WP3 Network Modelling - PowerPoint PPT Presentation

1 / 22
About This Presentation
Title:

WP3 Network Modelling

Description:

Primary rail network in Europe. Some primary links are in fact ... Strange values of variables e.g. travel time -31,767. Projection in ArcGIS not correct ... – PowerPoint PPT presentation

Number of Views:33
Avg rating:3.0/5.0
Slides: 23
Provided by: christiano8
Category:

less

Transcript and Presenter's Notes

Title: WP3 Network Modelling


1
WP3 Network Modelling
  • Otto Anker Nielsen, oan_at_ctt.dtu.dk
  • Professor, Ph.D.
  • Technical University of Denmark (DTU)
  • Centre for Traffic and Transport (CTT)

2
Presentation overview
  • Data formats and interfaces
  • Road Network
  • Rail Network
  • Air Network
  • Other networks
  • Zones and matrices

3
Road network
  • Road network is now coherent and quality
    controlled
  • Road charging data is not available at link level
  • Assume on fixed links (bridges, tunnels) in
    countries with no general road tax
  • Norway assumed to be Oslo and Trondheim only
  • Assumed to be all motorways in other countries
  • Border resistance
  • Note has been received but not coded
  • Ferries
  • Have been coded and quality controlled
  • Frequency, cost, and time remains to be estimated
    (based on standard function)

4
Network - Rail
  • Source (2)
  • UIC
  • Received
  • 28 April, 2005
  • Coverage
  • Primary and secondary network in Europe
  • Some secondary links are in fact primary
  • No. of records
  • 38,400 rail segments
  • Right projection
  • Source (1)
  • GISCO version II TEN-STAC
  • Received
  • 28 April, 2005
  • Coverage
  • Primary rail network in Europe
  • Some primary links are in fact secondary
  • No. of records
  • 17,600 rail segments
  • Wrong projection

5
Network - Rail
  • Map (1)
  • Map (2)

6
Completed validation and actions
  • Validation of rail network
  • Main rail network is spatially insufficient
  • Secondary network does not include attributes
    except length
  • Combination of the networks possible via IDs
  • Strange values of variables e.g. travel time
    -31,767
  • Projection in ArcGIS not correct
  • Actions
  • Combination of the two networks and estimation of
    attributes on secondary links
  • Editing of attribute values
  • Missing attributes Frequency, cost
  • Using detailed network to correct for wrong
    projection in the other

7
Complete Rail network
  • Key figures for the layer Rail_gisco_ctt
  • 38,391 records
  • Data on type of the railway line
  • No relevant attributes
  • The best network integrity
  • The most complete network

8
Network Adding rail lines
  • 16.000 km rail were added manually to the
    existing basis network (indicated by red)
  • The aim was to provide the basis network with
    extra rail lines were necessary, to generate a
    realistic route choice

9
Network improvements
  • At the same time a first hand quality check of
    the basis network was performed.
  • Securing and repairing the network integrity
  • Regenerating the FromTo and ToFrom node
    attributes

10
Estimating speeds
  • All the manually added and many of the basis
    rail lines are not provided with any indication
    of speed
  • Consequently different techniques for
    estimating travelling speeds, depending on
    available data are considered. The technique
    which delivers the best speed estimate is of
    course used as extensively as possible
  • In theory using the passenger and freight time
    attributes should give the best results. Time
    attribute is based on the UIC network model and
    therefore requires a recalculation to fit our
    network. The speeds derived from this do on
    average seem sensible, but going into detail
    reveals that there is a huge variance in the
    speed on the same line
  • On average the traveling time derived speed is
    70 of the top speed attribute. It is decided to
    use 70 of the top speed as traveling time for
    first choice traveling speed, since the speed
    variations in this way seem more credible

11
Estimating speed preference The procedure
  • If the maximum speed available then 70 of the
    maximum speed
  • Speed calculated on the basis of travelling time
    information (from UIC network model)
  • Speed estimated on NUTS2 level from similar types
    of rail lines
  • Speed estimated from similar types of rail lines
    in general
  • Manually added lines are given a speed of 50 km/h
    for passenger and 40 Km/h for freight
  • The few remaining are manually estimated

12
(No Transcript)
13
High-speed rail
  • Not a special mode, but special link types with
    higher speeds
  • Treated as part of the passenger assignment model
  • NOT as a special mode in the mode choice model

14
Calculation procedure, rail
  • Frequency is assumed fixed or estimated in a
    special loop in the assignment
  • Frequencies are proposed to be dependent on
    railway type (major, minor, double or single
    track, electrified or not), and volumes
    (volume-frequency function)
  • The assignment depend on cost and time and follow
    a stochastic loading procedure
  • The frequencies are collected along t he chosen
    paths and averaged
  • This is NOT used in the assignment, since no
    knowledge exist on lines and transfer points
  • BUT the averaged frequencies are used in the
    passenger demand model

15
Air network
  • Geocoded list of airports
  • All international airports
  • 290 airports in total
  • Fairly thorough quality control revealed good
    quality
  • Missing
  • Former Yugoslavia (all states)
  • Albania
  • Russia, Belarus, Ukraine
  • Keflavik (Iceland)
  • Turkey?
  • Greenland?

16
Air network
  • Air network
  • IWW Air network consisting of origin and
    destination airport, distance, time and 3 cost
    categories (Cost-B, P, H)
  • 4,805 air connections
  • Appears to have quite few connections per airport
    (16.5)
  • gt led to a manual inspection of connections on a
    random sample

17
Air network major airports
  • Connections found from airports homepages using
    Google combined with air specific search engines
  • Copenhagen
  • 125 connections in reality. 75 in Transtools
  • Malaga
  • 105 in reality
  • 50 in Transtools
  • Maybe OK, since the more important connections
    are present, BUT

18
Air network medium sized airports
  • Seville (Spain)
  • 30 In real life as of 16/1-2006
  • 13 in Transtools (of which 9 are also existing
    according to home-page)
  • Trondheim (Norway)
  • 24 in real life
  • 6 in Transtools (5 in common)

19
Air network minor airports
  • Pampolona (Spain) PNA
  • 26 connections as of 13/1-2006, hereof 4 to major
    hubs
  • 1 (one) in Transtools, only to secondary hub
    (Barcelona)
  • Brest (France), BES
  • 20 connections as of 13/1-2006
  • 7 in Transtools (of which only 4 are existing
    according the to homepage of the airport)
  • Several connections to foreign cities are missing
  • Sturup (Sweden)
  • 25 connections according to homepage
  • 3 in Transtools
  • La Rochelle (France) LRH
  • 8 as of 13/1
  • 2 according to Transtools (one common with
    homepage)
  • 6 international flights are missing

20
What to do?
  • Identify major and national hubs (refer to
    discussion on air access models), i.e. 46 major
    hubs
  • Add missing connections to/from all major hubs
  • gt This would be likely to double the number of
    connections
  • gt But most likely the ones with highest demand
    and frequency
  • This will secure that medium and small airports
    are connected to all correct major hubs (as each
    link is bi-directional)
  • Links between medium sized and small airports are
    not quality controlled, i.e. 244 airports are not
    checked
  • Justification
  • The quality control is quite time consuming
  • Finding the airport homepage and double
    controlling with air scheduling engines
  • I.e. the effort is almost identical per airport

21
Inland waterways and harbours a
  • Inland waterways OK
  • Harbours along inland waterways are assumed to be
    in all NUTS III they pass?
  • What about non-connected inland waterways?
  • Edgar has delivered two possible methods for
    calculations?
  • Harbours
  • Important harbours need to be coded (Ming
    Christian solve this)

22
Zones and matrices
  • Zone structure need to be finally agreed upon
  • Zonal data have to be sent to CTT
  • Country level, NUTSII, NUTSIII
  • Matrices should be delivered to CTT
  • IWW needs to provide information on conversion
    from passengers to cars
  • This is a pre-condition for CTT to be able to
    calculate LoS matrices as well as availability
    matrices (inland waterways, ships for TNO)
Write a Comment
User Comments (0)
About PowerShow.com