Title: French Engineering, LLC
1Work Zone Safety and Mobility Traffic Analysis
and Impacts
- French Engineering, LLC
- Greenhorne OMara, Inc.
- Pennsylvania Department of Transportation
- Bureau of Highway Safety and Traffic Engineering
- October 27, 2009
2Agenda
- Background Information
- DAWB Theory and Application to Freeway /
Interstate Projects - Questions on Traffic Analysis
- Lessons Learned / Group Discussion
- Course Wrap Up
- Text questions throughout
3Background Information
4State Survey and Background Work
- Five States Contacted
- Florida, Maryland, Michigan, Ohio, and Virginia
- Spreadsheets provided by 4 of 5
- Key Findings
- Quickzone only used for largest projects
- All states developed their own spreadsheets
- Ohio spreadsheet was foundation of the one
developed for PA - Estimating work zone capacity is usually weakest
link in analysis - Borrowed some FL methodologies for capacity
estimation
5Overview of Delay Computation Methodology
- Identify Critical Activities from a Traffic
Capacity / Bottleneck Point of View - Develop Approach Based on Available Tools, Data,
and Need for Multi-Period Analysis - Execute Approach
6Importance of Analysis Period
- Undersaturated, Uncongested Scenarios
- Single Period of Analysis May Be Sufficient
- Available Tools are Many
- Oversaturated, Congested Scenarios
- Multi-Period Analysis May Be Required
- DAWB Spreadsheets In Conjunction with Other
Programs - Other Programs Exclusively if Precision is
Required
7Delay Analysis Workbook (DAWB) Theory and
Application
P\bhste_shared\workzones\WZ traffic analysis
8Overview of DAWB
- 6 Spreadsheets Contained Within
- Capacity Estimation
- Bottleneck Analysis
- Quick Bottleneck Analysis
- Existing Bottleneck Analysis
- Two-Way One-Lane Not to be discussed today
- Detours Not to be discussed today
- Can Be Used as Standalone or With Other Programs
- Key is Estimate of Capacity and source of demand
information - Designed for Easy Multi-Period Analysis
9Capacity Estimation Spreadsheet
10Overview
- Tools and science available to estimate work zone
capacity are expected to improve in the future - Spreadsheet is designed to provide the user with
some guidance for the selection of a capacity for
the work zone - Three tools provided
- Freeways
- Two-Way One-Lane Work Zones
- Other Facilities
- Only Freeways will be discussed today
- Other tools (or experience) may provide better
estimates
11Freeways (HCM Chapter 22)
- Short-Term Work Zones
- Capacity (1600 I) fhv N R
- Where
- Capacity adjusted mainline capacity (vph)
- I adjustment factor for type, intensity, and
location of work activity (ranges from 160 to
-160 pcphpl) - R adjustment for on-ramps in the taper or
within 500-ft downstream of the beginning of the
full lane closure - R should be made equal to the ramp volume, not to
exceed half the capacity of one lane - Nnumber of lanes open through the short-term
work zone - fhv heavy vehicle factor
12Freeways (HCM Chapter 22)
- Long-Term Work Zones
- Summary of Capacity Values for Long-Term Freeway
Work Zones
Notes If crossovers are used, the capacity is
close to the value 1,550 vphpl If no crossover
is needed, but only a merge down to a single
lane, the value averages to 1,750 vph
13Freeways (HCM Chapter 22)
- Lane Width Considerations
- Capacity decreases 9 when lane widths drop from
11-ft to 10-ft - Capacity decreases 14 when lane widths drop from
11-ft to 9-ft - Capacity decreases could be greater with the
influence of trucks
14Example
- Short-term freeway closure with no ramps but a
very active work zone. One (of two) lanes to
remain open. Level terrain and 5 trucks.
15Example Solution Hand Calcs
15
- Solution (HCM)
- Capacity (1600 I) fhv N R
- I -160 R 0 ET 1.5 PT 5 N1
- fhv 1 / 10.05(1.5 1) 0.976
- Capacity (1600 -160) 0.976 1 0
- Capacity 1405 vph, rounded to 1400 vph
16Example Solution in DAWB
16
17Quick Bottleneck Analysis Spreadsheet
USE BOTH LANES TO MERGE POINT
18Quick Bottleneck Overview
- Intended for use when
- Only AADT and work zone capacity are known
- Work zone capacity is somewhat constant
throughout the day - Daily Commuter Route
- Performs queuing and delay analysis based on
cumulative arrivals and departures versus time - If more volume information is known, weekend
peaks are critical, or capacity is highly
variable, use Bottleneck Analysis Spreadsheet.
19Queue / Delay Model
20Spreadsheet Inputs
- One Way Work Zone Capacity
- Average Annual Daily Traffic (AADT)
- Percent of Peak Period (gt1000 vph) Traffic
Diverted () - Number of Lanes for Queued Vehicles (lanes)
- Percent Trucks (Daily)
- Traffic Pattern Group (TPG) (Number 1 to 10)
- http//www.dot7.state.pa.us/itms/main.htm
- Inbound 1, Outbound 2, Neutral 3
21Spreadsheet Outputs
- Number and Duration of 15-Minute Delay Episodes
- Number and Duration of 30-Minute Delay Episodes
- Total Daily Delay
- Queue Length (in vehicles and miles) at the End
of Each Hour - Delay for the Last Vehicle of Each Hour
22Example 1Analysis of Freeway Lane Closure /
Restricted Typical Section Using AADT and TPG
Information
23Overview of Example
- One of the two existing lanes is to be closed on
I-70 / I-79 Eastbound in Washington County
upstream of the south junction - Perform quick analysis using information from
PennDOT ITMS website and minimal other
information - Use Capacity Estimation and Quick Bottleneck
Analysis spreadsheets
24Location Map
PROJECT LOCATION
25PennDOT Video Log
http//www.dot7.state.pa.us/ividlog/video_locate.a
sp
26PennDOT ITMS Information
http//www.dot7.state.pa.us/itms/main.htm
27Capacity Estimation
28Quick Bottleneck Analysis Inputs
29Quick Bottleneck Analysis Outputs
30Quick Bottleneck Analysis Outputs (Continued)
30
3131
32Example Conclusion
- Proposed closure would have sustained 15-minute
delays lasting more than two-hours as well as
30-minute delays - Significant Project
- Remember
- Volume estimation off hourly distributions from
Table 350 in Traffic Data Report. Update to
2008 edition! - Actual volumes will likely provide better results.
33Bottleneck Analysis Spreadsheet
34Overview
- Use when
- Actual hourly volumes are available
- Capacity varies by the time of day
- Facility is not an existing bottleneck
- Outputs and computations are identical to those
in Quick Bottleneck Analysis Spreadsheet - Inputs are same except
- One-Way Annual Average Daily Traffic (AADT),
Traffic Pattern Group and Direction, and One-Way
Capacity are omitted - Hourly volumes and capacities are directly input
35Example 2I-70 Fulton CountySingle Lane Closure
36Overview of Example
- I-70 Eastbound between Breezewood and Maryland
- Long project 14 miles Crosses mountain ridge
and has three interchanges and a rest area - One week of hourly traffic data collected in
August 2008 available - Traffic queue and volume information from similar
lane closures on the westbound side
37Location Map
37
Project Location
38Key Issues
38
- Traffic peaks on the weekends. Average weekdays
are significantly different from Friday through
Sunday, and are not critical. - Estimation of capacity from similar work on
westbound side. - Queuing and delay expected based on experience in
westbound direction.
39Traffic Volumes
39
Volumes Estimated from AADT TPG
Actual Sunday Volumes
Actual Friday Volumes
40Hourly Traffic Volumes
40
41Estimation of Capacity
41
- EB and WB traffic was converted from vehicles
to passenger car equivalents to account for
differences in grade and truck . - Known WB queue was 2 miles in the Friday
afternoon peak. - Actual WB PCE volumes were input in Bottleneck
Spreadsheet. - Capacity adjusted until known queue length
resulted. - Resulting capacity was 1300 PCE / hour
- EB analysis was then conducted using PCE volumes
instead of actual volumes
4242
Spreadsheet / Analysis of Westbound Direction For
Determining Capacity
1300 PCE Capacity
2 mile backup
43Eastbound Analysis SpreadsheetsFridaySaturdayS
unday
4444
FRIDAY ANALYSIS
No delays or queues expected
PCE Volumes Input
1300 PCE Capacity
45SATURDAY ANALYSIS
Again, no delays or queues expected
4646
SUNDAY ANALYSIS
Major Delays and Queues Expected
47Example Conclusions
- No delays on days Monday through Thursday
- Friday had delays in the westbound direction but
not eastbound - Eastbound had significant delays on Sunday
- For an interstate / intercity route summertime
weekend traffic data are key
48Example 3Oversaturated Ramp to a Freeway Work
ZoneVariable Capacity Problem
48
49Overview of Example
49
- An interchange lies within a freeway work zone
that is oversaturated. The off-ramp is upstream
of the on-ramp. - The interchange volumes are shown on next slide.
The off-ramp volume will be the capacity for the
on-ramp traffic flow. - Perform a variable capacity problem using the
"Bottleneck Analysis" worksheet
50Interchange Traffic Volumes
50
51Bottleneck Spreadsheet Inputs
51
52Delay Outputs
52
53Example Conclusion
53
- Significant delay on the on-ramp.
- There are individual delays gt 50 min
- Delays gt30 min sustained for more than two hours
- The delay on the ramp could be greater than the
delay on the mainline at the entrance to the work
zone. - Variable capacity problem also applies to work
zone time restrictions
54Existing Bottleneck Analysis Spreadsheet
Squirrel Hill Tunnels, Pittsburgh
55Overview
- Modification of Bottleneck Analysis spreadsheet
- Need hourly volume and capacities are available
- Also need normal capacities, which are presumed
to result in some existing over-capacity
conditions - Outputs and overall methodology are the same as
the Bottleneck Analysis spreadsheet except
delay measures focus on added delay relative to
existing delay
56Area of Spreadsheet to Input Normal Capacity
57I-70 Sunday Example Data with Arbitrary Normal
Capacity
Delays are slightly less than before since some
is attributed to existing bottleneck
Normal Capacity input here
58Traffic Analysis QuestionsDiscussion
58
59Lessons Learned
60From Personal Experience
- Differentiate between commuter traffic patterns
and interstate / intercity patterns - Importance of representative traffic data
- Capacity estimation from observation of similar
projects
61Group Discussion of Lessons Learned
- Central Office
- District
- Consultant
62Final Questions Wrap - Up