Timeline. How Audit worked. PHMSA Expectations. What went well and not so well. Benefits of the Audit. Recommendations. 5. Audit Timeline. February 2006 - Pre-meeting ... – PowerPoint PPT presentation

Number of Views:19
Avg rating:3.0/5.0
Slides: 13
Provided by: elpas9
Category:

less

Transcript and Presenter's Notes

Title: Charlie Childs Pipeline Integrity Consultant


1
Charlie ChildsPipeline Integrity Consultant
  • SGA Web Conference Session 6 Audit Feedback
    from PHMSA
  • April 28, 2008

2
El Paso Corporation
the place to workthe neighbor to havethe
company to own
3
Asset Map
4
EPPG IMP Audit Experience Agenda
  • Timeline
  • How Audit worked
  • PHMSA Expectations
  • What went well and not so well
  • Benefits of the Audit
  • Recommendations

5
Audit Timeline
  • February 2006 - Pre-meeting
  • April May 2006 Audit (3 weeks)
  • August 2006 Meeting to discuss one specific
    issue
  • March 2007 Request for information and we
    provided updates to processes
  • July 2007 Proposed enforcement actions received
    from PHMSA
  • April 2008 Hearing
  • ?? Date for 2nd Hearing

6
How Audit worked
  • Protocol sections scheduled before hand
  • Operator presentation overview, before each
    major section
  • PHMSA followed Protocols
  • Covered processes
  • Vertical slice
  • PHMSA Caucuses
  • Exit issues each week
  • What you know at the end of the audit
  • Have an idea of the issues that were raised
  • Not know what issues are enforcement items
  • Not know if you answered all the issues raised
    during the audit some you will, some you wont

48
7
PHMSA Expectations
  • Documentation, documentation, documentation
  • Processes, processes, processes detailed
  • Individual inspectors will have their areas of
    expertise and interest
  • Knowledgeable individuals

48
8
What went well and not so well
  • What went well
  • Pre-audit preparation
  • Business like approach by both EPPG and PHMSA
  • Good rapport during the audit
  • PHMSA listened to our explanations and worked
    hard to understand our program
  • Time was well managed
  • What did not go as well
  • Long period of waiting in post audit process and
    little communication during this time
  • Not know what issues are enforcement items
  • Audit issues are written in generic protocol
    language not written to describe the specific
    issue discussed in the audit

48
9
Benefits of the Audit
  • Preparation for audit improved processes and
    emphasized importance of IMP
  • Improvement to IMP Processes identified during
    Audit
  • Thorough audit
  • Good feedback on importance of solid and detailed
    documentation of day to day OM activities

48
10
Recommendations
  • Before Audit
  • Tie your manual to the protocol sections
  • Know the protocols, FAQs, and your processes
  • Take time to complete a thorough pre-inspection
    form
  • Practice/Mock audit
  • Attitude - open to improvement, ready to listen
  • Management participation and support

48
11
Recommendations
  • Clear and thorough presentation of your program
    overview and for each protocol
  • Involve SMEs
  • You will have disagreements
  • Justify your procedures technically and based on
    the regulations
  • Stay open for improvement
  • Stand up for what is right in the right way,
    including if PHMSA is working outside the
    regulations

48
12
Charlie ChildsPipeline Integrity Consultant
  • SGA Web Conference Session 6 Audit Feedback
    from PHMSA
  • April 28, 2008