Title: NEPOOL Objective Capability (Installed Capacity Requirement) For Power Year 2005/2006
1NEPOOL Objective Capability (Installed Capacity
Requirement)For Power Year 2005/2006
- Presentation to the
- Joint ISO PAC/NEPOOL RC Meeting
- February 2, 2005
- Wyndham Hotel, Westborough MA
2Background
- NEPOOL Objective Capability (OC) is the amount of
installed capacity that NE needs to meet the
NEPOOL resource planning reliability criterion of
1 day in 10 years disconnection of
non-interruptible customers. This criterion takes
into account - Possible levels of peak loads due to weather
variations, - Impact of assumed generating unit performance,
and - Possible load and capacity relief obtainable
through the use ofISO-NE Operating Procedure no.
4 Action During a Capacity Deficiency.
3Background (Contd)
- OC is established by NEPOOL on an annual basis
one year at a time. - Power Supply Planning Committee reviews
assumptions and develop OC scenario(s) for
Reliability Committee (RC) consideration. - RC reviews the OC scenario(s) and votes a
recommendation(s) for Participants Committee
approval.
4Background (Contd)
- OC is calculated using the single area
Westinghouse/ABB Capacity Model Program. Single
area refers to the assumption that there is
adequate transmission to deliver capacity where
and when is needed. Simply said, all loads and
generators are assumed to be connected to a
single electric bus.
5Background (Contd)
- The Capacity Model uses probabilistic calculation
that simulates the availability of system
resources (taking into account each generating
units assumed forced outages and maintenance
requirements) to meet the expected load (taking
into account possible variations due to weather).
This calculation is often referred to as the
Loss of Load Expectation (LOLE) calculation.
6- Assumptions
- For 2005/06 OC Calculations
7Assumptions
- Loads
- Capacity
- Existing
- Additions
- Attrition
- Purchases and Sales
- Daily Cycle Hydro Ratings
- ICAP Capable Load Response Program Assets
- SWCT RFP
- Unit Availability
- Tie Benefits
- Other OP-4 Load Relief
8Loads
- Based on CELT 2005 forecast
- Weekly distributions represented with
- Expected value (mean)
- Standard deviation
- Skewness
- Based on short-run seasonal peak load forecast
- Summer peak 26,355 MW
- Winter peak 22,830 MW
9Capacity
- Existing Capacity
- Based on 2005 CELT Data
- Assets within January 2005 Seasonal Claimed
Capability (SCC) Report - Summer Rating August 2004 SCC Report
- Winter Rating January 2005 SCC Report
- Units categorized as EMS SO units included
- Energy Management System 30,516 MW (S) 32,878
MW (W) - Settlement Only resources 238 MW (S) 313 MW
(W)
10Capacity
- Capacity Additions
- Ridgewood Generation (8.4 MW)
- Kendall Steam 3 Reactivation (25 MW)
- Kendall CT Reactivation (158 MW)
- Capacity Attrition
- No attrition assumed
11Capacity
- Purchases and Sales
- Purchases and Sales as reported in 2004 CELT
Report (453 MW) - Daily Cycle Hydro Ratings
- 50 Percentile value of daily flows assumed with
adjustment (59 MW in July) to OC.
12Load Response Assumptions
- ICAP Capable Load Response Program
- All capacity listed as of January 1, 2005 as
ready to respond enrolled in - Day-Ahead Demand Response Program
- Real-Time Demand Response Program
- Real-Time Profiled Response Program
- Assets grouped by Program and Area
- Assets assumed to have performance factors based
on August 20, 2004 audit results and NERC Class
Average EFORd values for known emergency
generation.
13Assumed MW from Load Response Program
EFOR values based on Aug. 20, 2004 audit results
and NERC Class average data
Program Load Zone MW Assumed in 05/06 OC Calculations MW Assumed in 05/06 OC Calculations Assumed EFOR () Assumed EFOR ()
RT 2-hour Demand Response ME 1.0 30.0
NEMA 1.5 99.0
WCMA 9.0 84.0
RT 30 Minute Demand Response CT 218.0 3.9
NEMA 3.0 37.0
Profiled Response ME 76.0 100.0
NEMA 1.4 7.45
VT 5.9 100.0
Total Total 315.8
14Emergency Resources
- SWCT RFP
- Contracted SWCT RFP resources not currently
enrolled in Real-Time Demand Response included - 218 MW total contracted for summer 2005
15- PSPC recommended using EFORd instead of EFOR to
be consistent with EFORds application in the
ICAP market and the UCAP rating for generating
units.
16EFORd Equation
Where
17- EFORd - Equivalent Demand Forced Outage Rate
- ff - full f-factor
- fp - partial f-factor
- FOH - Full Forced Outage Hours
- EFOH - Equivalent Full Forced Outage Hours Sum
of all hours a unit was involved in an outage
expressed as equivalent hours of full forced
outage at its maximum net dependable capability - SH - Service Hours The time a unit is
electrically connected to the system - Sum of all
Unit Service Hours. - AH - Available Hours The time a unit is capable
of producing energy, regardless of its capacity
level -- Sum of all Service Hours Reserve
Shutdown Hours Pumping Hours Synchronous
Condensing Hours - RSH - Reserve Shutdown Hours The time a unit is
available for service but not dispatched due to
economic or other reasons
18Equiv. Forced Outage Rate Demand (EFORd)
- Interpretation
- The probability that a unit will not meet
itsdemand periods for generating requirements. - Best measure of reliability for all loading
types(base, cycling, peaking, etc.) - Best measure of reliability for all unit
types(fossil, nuclear, gas turbines, diesels,
etc.) - For demand period measures and not for thefull
24-hour clock.
19Unit Availability Assumption
- 5-year average EFORd modeled
- Forced Outage Rates (EFORd) determined using
combination of NERC Class Average EFORd data and
available New England GADs data. - NERC Class Average used Jan00 Feb03
- Calculated EFORd using GADs used Mar03 Dec 04
- Since Dec 04 data is not yet available,Dec 03
data is used for Dec 04.
20Unit Availability
- New England Nuclear units performance not
correctly represented by NERC Class Average EFORd - For Nuclear units, used ISO-NE calculated Jan00
through Feb03 EFOR and Mar03 through Dec04
EFORd. - Since Dec 04 data is not yet available,Dec 03
data is used for Dec 04.
21Results of 60-Month Average
Unit Category Summer MW of System 05/06 Assumed WEFORd ()
Fossil 10,179 32.9 6.71
CC 11,040 35.7 6.03
Diesel 121 0.4 5.56
Jet 1,873 6.1 7.09
Nuclear 4,387 14.2 1.35
Hydro (Includes Pumped Storage) 3,340 10.8 3.80
Total System 30,940 100 5.41
22Tie Reliability Benefits
- Tie Reliability Benefits from Hydro-Quebec, New
Brunswick, and New York are modeled in the
Westinghouse Capacity Model as Resources - PSPC suggested two sets of tie benefits
assumptions - 1,400 MW (summer values including HQICC)
- 2,000 MW (summer values including HQICC)
23Tie Reliability Benefits - HQICC
- Hydro-Quebec Interconnection Capability Credits
for 2005/06 are determined based on load and
capacity data submitted to ISO-NE by Hydro-Quebec
Distribution and Hydro-Quebec Production. - The monthly HQICC values recommendedby ISO-NE
are - June through November, March through May 1,200
MW - December through February 0 MW
24OP-4 Load Relief
- Load Relief values based on ISO-NE Operating
Procedure No. 4 (OP-4)
2005-2006 Power Year OP-4 Load Relief (MW) 2005-2006 Power Year OP-4 Load Relief (MW) 2005-2006 Power Year OP-4 Load Relief (MW) 2005-2006 Power Year OP-4 Load Relief (MW) 2005-2006 Power Year OP-4 Load Relief (MW)
(A) (B) (C) (BC-A)
Minimum Operating Reserve OP-4 Actions 9 10 5 Voltage Reduction Total OP-4 Load Relief
June September 200 45 395 240
October - May 200 45 342 187
- 5 Voltage Reduction is based on 1.5 of the
seasonal peak load as determined by Spring
Voltage Reduction Test Results
25 Tie Reliability Benefits Scenarios
- The PSPC suggested calculating NEPOOL OC for
2005/06 Power year with two sets of tie
reliability benefits assumptions. The results
are
262005-2006 Power Year Objective Capability
Values Assuming ISO Recommended HQICC Values (MW)
272004-2005 Power Year Objective Capability
Values (MW)
28 ISO-NE OC Recommendation
- ISO-NE recommends that the NEPOOL Objective
Capability for the Power Year commencing on June
1, 2005 and ending on May 31, 2006 be those
associated with assuming 2,000 MW of tie
reliability benefits.
29(No Transcript)
30 Appendix
- Examples of LOLE calculation
31(No Transcript)
32(No Transcript)
33Capacity Outage Calculation
Two Identical Units 100 MW RatingEquivalent
Forced Outage Rate 0.10
Assuming that the load is 100 MW, then the
probability of not being able to serve the load
is 0.01
34Capacity Outage Calculation (Contd)
Three Identical Units 50 MW RatingEquivalent
Forced Outage Rate 0.05
Assuming that the load is 100 MW, then the
probability of not being able to serve the load
is 0.00715 0.000125 0.00725
35Capacity Outage Calculation (Contd)
Four Identical Units 50 MW Rating Equivalent
Forced Outage Rate 0.05
Assuming that the load is 100 MW, then the
probability of not being able to serve the load
is 0.000475 0.00000625 0.0004813
36Questionsnow orpwong_at_iso-ne.comorteac_matters_at_
iso-ne.com