Title: WorkshopWebcast
1Workshop/Webcast 3 Municipal Hazardous or
Special Waste Program Plan Development Process
2Welcome
- In person 60 in room
- Webcast audience 100
- slides advance automatically
- enlarge slide
- email box for questions/comments left of slide
screen - use any time
- please include name affiliation
- Archived webcast available
3Todays Agenda - First Half
- Where we are in plan development process
- Summary of comments received
- Product specific summaries
- Targetsaccessibility collection
- QA
- Break (about 310, 20 minutes)
4Todays Agenda - Second Half
- Municipal input comments
- Costs economic impact
- Preliminary fee-setting framework
- QA
- Next steps
- Adjourn (about 500 p.m.)
5Update on Status of MHSW Plan Development Process
6Observations About Plan Development Process to
Date (1)
- March 12 preliminary plan reflects
- baseline information
- current views on how plan should be shaped
- Allows stakeholders opportunity to improve on
work done to date - But now..
- must confirm BEST available data for Year 1
- fee rates must be specified in plan
7Observations About Plan Development Process to
Date (2)
- Municipalities want more specificity
- immediate shift from disposal
- details of 5-year plan
- Stewardsbroadly accepting
- focused on whats expected of them
- costs
- Plan approval depends on
- all requirements of WDA Ministers letter
- defensible Year 1 cost data
- costs are fairly allocated
8Observations About Plan Development Process to
Date (3)
- Comments importantMarch 29, 4 p.m.
- look to you to help improve Year 1 planning
estimates - Plan will make 5-year projections, but
- best estimates aspirational goals
- will be better informed after plan approved
implementation begun - will have stewards reports on actual sales
- agreements negotiated with municipalities
- complete assessments of barriers
- investment costs defined built in
9Consultation Plan Development (1)
10Consultation Plan Development (2)
11Workshops 1 2 Submissions Received
- Stewards (Phase 1 other) 12
- Industry Trade Associations 4
- Municipalities 3
- Service providers 2
- No affiliation mentioned 2
- Total 24
17 received via email 7 via online survey
one stakeholder expanded on survey
12Workshop 2 Comments by Issue (1)
13Workshop 2 Comments by Issue (2)
14Workshop 2 Comments by Issue (3)
15Workshop 2 Comments by Issue (4)
16March 12 Plan Submissions Received to Date
- End Market 1
- Municipalities AMRC 3
- Industry association 1
- ENGOs 6
- Total 11
All comments received via email
Continue to submit comments, please!
17March 12 Plan Comments by Issue (1)
18March 12 Plan Comments by Issue (2)
19March 12 Plan Comments by Issue (3)
20March 12 Plan Comments by Issue (4)
21March 12 Plan Comments by Issue (5)
22March 12 Plan Comments by Issue (6)
23Updates on Status Changes to Product Specific
Summaries
- Mark Kurschner Gordon Day
24Paint Coatings (1)
- Update
- verifying recovery rate
- small quantity Industrial, Commercial
Institutional (ICI) volumes not quantified - Collection Diversion
- primarily municipal collection, highest volume,
most commonly collected product - paint recycler in Ontario
- need 3Rs solution for some container types
25Paint Coatings (2)
- Issues
- verifying collection rate
- managing ICI products
- regulatory potential liability issues re reuse
- potential for return to retail
- plastic container recycling
- reduce leftover quantity
26Paint Coatings (3)
- RD Investments
- develop other recycling options (e.g. latex in
concrete study at University of Western Ontario) - analyze recycling potential for ICI products
- develop container recycling options
- logistical solutions if municipalities no longer
densify by bulking - promotion of BUD message to consumers
retailers, buy what you need, use what you buy,
dispose responsibly
27Oil Filters (1)
- Update
- industry consensus to target all automotive oil
filters, Do-It-Yourself (DIY) Do-It-For-Me
(DIFM), not just residential small ICI - hauler incentive system proposed as in other oil
material programs - Collection Diversion
- collection primarily via participating auto
service providers, also participating
municipalities - haulers processors present in Ontario, need to
examine capacity
28Oil Filters (2)
- Issues
- modifying established hauler incentive system to
cover only filters containers - verifying processing capacity
29Oil Filters (3)
- RD Investments
- analyze existing system infrastructure
- design of hauler incentive system
- including establishment of functional regions
- recruiting collection sites
- educating DIYs to use new system
30Oil Containers (1)
- Update
- industry consensus to target all lubricating oil
containers, DIY DIFM, not just residential
small ICI - hauler incentive system proposed, e.g. as in
other provinces - end market recycler incentive possibly required
- Collection Diversion
- collection primarily via participating auto
service providers participating municipalities
- processing technology exists in other provinces,
needs development in Ontario
31Oil Containers (2)
- Issues
- modifying established hauler incentive system to
cover only filters containers - challenge to municipalities where fluid oil not
included - establishing container recycling
technology/capacity in Ontario
32Oil Containers (3)
- RD Investments
- container recycling capacity
- design of hauler incentive system
- including establishment of functional regions
- recruiting collection sites
- educating DIYs DIFMs to use new system
33Antifreeze (1)
- Update
- discussion within industryshould program go
beyond mandated residential small ICI - new approach targets packaged antifreeze
onlyexceeds ministers mandate, but does not
disrupt established bulk antifreeze programs - hauler incentive system under consideration
- Collection Diversion
- collection primarily via participating auto
service providers participating municipalities
- processing technology capacity exist in Ontario
for fluid, capacity needs confirmation - processing for antifreeze containers needs
development
34Antifreeze (2)
- Issues
- confirming consensus on new approach targeting
packaged antifreeze only - designing hauler incentive system
- quantifying packaged-only generation
- confirming recycling capacity
- confirm reuse options (on site reprocessing)
35Antifreeze (3)
- RD Investments
- analyze existing system infrastructure
- design of hauler incentive system
- including establishment of functional regions
- recruiting collection sites
- educate DIYs to use new system
36Dry Cell Batteries (1)
- Update
- limited information about end-of-life
management Mercury (Hg) percentage - Collection Diversion
- processor in Ontario
- not current destination for collected batteries
- industry to assess all options
- collected through municipal system
- explore opportunities for other options
37Dry Cell Batteries (2)
- Issues
- batteries containing Hg pose greatest challenge
- additional costs to all batteries
- expand collection opportunities when
infrastructure available - targets a struggle
- European Union (EU) directive target used as
place-holder in draft
38Dry Cell Batteries (3)
- RD Investments
- need to assess available for collection rate
- need to analyze Hg levels in battery stream
- pilot collection options
- develop recycling processing standard
- tender for processing
- scale up collection
39Pressurized Containers (1)
- Update
- new recovery information from Parks Ontario
- Collection Diversion
- refillables collected outside municipal system
- hundreds of return outlets
- high return recycling rate precise rate
uncertain - non-refillables (NR) collected municipal
Ontario Parks - once evacuated, cylinder recycled
40Pressurized Containers (2)
- Issues
- high recovery for refillables
- need to quantify
- collection network for NR cylinders
- municipalities, parks
- build on existing propane infrastructure
- developing infrastructure for NR cylinders
41Pressurized Containers (3)
- RD Investments
- expand collection of NR containers at exchange
sites - build on success of refillables
- viability of evacuating NR containers at point of
collection to remove potential hazard costs
42Fertilizers (1)
- Update
- treated separately from pesticides in program
plan - definition requires further clarification
- Collection Diversion
- collected through current municipal system
- cannot be recycled collection equals disposed
- on-site reuse possible option
43Fertilizers (2)
- Issues
- fertilizers consumabledifficult to define
quantity available for collection - using industry collection sales data for retail
fertilizers only - what quantity of fertilizers captured in
definition? - reduction targets 5-year sales projections
44Fertilizers (3)
- RD Investments
- to reduce amount of fertilizers managed through
municipal depots - to develop recycling options for plastic
fertilizer containers - Integrated Pest Management (IPM) strategies
45Pesticides (1)
- Update
- pesticides separated from fertilizers for program
plan - Collection Diversion
- domestic pesticides collected through current
municipal system - commercial agricultural pesticides included in
definition - separate systems in place
46Pesticides (2)
- Issues
- pesticides consumabledifficult to define
quantity available for collection - using extrapolated collection sales data from
other programs for domestic pesticides only - quantity of pesticides captured in current
definition - reduction targets 5-year sales projections
47Pesticides (3)
- RD Investments
- to assess viability of alternatives to landfill
- to develop recycling options for plastic
pesticide containers - Integrated Pest Management (IPM) strategies
48Solvents (1)
- Update
- sales volumes are hydrocarbon
halogenated-hydrocarbon based products sold into
the retail/mass merchandiser market - Collection Diversion
- solvents collected through current municipal
system - solvent can be recycled if non-contaminated
49Solvents (2)
- Issues
- solvents consumabledifficult to define
quantity available for collection - does not match with other provincial program
- quantity of solvent captured in current
definition - wide range of companies may be covered
- reduction targets 5-year sales projections
50Solvents (3)
- RD Investments
- develop processes to produce good quality
recyclable waste streams - education focused on using product up
- education on improved storage practices to reduce
leakage evaporation
51Targets Accessibility Collection
52Targets Accessibility Collection (1)
- Ministers letter
- requires methodology for expanding and
improving the existing collection and diversion
infrastructure for municipal hazardous or special
waste to meet the capture and accessibility
targets - expand accessibility including urban, rural,
northern - methodology to define accessibility targets
- consider capital costs to meet targets
53Targets Accessibility Collection (2)
- Improved accessibility should result in increased
collection - Accessibility measures
- proximity/travel time
- frequency/duration/capacity of events
- program awareness
- increased collection of Phase 1 materials
54Targets Accessibility Collection (3)
- Increasing accessibility Year 1
- PE plan developed to increase awareness
- existing municipal programs encourage doubling
of existing events expansion of depot hours - other municipalities encourage 2 events per year
- provide financial incentives to encourage
industry take back programs
55Targets Accessibility Collection (4)
- During Year 1, begin effectiveness analysis to
plan for subsequent years - compare events to depots
- relative contribution to collection targets
- relative cost to operate
- examine industry take back program
- number of programs
- contribution to collection targets
- analyze materials managed per household served
- Improve methodology based on results
- Analyze capital costs for depot development
infrastructure
56Targets Accessibility Collection (5)
- Increased accessibility, PE intended to increase
collection rate - by increasing amount collected through municipal
industry collection systems - and/or by reducing amount available (for some
products) - Collection targets
- to improve amount collected compared to
available for collection (not volumes
generated) - Diversion targets
- to improve amount diverted to reuse recycling
options instead of disposal methods
57Targets of Available for Collection
58Targets Accessibility Collection (6)
- Targets will be adjusted as program progresses
- amount generated will become more reliable as
stewards reports received - amount collected diverted will be captured
through WDO Datacall MHSW program tracking
59Small Quantity Waste from ICI (1)
- Means MHSW waste from businesses
- where not required to submit generator
registration report under Reg. 347 - not to return more than 100 kg MHSW per month
- Existing Reg. 347 exemptions considered
- residential waste
- small quantity exemptions vary by product,
usually maximum of 5-25 kg per month or
accumulated on-site - waste from servicing motor vehicles subject to
conditions - DIY waste antifreeze, lubricant, oil filters to
selected waste depots subject to conditions
60Small Quantity Waste from ICI (2)
- Issues
- ability of small quantity generator (SQG) to
transport waste due to Reg. 347 requirements
TDGR - ability of municipal collection sites to receive
MHSW from SQG due to limitations in Certificates
of Approval - ability of other collection sites to accept waste
from SQG under Reg. 347 where specific exemptions
do not exist - method of identifying bona fide SQGs,
verification/tracking system may be required
61Small Quantity Waste from ICI (3)
- Possible solutions
- municipalities service providers apply to
change Certificates of Approval (C of A) on
voluntary basis (precedent Peel Region) - apply for blanket C of A to cover MHSW from SQGs
(precedent Rechargeable Battery) - exemption by Rule under Reg. 347 seek
additional exemptions (precedent auto service
centres) - await proposed streamlining changes to Reg. 347
initiated in 2006 - develop verification/tracking system
62Small Quantity Waste from ICI (4)
- Next steps
- continue consultation
- with Ministry of Environment (MOE),
municipalities service providers to identify
best course of action to resolve regulatory
issues - with industry collection site operators to
develop effective SQG verification/tracking
system - process to develop solutions underway will
continue after program start date
63Questions Answers
- Use question/comment box, left of this screen
64Break
65Welcome Back!
66Coming up
- Municipal input comments
- Estimating costs economic impacts
- Preliminary fee-setting framework
- QA
- Next steps
Reminder please send in questions comments
67Municipal Input Comments
68Overview
- General
- PE
- ICI small quantity generators
- RD market development
- Infrastructure accessibility
- Collection diversion targets
- Opportunities next steps
69General (1)
- Plan Development
- fast pace, complicated, iterative
- Municipalities
- support initiative
- Extended Producer Responsibility (EPR) components
evident - encourage more EPR
70General (2)
- Plan approach
- dealing with unknowns
- ICI generation, PE effect on collection
- restructure plan layout to reflect a project
management approach
71Promotion Education (1)
- Plan states PE outline in draft to be replaced
- communications program plan to be developed
- implementation work plan
- RD, using market target audience research
72Promotion Education (2)
- PE outline very general
- PE Strategic Plan will be more effective with
- fixed review periods revision schedule
- clear objectives goals
- measurement tools linked to collection targets
- monitoring reporting protocols
- corrective actions
73ICI Small Quantity Generators (1)
- Good summary of challenges of current system to
service ICI sector - Options fall short of dealing with problem
- Recommend MOE allocate staff financial
resources to develop timely C of A review
solutions
74ICI Small Quantity Generators (2)
- Plan must set out ICI SQG
- objectives goals
- risk areas issues of concern (e.g. unknown
quantities regulatory route) - time frames deliverables
- protocols measurement, monitoring, reporting,
corrective actions
75RD Market Development (1)
- Good concepts identified
- Need to identify diversion targetskey assessment
criteria - Current MHSW infrastructure disposal-based
- Need to draw on experience from other provinces
global initiatives
76RD Market Development (2)
- Current service providers need to be engaged in
processcan be part of solution - Define new market system by bringing in existing
technologies to manage MHSW to higher established
standards
77Infrastructure Accessibility (1)
- Good summary of existing status
- Plan mentions 3Rs options available for most
Phase 1 materials - outlined in material profiles
- Plan states disposal in early years likely to
be relied uponmove quickly to other options - 3Rs options are available
78Infrastructure Accessibility (2)
- Multi-year plan proposed to expand improve
collection diversion - Details available for Year 1 only
- Collection targets defined as goal objective
- diversion targets required
79Infrastructure Accessibility (3)
- PE awareness plan developed in Year 1need it
before commencement date - Year 1 expansion based on municipalities
investing disposal savings into collection - Double events extended hours increase
collection costsis this effective diversion?
80Infrastructure Accessibility (4)
- Take-back programs identifiedplan should
emphasize encourage more - supported by municipalities
- Better define evaluation frequency to enable plan
to adapt meet identified targets
81Collection Diversion Targets
- Year 5 targets shownneed to identify annual
steps - Do-It-Yourself (DIY) Do-It-For-Me (DIFM) exceed
Ministers request - targets entire MHSW stream on some materials
- this is good, however
- Raises questions on evaluation parameters
diversion assessment of all Ontarians SQG
ICI streams
82Performance Tracking
- Year to year comparison in plan
- Need protocols to gather data on-line to
evaluate rapidly accurately program performance
- monthly or quarterly assessments
- Will lead to
- quicker program roll out
- quicker achievement of targets
83Material-Specific Plans
- Comments made via consultation process
- Primary concern is exclusion of some materials
containers from definition - Will monitor plan development for changes
answers to concerns
84Opportunities Next Steps (1)
- Municipalities
- appreciate opportunity to be at table to
formulate first EPR-based functional split plan - will seriously consider using savings for
investment into program expansion - are committed to making this work for all
Ontarians
85Opportunities Next Steps (2)
- Industry
- has opportunity to clean Ontario Homes of MHSW
- MHSW Plan will definitely improve our environment
- Next Steps
- work together to get approvable, workable
measurable plan
86Thank you
- Joseph Hall
- General Manager
- Ottawa Valley Waste Recovery Centre
- jhall_at_ovwrc.com
- 613-732-9285
- www.ovwrc.com
87Estimating Costs Economic Impacts
88Cost Estimates Data Collection
- Municipalities
- all surveyed for net program cost, contract cost
promotional costs 88 provided data - selection surveyed for contract data, material
activity- specific pricing some data provided - Service providers
- surveyed for materials collected, source
processing capacity, pricing by material - limited response very limited pricing data
89Municipal Channel Current Cost (1)
- Total operating cost of existing system (all
activities, all materials) 15M - 88 of programs responded, estimates for 12
- Based on programs that provided detailed
information - 25-50 of current operating cost is for
collection - majority of cost is for Phase 1 materials (some
cross-subsidization) - disposal costs are greatest
90Municipal Channel Current Cost (2)
- Event days
- flat rate for set up 1,000-5,000
- material-specific pricing for packing, bulking,
transport recycling/disposal - combined handling recycling/disposal costs
typically 40-200/lab pack - Permanent depots
- range of operating costs reflect infrastructure
materials collected 600-2,500/tonne - capital cost estimates being developed
91Municipal Channel Accessibility
- Anticipated events facilities
- events additional in current locations, new in
under-serviced areas - depots needs assessment in first program year
with support to programs with existing council
approval - Develop cost estimate for increased accessibility
- event cost set-up, post-collection operations,
transportation, recycling/disposal, capital
(vehicles) - depot capital, operation
92Non-Municipal Channel
- Barriers opportunities to reach targets being
identified as part of industry sector
consultations summarized in profiles - Estimates of investments to support required
activities will be developed - incentives to service providers to increase the
accessibility quantities returned through
existing channels - RD required to foster growth of new channels
- investments to increase diversion of materials
collected through these channels
93Assessing Economic Impacts
94Total Program Cost Comparisons Current System
vs. Year 1 Projections
Where this information is available or can be
approximated in the draft Program Plan
95Year 1 5 Key Program Element Cost Projections
96Examples of Product-Specific Cost Impacts
97Preliminary Fee-Setting Framework
98Guiding Principles
- Fee-setting begins with cost to manage each
material under program - determined by transparent cost allocation
methodology - Material specific fees may be modified to achieve
- overall MHSW program policy goals
- material-specific policy goals including
achieving accessibility targets, collection,
recovery diversion from landfill - Assess Stewardship Ontario common shared costs
across all stewards in fair transparent manner
99Context
- Must meet legal policy objectives in WDA
Ministers program request letter - fees reflect program cost
- need for material specific targets performance
measures - accessibility, collection, diversion
- need for investments to reach targets
- Differs from Blue Box Program other MHSW
programs - no overall combined target, e.g. 60 for Blue Box
materials - little investment in 3Rs infrastructure to date
- Data time limitations for needs assessment
100Implications for Fees
- Fees for each material will have
- portion of common or shared costs
- material-specific cost to manage
- investments required to meet material-specific
targets - No need to transfer cost from one or more
materials to others to meet policy objectives - managed through investments in RD, capital, PE
to meet policy objectives - may consider differences in management cost
within material groups
101Two-Stage Approach
- Stage 1
- Methodology for setting material specific fees to
be defined for first two years of program - Based on best available data
- Year 1 agreements for
- common shared cost allocations
- fee for service arrangements with municipalities
- allocation of cost elements for municipal
channels - material-specific costs for non-municipal
channels - material-specific investments in diversion
infrastructure
102Stage 1 Year 2
- Same methodology with refinements based on
- Stewards Reports received during Year 1
- fee for service arrangements with municipalities
- contracts with service providers
- detailed cost allocation work
103Stage Two
- Review fee-setting methodology
- If revisions required, would constitute a
material change to approved plan - subject to consultation,
- approval by WDO Minister of the Environment
- Based on
- verified cost data
- Stewards Reports
- contracts with service providers
- tracking systems data
104(No Transcript)
105Allocating Common Shared Costs
- Range of options considered
- Preferred Option
- 50 of total shared equally by each material
group - equal cost ( ) for each material group
- 50 of total proportional to direct cost
106Allocating Cost through Municipal Channels
- Post collection cost
- Fee for service agreements with municipalities in
Year 1 - Direct contracts with service providers over time
- Contracts itemize material-specific prices
- No need for detailed allocation methodology
- Some materials managed together costs need to
be separated - physical management or composition audits
- account for different treatment or disposal costs
107Allocating Other Management Costs
- Non-Municipal Channels
- Dedicated to one material costs separate
- Investments to meet targets
- Material-specific, e.g.
- PE
- recycling technology capacity development
- No need for detailed allocation methodology
- Appropriate allocation methodology when costs
address more than one material
108Final Fee Rates
- For each material
- Sum each cost element
- Divide total fees by appropriate physical unit to
get a fee rate, i.e. per unit or volume - Preferred option
- likely some measure of quantity volume format
109Questions Answers
- Use question/comment box, left of this screen
110Next Steps
111Milestones
112Consultation Process
- We want your views!
- Please email questions comments to
- comments_at_stewardshipontario.ca
- by
- 400 p.m
- Thursday, March 29
113Meeting Adjourned