • Draft Study Reports in preparation
  • Initial Study Reports due 1/21/10 are not
    required by FERC to be Draft Study Reports
  • LPP Management Committee proposed to file as many
    Draft Study Reports as possible to accelerate
    overall project schedule
  • Draft Study Reports will be provided to LPP
    Management Committee as they are completed in
    November and December
  • Draft Study Reports not completed by 1/21/10 will
    be provided to FERC/agencies as they are
    completed following internal reviews