Title: Building Resilient IT Infrastructure for the 21st Century
1Building Resilient IT Infrastructure for the
21st Century
- Jack Pressman
- Chief Technology OfficerCyber Development Group
International - March 7, 2007
2The Problem
- IT decision makers of enterprise level
companies face the daunting task of - Providing a survival IT Platform
- Providing a durable IT Platform
- Providing an adaptable IT Platform
- Providing a compliant IT Platform
- Providing a cost effective IT Platform
3 The Challenge
- Building a true resilient IT infrastructure
requires significant - Planning
- Resource allocation
- Underlying CxO / Board commitment
4a Methodology for Success.
- Fundamental Steps
- SETUP a dedicated IT Infrastructure Resiliency
Planning Team - PLANNING is key to defining the Enterprise / Data
Center Platform Critical Goals - Develop a fundamental corporate IT Infrastructure
STRATEGY for achieving the Critical Goals - Acquire CxO / Board SUPPORT for Team, Goals and
Strategy
5PLANNING The Data Center
- Building a true resilient Data Center platform
requires addressing 4 Fundamental Components - Capacity Planning
- Floor Plan Layout
- MEP Load Distribution Strategy
- Efficient / Value Based Procurement and
Infrastructure Deployment
6Step One Capacity Planning
- Define the current and FUTURE capacity for both
MEP and DATACOM requirements of the Data Center - Key Capacity Constants
- 1) One Rack takes up 40 SF of Raised Floor
- 40 SF of MEP Equipment Space
(Medium Density) -
- 2) One 20 amp 120 VAC circuit 2 kW (approx)
-
- 3) One Single Phase 30 amp 208 VAC circuit
5.77 kW -
- 4) BTUs kWh 3,412
-
- 5) One Ton of Cooling 12,000 BTUs per Hour
- Example One (1) 20 Ton CRAC provides cooling
for 80 kW of - electricity i.e. 20 racks _at_ 4 kW/
Rack -
-
7Step One Capacity Planning
- KEY CAPACITY VARIABLES
- Total Data Center Floor (in SF)
- Kilowatts per Rack (kW / Rack)
- Production Balance ( of Total Load _at_ each
facility) - Production Capacity Processing Storage (MIPS
/ TB)
8Step One Capacity Planning
- KEY CAPACITY FORMULAS for Current and Future
MEP and DATACOM Requirements - 1a CURRENT (Data Center Floor) Existing DC
Foot Print 1.2 - 1b CURRENT (Kilowatts per Rack) Existing kW
per Rack 1.2 -
- 1c FUTURE (Data Center Floor) Existing DC
Foot Print 2.0 - 1d FUTURE (Kilowatts per Rack) Existing kW per
Rack 2.0 - 1e CURRENT (Bandwidth) Existing Bandwidth
1.4 - 1f FUTURE (Bandwidth) Existing Bandwidth
10.0 - 1g FUTURE (Load Dispersion / Site)
Existing Production 0.33 - 1h FUTURE (Production Capacity / Site)
Existing Production 4.0 -
9Step One Capacity Planning
- EXAMPLES
- 1a IF CURRENT (Data Center Floor) 2,000 SF
48 Racks - THEN near term growth will most likely exceed
2,400 SF 60 Racks - AND long term growth will require a minimum of
4,000 SF 80 Racks - 1b IF CURRENT (Kilowatts per Rack) 3.0 kW per
average rack usage - THEN near term growth will most likely exceed
3.6 kW per rack - AND long term growth will require a minimum of
6.0 kW per rack - 1e IF CURRENT (Bandwidth) 1.5 Gigabits per
Second (GBS) - THEN near term growth will most likely exceed
3.0 GBS - AND long term growth will require a minimum of
15.0 GBS - 1g IF CURRENT (Production Load) 100 MIPS / 4
TB _at_ one Site - THEN long term CAPACITY PLANNING should assume
a LOAD BALANCED platform of 3 sites capable
of 400 MIPS/ 16 TB per site
10Step Two Floor Plan Layout
-
- KEY DESIGN CONCEPT Compartmentalize
- Define the specific Floor Plan based on
PRIORITIES - Security / Access and Control Parameter
- Power / Cooling (Heat Dissipation) Densities
- Business Unit
11Step Two Floor Plan Layout
- EXAMPLES
- Security / Access and Control can be addressed
through multiple levels of physical separation - Highest Level Separate Rooms with 4 hour fire
walls and Man Traps - Medium Level Physically demised rooms using
bonded drywall with a wire fence center from slab
to ceiling - Moderate Level Steel Cage demising each
specified Business Unit from slab to ceiling
12Step Two Floor Plan Layout
- EXAMPLES
- Power Densities can be addressed through 3
physical zones - High Density Racks requiring in excess of 10 kW
- Specifically focused on supporting Blade
Chassis Chilled Water infrastructure required - Medium Density Racks requiring 6 to 10 kW
Blade Servers, Storage Devises Significant
increase in SF allocation per rack for
under-floor air-cooled distribution - Moderate Density Racks requiring 2 to 6 kW
Light Server distribution, Tape Devices, Network
Devices Traditional under-floor air cooling
acceptable
13Step Three MEP Load Distribution
- KEY STARTING POINT Defining the MEP Fork in
the Road Under floor air cooling vs. in-row
chilled water based CRAC systems. - Rack densities (in excess of 6 10 racks)
requiring 8 kW /rack will require a chilled water
based CRAC system - Three Build Options to supporting High Density (8
kW / Rack ) - CHEAP and SHORT-SIDED Spread out rack based
devices to lower energy consumption per rack - EXPENSIVE and COST INEFFICIENT Build the Data
Center with a chilled water based MEP
infrastructure to support in-row cooling - REASONABLE Separate LOW / MEDIUM Density Racks
into a separate MEP ZONE (/ room) from HIGH
DENSITY Racks
14Step Four Efficient / Value Based Procurement
and Deployment
- KEY Efficient and Cost Effective components to
building a better IT Data Center Facility - Build / lease (w/option) facilities with adequate
physical shell space to support future expansion.
- Physically separate High Density Racks that
require expensive in row based chilled water
solutions from Medium / Moderate racks that can
be cooled with traditional under floor air - Look carefully at developing a load balanced /
mirrored multi-site platform vs. a one on-site
production facility with an off-site D/R
facility - NOTE COST OF MOVING A PRIMARY PRODUCTION SITE
AT A LATER DATE IS AN EXTREME EXPENSE AND
SIGNIFICANT DISRUPTION - Only enter in Datacom contracts that provide
roll-up options to more bandwidth at
substantially lower cost per unit at a future
date. - 5. Build networks that provides scalable /
gigabit (lambda) bridges to key metro NAPs
15Building Resilient IT Infrastructure
- Thank You.
- Jack Pressman
- Chief Technology Officer
- Cyber Development Group International, LLC
- 877-996-2999
- www.cyberdevgroup.com
Disclaimer Examples and information provided
are for estimates and discussion only.