CMS Tracker Readout Effort Requirements in Instrumentation Department - PowerPoint PPT Presentation

About This Presentation
Title:

CMS Tracker Readout Effort Requirements in Instrumentation Department

Description:

8 Racks. 40 K ADC Channels 10 Bit_at_40MHz. Max Trigger Rate 100 kHz. Input Rate 1.5 T Byte/s ... Testing is a big job. Can't promise to deliver in June? Use Batch1 PCBs. ... – PowerPoint PPT presentation

Number of Views:22
Avg rating:3.0/5.0
Slides: 24
Provided by: rob1164
Category:

less

Transcript and Presenter's Notes

Title: CMS Tracker Readout Effort Requirements in Instrumentation Department


1
CMS Tracker ReadoutEffort Requirements
inInstrumentation Department
  • John Coughlan

2
CMS Tracker Readout Summary
  • Overview.
  • Scope of project in INS
  • Team members
  • Project Status
  • List of tasks to completion
  • Effort required
  • Summary Comments

3
CMS Tracker ReadoutOverview
Task To readout a very large Silicon Tracking
detector. 9 million Silicon Strip channels ON
Detector 73K APV25 pipeline chips _at_ L1 Trigger
MUX APV Frame output Analogue Data readout via
Optical links (APV Frame Header Strip Data) gt
INS Effort essentially complete OFF Detector
Front-End Drivers (FED) Digitise / Zero Suppress
/ DAQ readout 500 x 9U VME64x boards (incl
spares) 96 ADC channel boards gt INS Effort
major activity
25
Hybrid
Front-End Hybrid
Silicon Strips
70m
On Detector (Hard Radiation)
FPGA
DAQ
Counting Room
VME 9U FEDs
4
CMS Tracker FED Block Diagram
96 Tracker Opto Fibres
CERN Opto- Rx
Modularity 9U VME64x Form Factor Modularity
matches Opto Links Data suppression board. 8 x
Front-End modules OptoRx/Digitisation/Cluster
Finding Back-End module / Event Builder VME
module / Configuration Power module Other
Interfaces TTC Clk / L1 / BX DAQ Fast
Readout Link TCS Busy Throttle VME Control
Monitoring JTAG Test Configuration
9U VME64x
Analogue/Digital
JTAG
FPGA Configuration
FE-FPGA Cluster Finder
VME Interface
VME-FPGA
BE-FPGA Event Builder
TCS
TTC
TTCrx
DAQ Interface
Buffers
Power DC-DC
Temp Monitor
Front-End Modules x 8 Double-sided board
Xilinx Virtex-II FPGA
TCS Trigger Control System
5
CMS Tracker FED Data Processing
96 Tracker Opto Fibres
CERN Opto- Rx
9U VME64x
Data Suppression 9U VME64x Form Factor Analogue
96 ADC channels (10-bit _at_ 40 MHz ) _at_ L1 Trigger
processes 25K MUXed silicon strips / FED Raw
Input 3 Gbytes/sec after Zero
Suppression... DAQ Output 200 MBytes/sec (_at_
L1 max rate 100 kHz) Digital
Processing Flexible Digital Logic Xilinx
Virtex-II FPGAs 40K-gt3M gatesFPGAs programmed in
VHDL VERILOG
Analogue/Digital
JTAG
FPGA Configuration
FE-FPGA Cluster Finder
VME Interface
VME-FPGA
BE-FPGA Event Builder
TCS
TTC
TTCrx
DAQ Interface
Buffers
Power DC-DC
Temp Monitor
Front-End Modules x 8 Double-sided board
Xilinx Virtex-II FPGA
TCS Trigger Control System
6
CMS Tracker FED Board Layout Primary Side
  • Complex board
  • Pushing density limits on large board for cost
  • Opto Analogue Digital issues
  • Brings together considerable INS Dept expertise
    and experience from several areas into one project

7
CMS Tracker FED Board Layout Primary Side
Double sided
View thru the board
8
FEDv1 Front-End module Primary Routed
OptoRx
ADCs
OpAmps
40K FPGAs
1500K FPGA
Note FPGA de-coupling
Dense circuitry
12 optical channels
9
CMS Tracker FED Transition card option
Due to mechanical constraints place DAQ link card
on Transition card
Transition Card
Very simple card
BE-FPGA Event Builder
DAQ Mezzanine Card
TTC
TTCrx
DAQ Front-end Readout Link FRL
S-LINK64
Buffers
10
CMS Tracker FED INS Main Deliverables (Project
Spec)
  • RAL INS
  • RAL PPD
  • Imperial College
  • Brunel

FED project institutes
  • Includes
  • Design of 9U FEDs. Electrical tests of design.
  • Design Testing Baseline FPGA Firmware.
  • Production of prototypes for CMS silicon tests.
  • Production and Testing of 500 FEDs (incl
    spares.)
  • Transition cards for DAQ links (optional)
  • Low level driver software.
  • Full Documentation.
  • Communication with CMS groups
  • Assistance during Tracker installation
    commissioning.
  • Excludes
  • OptoRx design testing.
  • Opto Test equipment for FEDs.
  • DAQ link mezzanine card.
  • High level software.
  • Provision of VME crates and cabling.
  • Other modules in FED VME crates e.g. CPUs.

11
CMS Tracker FED Team Members in INS
Moving from Design phase to Test phase...
  • Core Team
  • John Coughlan
  • Project Manager CMS Link
  • Software
  • Saeed Taghavirad
  • Hardware Design Firmware
  • Ivan Church
  • Test Engineer
  • Plus
  • Ed Freeman
  • Firmware
  • James Salisbury
  • Analogue Design
  • Rob Halsall
  • Technical Advisor
  • Others
  • Design Office
  • Procurement
  • Additional Test support

12
CMS Tracker FED Project Status
  • 1998-gt2001
  • FED-PMCs x 60 produced for CMS Silicon module
    testing.
  • Small nr channels with limited functionality.
  • Cheap. Very flexible. Plug in PC or use in VME
    crate.
  • Very popular with CMS! (and others)
  • 2001
  • Final 9U FED design started in earnest.
  • Requirements document produced.
  • Algorithms studied. Board interfaces
    investigated.
  • Choice of (NEW) FPGA family made. (Cost critical)
  • 2002
  • Implementation of design 96 chan ADC on 9U.
  • Analogue design complete (OptoRx finalised by
    CERN).
  • Cluster finding algorithms implemented in
    Firmware.
  • DAQ interface baseline decided.
  • Basic simulations and test bench measurments
    made.
  • Components chosen. Board layout Routing.
  • Manufacture of first pair of FEDv1s.

FED-PMC (FED prototype)
13
CMS Tracker FED INS Dept Outline Tasks
  • 2002
  • Manufacture 2 x FEDv1.
  • 2003
  • Test FEDv1 design
  • Analogue electrical tests (Opto tests _at_ IC)
  • Firmware (Cluster finding Event readout)
  • VME Interface
  • DAQ interfaces (with IC)
  • Driver software
  • Production and Testing of 20 FEDv1s for CMS
    tracker testing.
  • 2004
  • Pre-Production and Test of 20 x FEDv2.
  • Start procurement for 500 FEDs.
  • Set up for production Tests.
  • 2005 (tasks in parallel)
  • Manufacture of 500 FEDv3.
  • Production Testing _at_ RAL.
  • Assist Installation Commissioning _at_ CMS.
  • 2006
  • Complete commissioning _at_ CMS.

14
CMS Tracker FED INS Dept Effort
15
CMS Tracker FED Comments
  • Effort projections (made in 2000) have not been
    adjusted.
  • Allocations should be sufficient given following
    assumptions
  • Effort profile needs adjusting to reflect
    schedule changes (carry over this year).
  • Assumes no major re-design of FEDv1 to FEDv3 for
    production.
  • Assumes no further schedule slippage
    (installation in 2005)
  • No contingency needed (e.g. for staff turnover).
  • Assumes personnel with key skills (eg. FPGA
    design) stay with project.
  • Assumes assistance in automated FED production
    testing.
  • Assumes little or no support for FEDs with CMS
    tracker module testing.
  • But Installation commissioning effort will not
    be sufficient.

16
FED Design Testing
96 Tracker Opto Fibres
CERN Opto- Rx
Detailed Design Test Plan JTAG Boundary Scan
Digital connections Chip Scope Integrated Logic
Analyser Cores Capture raw ADC data (without
VME) Opto-Tests or Inject electrical signals
post-OptoRx Special FPGA loads e.g. Pattern
Generators Additional Test Features Internal/Ex
ternal Clocks External Triggers
9U VME64x
Analogue/Digital
JTAG
FPGA Configuration
FE-FPGA Cluster Finder
VME Interface
VME-FPGA
BE-FPGA Event Builder
TCS
TTC
TTCrx
DAQ Interface
Buffers
Power DC-DC
Temp Monitor
Front-End Modules x 8 Double-sided board
Xilinx Virtex-II FPGA
TCS Trigger Control System
17
CMS Silicon Strip Tracker FED Status
96 Tracker Opto Fibres
CERN Opto- Rx
9U VME64x
Analogue/Digital
JTAG
Board Status
FPGA Configuration
FE-FPGA Cluster Finder
VME Interface
VME-FPGA
BE-FPGA Event Builder
TCS
TTC
TTCrx
DAQ Interface
Buffers
Power DC-DC
Temp Monitor
Front-End Modules x 8 Double-sided board
Xilinx Virtex-II FPGA
TCS Trigger Control System
18
CMS Silicon Strip Tracker FED Summary Schedule
FF1 Full scale Prototype FF2
Pre-production FF3 Final production
Summary Presented a 9U VME64x board for
off-detector readout of Silicon Strip
Tracker Digitisation Zero Suppression Event
Readout Meets SST data rate requirements Analogue
96 channel 10-bit ADC _at_ 40 MHz Digital
Virtex-II FPGAs flexible logic Test and Monitor
features aid debugging
Schedule 2002/Q4 2 x FF1 _at_ RAL for
test 2003/Q4 10 x FF1 _at_ CERN 2004/Q4 10 x
FF2 manufacture 2005/Q2 500 x FF3
manufacture (funds permitting)
http//www.te.rl.ac.uk/esdg/cms-fed/index.html
19
CMS Silicon Strip Tracker FED Summary Schedule
  • In order to achieve minimum firmware software
    on TIB timescales require...
  • Confirmation of functionality needed for TIB
    tests.
  • Close co-operation between UK and Tracker DAQ
    group.
  • Arrange small FEDv1 online meeting.
  • Propose contact from UK to visit CERN for
    technology transfer.
  • Keep systems h/w and s/w as close as possible
    (within UK) and between UK and CERN.
  • Note We now have additional effort in UK for
    test software, database, etc.
  • See Testing Talk

20
CMS Silicon Strip Tracker FED Counting Room
Layout (illustration)
FED
DAQ
  • 40 K ADC Channels 10 Bit_at_40MHz
  • Max Trigger Rate 100 kHz
  • Input Rate 1.5 T Byte/s
  • Output rate 25 Gbyte/s/
  • 440 Boards 96 ADC/Board
  • 24 Crates
  • 8 Racks

4 TTC Partitions
21
FED Schedule
FEDv1 Full scale Prototype FEDv2
Pre-production FEDv3 Final production
Schedule 2002/Q4 2 x FEDv1 _at_ for UK test Batch
1 2003/Q4 10? x FEDv1 _at_ CERN Batch
2 2004/Q4 10? x FEDv2 manufacture 2005/Q2
500 x FEDv3 manufacture (funds permitting)
OptoRx added post-assembly. Procurement
started for critical parts for Batch 2
22
FED TIB Test Schedule
Q. Deliver 2 x FEDv1 Batch 1.5 _at_ CERN for TIB
test starting July 2003 ??
  • Very tough. Testing is a big job. Cant promise
    to deliver in June?
  • Use Batch1 PCBs. ie No design iteration possible.
  • Risk that design has major fault.
  • Prioritise essential firmware and testing plan.
  • Require explicit list of functionality essential
    for the TIB assembly centre.

23
FED TIB Test Schedule
Write a Comment
User Comments (0)
About PowerShow.com