Title: PDO NORM Management System


1
PDO NORM Management System
  • Brett Young

2
Specification SP 1170 Version .3.0
  • Defines responsibilities
  • Est. Dose limits
  • Inc. NORM Radiological Surveys into the PTW
  • Training
  • Transport and Storage Locations
  • Emergency Procedures
  • Incorporates NORM Management Guidelines

3
SP 1170
  • PDO Policy
  • Plant that has conveyed or stored production
    fluids (water/oil) or gas are potentially NORM
    contaminated.
  • Dose Limits
  • 1 mSv/year for PDO workers contractors
  • NORM Guideline CSM.001 provides guidance on
    action limits
  • Inhalation / Ingestions Limits
  • 5 cps above background - PPE

4
NORM Management Guidelines
  • Based on Syrian Guidelines
  • How to.. guidelines
  • Inc. NRS in PTW for consistency of approach
  • Added flow charts for specific activities
  • Modified to include PDOs meters

5
HEMP - Permit To Work
  • Production oil/gas/water - conveyed/stored
  • Trips PTW which requires a NORM Radiological
    Survey (NRS)
  • Measurements conducted by RPT
  • Recorded and attached to PTW
  • NRS stipulates controls
  • e.g. PPE, Supervised/Controlled Areas.

6
Example - Zauliyah
  • Measurements for Tank T7402
  • Ground 5 µSv/hour (450 - 500 cps) exterior wall
  • At 50 cm above ground 2.0 µSv/hr exterior wall
  • At 1.0 m above ground 1.5 µSv/hr (125 cps)
    exterior wall
  • At 1.5 m above ground 20 cps exterior wall
  • Inside tank in centre approx. 15 - 20 µSv/hr
  • Workers 4 hrs per day inside cleaning 80
    µSv/day
  • 80 uSv/day x 14 (days) 1120 µSv/2 weeks inside
    tank
  • gt 1 mSv/2 weeks

7
NORM Radiological Survey v 24372
8
Example of NORM Survey Report Certificate No
24372
9
Monitoring of Personnel
  • Action Limit 1 µSv/hour
  • Record on NORM Radiological Survey
  • Attached to PTW
  • RPT estimates workers daily dose
  • gt 8 µSv/day record into a database
  • Risk assessment - Tank cleaners and sludge farm
    operators required to wear TLD Badge

10
Bahja NORM Storage facility
400 m
Entrance
Concrete pad 100 m x 50 m
Rest Room Toilet
400 m
gate
2 Pits Sludge Storage 100m10m1m depth
Tubulars 50m x 25m
Drum storage 50m x 25m
Scrap metal 50m x 25m
11
NORM Survey Proposal
  • Reservoir to Min Al Fahal (MAF)
  • Oil/water/gas ? wells ? manifold/gathering
    station
  • ? Main pumping station (MPS) ? MAF tanks
  • Survey Proposal
  • Survey backwards from MPS (dehydration tanks) ?
    Gathering Stations (separators) ? well heads
  • Fields declared
  • Green (NORM Free)
  • Yellow (NORM Suspected)
  • Red (Known NORM)
  • Work back as to which geology, depth, water
    chemistry, E.O.R. programs are likely to produce
    NORM

12
Further discussion
  • Does PDO need dedicated Interior based RPS?
  • How do other organisations consistently identify
    contaminated plant/areas? Do you use a PTW system
    or other?
  • Are surveys a useful tool? Do you utilise a
    similar method or other than proposed?