Title: Fermilab PMG Meeting


1
General Quality Assurance of Silicon Sensors and
Parts Flow
DØ Inner Layer Sensor Production Readiness
Review August 08, 2003 M. Demarteaufor the
Run IIb silicon group
2
Sensor Delivery
  • The production at Hamamatsu calls for the
    following delivery schedule
  • The terms of the contract with Hamamatsu are such
    that the project has six months after receipt of
    the sensors to reject them

3
Parts Flow
  • All sensors are checked in at Fermilab undergo
    visual inspection
  • Outer Layer sensors
  • Fermilab IV/CV
  • 10 to Stony Brook, KSU for strip tests in ratio
    21
  • Inner layer sensors
  • All tests at Rochester

4
QA Program
  • Sensor QA and Distribution
  • Rene Jones receives sensors, enters data into
    database
  • passes sensors for I-V, C-V and visual inspection
  • Mme. Mao will do all C-V, I-V measurements and
    long-term burn-in
  • Nina Ronzhina will do all visual inspection with
    Rene Jones as backup
  • Ralf Bernhard will oversee the whole QA program
  • backup help from Ron Lipton, Marcel Demarteau, L3
    managers
  • passes 10 of sensors for mechanical measurement
    at Fermilab
  • based on recommendation from L3 managers
  • measurements performed on OGP by SiDet metrology
    group
  • Outer layer sensors
  • ship 10 of the sensors to various test sites,
    based on L3 manager recommendation
  • Stony Brook KSU 2/3 1/3
  • Stony Brook Bob McCarthy, Hai-Jiang Gong
  • KSU Robin Sidwell, Ron Sidwell graduate
    students
  • Inner layer sensors
  • ship 100 to University of Rochester
  • Sergey Korjenevski graduate students

5
Irradiation QA Program
  • Sensor Irradiation
  • All irradiation carried out at KSU JRM using 10
    MeV proton beam
  • 1.5 of the test structures with diodes and baby
    sensors will be irradiated
  • two sessions 2.5x1013 1MeV n equivalent/cm2 each.
  • The depletion voltage after the integrated dose
    must not exceed 350 V and no breakdown can be
    observed at this voltage or below.
  • Person in charge of irradiation at KSU is Tim
    Bolton

6
Manpower Estimates for Probing
  • Based on workload, timing of actual strip scan of
    sensors using switching matrix, maintenance of
    setup, etc, determined the distribution for
    various test sites and FTEs needed

All people identified by name, and have accepted
the responsibility, for carrying out the proposed
QA program.
Manpower for measuring irradiated sensors will
come mainly from KSU
7
Database
  • All information will be stored and tracked in
    database
  • Adopted ATLAS database
  • Old database in MySQL relied on student in
    computing department at UIC. Concerns about long
    term stability, support and flexibility motivated
    us to adopt the ATLAS database design
  • Oracle based identity relationship
  • Item
  • Test
  • Assembly
  • Shipment/Tracking
  • Ideally suited to silicon detector
  • Official transfer of designer files from ATLAS by
    the University of Geneva
  • Supported by DØ online support group
  • Stan Krzywdzinski, Vladimir Sirotenko, Taka
    Yasuda, Stu Fuess
  • Will provide web interface using existing tools

8
Entity Relationship
  • Full entity relationship defined and implemented
  • Database can be accessed at http//www-d0online.
    fnal.gov/sdb-dev/

9
Database Use
  • Common excel format defined for all sensor tests
  • Scripts have been written which take the
    information from the spreadsheets and uploads the
    information into the database
  • Server at each test site with all information
  • e.g. http//sbhepnt.physics.sunysb.edu/silicon/
    L2
  • Same principle used for all components in the
    silicon detector

10
Conclusions
  • All outstanding concerns have been addressed
    regarding
  • quality control
  • manpower estimates
  • site verification
  • tracking
  • data storage and retrieval
  • We believe we have a rigorous quality sensor
    control program in place
  • Well defined QA procedures
  • Certified test sites with trained personnel
  • Sound manpower estimates and manpower allocated
    to the project
  • Part tracking using Oracle database
  • We thank the committee for helping us addressing
    some earlier shortcomings