Title: Eustrio Benitz Furieri
1Regulatory Review of IC Systems Changes Related
to SGs Replacement, Use of Advanced Fuel and
Power Increasing of ANGRA 1 NPP
COMISSÃO NACIONAL DE ENERGIA NUCLEAR (National
Nuclear Energy Commission)
PRESENTATION TO TECHNICAL MEETING POWER
INCREASING IMPROVED IC MAY 29-31, 2007
PRAGUE CZECH REPUBLIC
- Eustério Benitz Furieri
- Electrical and IC Group
- Reactor Coordination
- CNEN - Brazil
2Presentation Topics
- Angra 1 Operational Experience Main Facts
- Project Schedules
- Licensing of IC and Electrical Systems
- Some Regulatory Issues
- Conclusions
3Angra 1 Operational Experiences Main Facts
- Thermal power 1882 MWth, 657 MWe, 2 Loops PWR,
Westinghouse Twin plant Krsko (Slovenia) - Utility / Engineering Company - ELETRONUCLEAR
- Construction license May 1974
- Core load September 1981
- First Criticality - March 1982
- Connection to the Grid - April 1982
- Commercial operation - January 1985
4Angra 1 Operational Experiences Main
Facts(continued)
- Upgrading Programs during Provisional
Authorization (1981) and Authorization for
Initial Operation (1987) - Lessons-learned from TMI-2 accident (IC,
electrical systems, operator support systems,
emergency procedures, etc) - Corrections on design changes of Steam Generators
- Installation of titanium tubes in the Condenser
- New Diesel Generators (currently, 2 main DGs and
2 former DGs for Blackout Rule)
5Angra 1 Operational Experiences Main
Facts(continued)
- Phase after the Authorization for Permanent
Operation (APO) in December 1994 - Upgrading programs from the previous
authorization had continued and new programs were
developed after the APO issuance, as Improvement
Programs of the Authorization. - In 1990 decade, the rate of degradation of SGs
tubes in Angra 1 and in other plants with similar
SGs had urged studies for the replacement
planning, consolidated in 2000 (when the SGs of
Krsko were replaced).
6Project Scope and Schedules
- Steam Generators Replacement
- Utility signed in 2004 a contract with AREVA NP
subcontract with Brazilian Company NUCLEP for
assembly scope planned delivery in July 2007 - From Oct-2008 to Jan-26-2009 (Plant Outage P16)
- Next Generation Fuel 16NGF (Westinghouse with
Brazilian, Korean and Slovenian Organizations
started 2000-2001) transition fuel cycles are
going on full core in 21th fuel cycle - Power uprate of 6.3 is estimated for 2012 19th
fuel cycle - Westinghouse was contracted for the Safety
Analyses revision and related issues at new power
level.
7Licensing Events and Documentation
Dead-LinesPlant operation planned to January 26,
2009
8Some Regulatory Issues
- The following issues should have attention
together with analyses of the IC and electrical
systems changes for the Project SGs
replacement/16NGF/Power uprate - Significant number of plant transients and trips
caused by IC and electric systems malfunctions
of BOL, transformers and off-site power supply. - Plant performance has been lessened by human,
ageing mechanisms and organizational factors
which have to be considered in Project analyses. - Discussions on unreviewed safety questions had
some contribution to delay the documentation for
preliminary reviews on acceptance criteria and
safety analyses impact.
9Some Regulatory Issues(continued)
- The new or revised documentation should be
implemented taking into consideration responses
to current license conditions (for example PSR
revision, new Tech. Spec. completion, updated
FSAR according to recent NUREG-800, electrical
and IC qualification program to routine plant
programs) - The quality management system should be improved
to assure the application of similar requirements
for software and digital IC systems important to
safety by all sectors of the Utility (operation,
engineering, safety analysis)
10Conclusions
- Major changes and modernization at Angra 1 NPP
will improve the safety and overall performance
of the plant. However, specific demands from IC
and electrical systems need integrated solutions
with current plant programs. - The compliance with regulatory requirements of
the current License involve many IC, HSI and
support systems issues which require a management
together with these major changes and
modernization of the plant for the next five
years. - The improvement of quality management system in
progress is an important regulatory issue,
specially in the case of requirements for
software and digital IC systems important to
safety, with impact in all upgrading projects and
in the licensing of new plant with digital IC
system.
11ANGRA 1(right) and ANGRA 2 - 2002
12ANGRA 1, 2 and the Local of Future ANGRA 3
NPPs(picture-1998)