Title: Tritium Removal Facility


1
Tritium Removal Facility CNE Cernavoda
ROMANIA Present status and perspectives
The 14-th Conference Progress in Cryogenics and
Isotopes Separation 29-31 OCTOBER,
2008 CALIMANESTI - CACIULATA, VALCEA

2
Short history
  • 2006/2007 final approval for pre and
    feasibility study rev 3
  • Technology adopted LPCE CD similar in
    Wolsung, Korea and ICIT, Romania
  • Proposed 5 year project for construction
    2007-2012
  • Solution adopted by CNE Cernavoda 2 year design
    phase
  • MPA no 613 issued by CNE Cernavoda and approved
    by CNCAN in August 2007
  • Contract signed in December 2007

3
Design
4
Location of CTRF
5
Participants
  • Initial, at beginning of contract
  • ICSI
  • SITON
  • AECL Canada
  • CELIN SA
  • ISTECH
  • All proposed companies together covers all
    specialties of project

6
Participants
  • Today, contract in force
  • ICSI technology, licensing support
  • SITON technology, safety, construction,
    licensing, electrical instrumentation
  • CELIN - electrical instrumentation,
    construction
  • ISTECH technology, licensing support
  • CEPSTRA GROUP support for environmental
    licensing

7
Participants
  • New companies will be involved in order to
    fulfill the project objectives and schedule
  • KRAFTANLAGEN GmbH, Germany
  • AECL Canada

8
Project organization
9
Licensing organization
Resolved
10
Milestones
  • Background
  • 2 year design contract
  • Licensing process 3 licenses has to be obtained
    (location, construct construction)
  • Technical project as support for construction
    license
  • Detailed design project of CTRF

11
Milestones
  • Technical project part 1 December 2008
  • Technical project part 2 March 2009
  • Final review of TP and initial SAR April/May
    2009
  • PSAR October 2009
  • License for construction/construct of CTRF
    December 2009
  • Detailed design of CTRF (DDRP) in order to close
    MPA December 2009

12
Schedule
13
Issues regarding CTRF project
  • Change of participants
  • AECL is not allowed at this moment to provide
    support because of bilateral agreement between
    Romania and Canada or EURATOM Canada
  • Interface with CNE Cernavoda
  • Hard communication
  • Delays in answering
  • ICSI take decision to open an office in CNE
    Cernavoda in order to increase information
    exchange
  • Changed solutions
  • There are some identified changes between
    feasibility study and actual phase regarding the
    links with U1 (electrical, construction)
    increase the number of systems

14
Results
  • Licensing
  • Initial documents for starting licensing process
    were issued
  • Code and standards, LBD, list of CTRF systems
    after FS, system classification list
  • CU license (from local authorities) approved in
    October 2008 after 3 month
  • Environment initial documents
  • Continuous discussion with CNCAN
  • ISAR and PSAR content agreed with CNCAN

15
Results
  • Technology
  • All technological or auxiliary systems starts
  • LPCE system final configuration
  • CD system final configuration including
    solution for helium refrigeration unit
  • Interface systems (HWFS HWPS) final
    configuration. Connecting points with U1 systems
    identified
  • Others (HVAC, ADS, TRS, TGHSS, VTMS) ongoing to
    finalize solution
  • Conceptual project in development in order to
    review the feasibility study

16
Results
  • Construction
  • Building freeze in October 2008
  • Changed solution as requested by CNE Cernavoda
    panels instead concrete for walls
  • Location of systems and main equipment
  • Seismically solution for CTRF building developed
    by SITON low cost for equipment
  • Technical channel between service building
    there is additional work, will be 2 TC, and we do
    not have an agreement about the link with U2

17
Building
18
Building
CD System
ADS
TRS
L4
L3
L2
L1
L0
B1
LPCE System
HVAC Shaft
Heating System
Tritium Storage
Tritiated water holding tank system
19
Perspectives
  • Technical project, licensing process and detailed
    design for CTRF can be finalized on schedule
  • Delays expected in licensing process
  • As result of TP CTRF construction costs can
    increase take in account market prices CTRF
    price will be adjusted
  • Some issues regarding heavy water management
    U1/U2 can affect CTRF project and in
    perspective the construction of facility CNE
    Cernavoda has to define how the CTRF will serve
    U1/U2
  • Tritium aspects a strategy has to be developed

20
Perspectives
Korea Wolsung TRF
Canada Darlington TRF
European Union ICIT TRF, Romania CTRF, Romania
TRITIUM REMOVAL FACILITIES MAP
21
Tritium Removal Facilities in Romania
ICSI TRF research training
CERNAVODA TRF commercial
22
Tritium inventory in the world
? 2.5 Kg/year tritium in 20 CANDU units (Ontario
OPG) ? Tritium removal facility in Wolsung (4
CANDU units) in operation ? Cernavoda TRF for U1
U2 ?
23
Recovery of investment
  • Tritium price on market 23 Euro/Ci
  • At start of Cernavoda tritium removal facility
    tritium activity will be 54 Ci/kg (if CTRF
    proceed as schedule in FS)
  • Scope of CTRF target of 10 Ci/kg in first two
    years can be stored 107 Ci meaning 23 107
    Euro
  • After target achieved can be recovered 4.5
    Ci/kg per year tritium production per year and
    unit of 106 Ci equivalent with 23 106
    Euro/unit/year

24
Conclusions
  • Romanian and international technologies applied
    for CTRF
  • Great effort !
  • CTRF schedule can be adjusted
  • Results from project skills developed inside
    project companies in perspectives of ITER
    construction
  • Romanian industry can be prepared for CTRF ITER
    construction
  • In perspective CTRF has two major advantages
  • CNE Cernavoda will be major player on European
    tritium market. Romania is EU member!
  • CTRF experience can be used for ITER
  • As things going in ITER project, CTRF will be
    build before ITER, so contracts related to
    tritium for ITER should be in place next years

25