NEPOOL Objective Capability (Installed Capacity Requirement) For Power Year 2005/2006 - PowerPoint PPT Presentation

1 / 36
About This Presentation
Title:

NEPOOL Objective Capability (Installed Capacity Requirement) For Power Year 2005/2006

Description:

Best measure of reliability for all loading types (base, cycling, peaking, etc. ... Forced Outage Rates (EFORd) determined using combination of NERC Class Average ... – PowerPoint PPT presentation

Number of Views:43
Avg rating:3.0/5.0
Slides: 37
Provided by: iso6
Category:

less

Transcript and Presenter's Notes

Title: NEPOOL Objective Capability (Installed Capacity Requirement) For Power Year 2005/2006


1
NEPOOL Objective Capability (Installed Capacity
Requirement)For Power Year 2005/2006
  • Presentation to the
  • Joint ISO PAC/NEPOOL RC Meeting
  • February 2, 2005
  • Wyndham Hotel, Westborough MA

2
Background
  • NEPOOL Objective Capability (OC) is the amount of
    installed capacity that NE needs to meet the
    NEPOOL resource planning reliability criterion of
    1 day in 10 years disconnection of
    non-interruptible customers. This criterion takes
    into account
  • Possible levels of peak loads due to weather
    variations,
  • Impact of assumed generating unit performance,
    and
  • Possible load and capacity relief obtainable
    through the use ofISO-NE Operating Procedure no.
    4 Action During a Capacity Deficiency.

3
Background (Contd)
  • OC is established by NEPOOL on an annual basis
    one year at a time.
  • Power Supply Planning Committee reviews
    assumptions and develop OC scenario(s) for
    Reliability Committee (RC) consideration.
  • RC reviews the OC scenario(s) and votes a
    recommendation(s) for Participants Committee
    approval.

4
Background (Contd)
  • OC is calculated using the single area
    Westinghouse/ABB Capacity Model Program. Single
    area refers to the assumption that there is
    adequate transmission to deliver capacity where
    and when is needed. Simply said, all loads and
    generators are assumed to be connected to a
    single electric bus.

5
Background (Contd)
  • The Capacity Model uses probabilistic calculation
    that simulates the availability of system
    resources (taking into account each generating
    units assumed forced outages and maintenance
    requirements) to meet the expected load (taking
    into account possible variations due to weather).
    This calculation is often referred to as the
    Loss of Load Expectation (LOLE) calculation.

6
  • Assumptions
  • For 2005/06 OC Calculations

7
Assumptions
  • Loads
  • Capacity
  • Existing
  • Additions
  • Attrition
  • Purchases and Sales
  • Daily Cycle Hydro Ratings
  • ICAP Capable Load Response Program Assets
  • SWCT RFP
  • Unit Availability
  • Tie Benefits
  • Other OP-4 Load Relief

8
Loads
  • Based on CELT 2005 forecast
  • Weekly distributions represented with
  • Expected value (mean)
  • Standard deviation
  • Skewness
  • Based on short-run seasonal peak load forecast
  • Summer peak 26,355 MW
  • Winter peak 22,830 MW

9
Capacity
  • Existing Capacity
  • Based on 2005 CELT Data
  • Assets within January 2005 Seasonal Claimed
    Capability (SCC) Report
  • Summer Rating August 2004 SCC Report
  • Winter Rating January 2005 SCC Report
  • Units categorized as EMS SO units included
  • Energy Management System 30,516 MW (S) 32,878
    MW (W)
  • Settlement Only resources 238 MW (S) 313 MW
    (W)

10
Capacity
  • Capacity Additions
  • Ridgewood Generation (8.4 MW)
  • Kendall Steam 3 Reactivation (25 MW)
  • Kendall CT Reactivation (158 MW)
  • Capacity Attrition
  • No attrition assumed

11
Capacity
  • Purchases and Sales
  • Purchases and Sales as reported in 2004 CELT
    Report (453 MW)
  • Daily Cycle Hydro Ratings
  • 50 Percentile value of daily flows assumed with
    adjustment (59 MW in July) to OC.

12
Load Response Assumptions
  • ICAP Capable Load Response Program
  • All capacity listed as of January 1, 2005 as
    ready to respond enrolled in
  • Day-Ahead Demand Response Program
  • Real-Time Demand Response Program
  • Real-Time Profiled Response Program
  • Assets grouped by Program and Area
  • Assets assumed to have performance factors based
    on August 20, 2004 audit results and NERC Class
    Average EFORd values for known emergency
    generation.

13
Assumed MW from Load Response Program
EFOR values based on Aug. 20, 2004 audit results
and NERC Class average data
Program Load Zone MW Assumed in 05/06 OC Calculations MW Assumed in 05/06 OC Calculations Assumed EFOR () Assumed EFOR ()
RT 2-hour Demand Response ME 1.0 30.0
  NEMA 1.5 99.0
  WCMA 9.0 84.0
RT 30 Minute Demand Response CT 218.0 3.9
NEMA 3.0 37.0
 Profiled Response ME 76.0 100.0
  NEMA 1.4 7.45
VT 5.9 100.0
Total Total 315.8

14
Emergency Resources
  • SWCT RFP
  • Contracted SWCT RFP resources not currently
    enrolled in Real-Time Demand Response included
  • 218 MW total contracted for summer 2005

15
  • PSPC recommended using EFORd instead of EFOR to
    be consistent with EFORds application in the
    ICAP market and the UCAP rating for generating
    units.

16
EFORd Equation
Where
17
  • EFORd - Equivalent Demand Forced Outage Rate
  • ff - full f-factor
  • fp - partial f-factor
  • FOH - Full Forced Outage Hours
  • EFOH - Equivalent Full Forced Outage Hours Sum
    of all hours a unit was involved in an outage
    expressed as equivalent hours of full forced
    outage at its maximum net dependable capability
  • SH - Service Hours The time a unit is
    electrically connected to the system - Sum of all
    Unit Service Hours.
  • AH - Available Hours The time a unit is capable
    of producing energy, regardless of its capacity
    level -- Sum of all Service Hours Reserve
    Shutdown Hours Pumping Hours Synchronous
    Condensing Hours
  • RSH - Reserve Shutdown Hours The time a unit is
    available for service but not dispatched due to
    economic or other reasons

18
Equiv. Forced Outage Rate Demand (EFORd)
  • Interpretation
  • The probability that a unit will not meet
    itsdemand periods for generating requirements.
  • Best measure of reliability for all loading
    types(base, cycling, peaking, etc.)
  • Best measure of reliability for all unit
    types(fossil, nuclear, gas turbines, diesels,
    etc.)
  • For demand period measures and not for thefull
    24-hour clock.

19
Unit Availability Assumption
  • 5-year average EFORd modeled
  • Forced Outage Rates (EFORd) determined using
    combination of NERC Class Average EFORd data and
    available New England GADs data.
  • NERC Class Average used Jan00 Feb03
  • Calculated EFORd using GADs used Mar03 Dec 04
  • Since Dec 04 data is not yet available,Dec 03
    data is used for Dec 04.

20
Unit Availability
  • New England Nuclear units performance not
    correctly represented by NERC Class Average EFORd
  • For Nuclear units, used ISO-NE calculated Jan00
    through Feb03 EFOR and Mar03 through Dec04
    EFORd.
  • Since Dec 04 data is not yet available,Dec 03
    data is used for Dec 04.

21
Results of 60-Month Average
Unit Category Summer MW of System 05/06 Assumed WEFORd ()
Fossil 10,179 32.9 6.71
CC 11,040 35.7 6.03
Diesel 121 0.4 5.56
Jet 1,873 6.1 7.09
Nuclear 4,387 14.2 1.35
Hydro (Includes Pumped Storage) 3,340 10.8 3.80
Total System 30,940 100 5.41
22
Tie Reliability Benefits
  • Tie Reliability Benefits from Hydro-Quebec, New
    Brunswick, and New York are modeled in the
    Westinghouse Capacity Model as Resources
  • PSPC suggested two sets of tie benefits
    assumptions
  • 1,400 MW (summer values including HQICC)
  • 2,000 MW (summer values including HQICC)

23
Tie Reliability Benefits - HQICC
  • Hydro-Quebec Interconnection Capability Credits
    for 2005/06 are determined based on load and
    capacity data submitted to ISO-NE by Hydro-Quebec
    Distribution and Hydro-Quebec Production.
  • The monthly HQICC values recommendedby ISO-NE
    are
  • June through November, March through May 1,200
    MW
  • December through February 0 MW

24
OP-4 Load Relief
  • Load Relief values based on ISO-NE Operating
    Procedure No. 4 (OP-4)

2005-2006 Power Year OP-4 Load Relief (MW) 2005-2006 Power Year OP-4 Load Relief (MW) 2005-2006 Power Year OP-4 Load Relief (MW) 2005-2006 Power Year OP-4 Load Relief (MW) 2005-2006 Power Year OP-4 Load Relief (MW)
(A) (B) (C) (BC-A)
Minimum Operating Reserve OP-4 Actions 9 10 5 Voltage Reduction Total OP-4 Load Relief
June September 200 45 395 240
October - May 200 45 342 187
  • 5 Voltage Reduction is based on 1.5 of the
    seasonal peak load as determined by Spring
    Voltage Reduction Test Results

25
Tie Reliability Benefits Scenarios
  • The PSPC suggested calculating NEPOOL OC for
    2005/06 Power year with two sets of tie
    reliability benefits assumptions. The results
    are

26
2005-2006 Power Year Objective Capability
Values Assuming ISO Recommended HQICC Values (MW)
27
2004-2005 Power Year Objective Capability
Values (MW)
28
ISO-NE OC Recommendation
  • ISO-NE recommends that the NEPOOL Objective
    Capability for the Power Year commencing on June
    1, 2005 and ending on May 31, 2006 be those
    associated with assuming 2,000 MW of tie
    reliability benefits.

29
(No Transcript)
30
Appendix
  • Examples of LOLE calculation

31
(No Transcript)
32
(No Transcript)
33
Capacity Outage Calculation
Two Identical Units 100 MW RatingEquivalent
Forced Outage Rate 0.10
Assuming that the load is 100 MW, then the
probability of not being able to serve the load
is 0.01
34
Capacity Outage Calculation (Contd)
Three Identical Units 50 MW RatingEquivalent
Forced Outage Rate 0.05
Assuming that the load is 100 MW, then the
probability of not being able to serve the load
is 0.00715 0.000125 0.00725
35
Capacity Outage Calculation (Contd)
Four Identical Units 50 MW Rating Equivalent
Forced Outage Rate 0.05
Assuming that the load is 100 MW, then the
probability of not being able to serve the load
is 0.000475 0.00000625 0.0004813
36
Questionsnow orpwong_at_iso-ne.comorteac_matters_at_
iso-ne.com
Write a Comment
User Comments (0)
About PowerShow.com