Title: SuperJANET5 RNO installation guide


1
SuperJANET5 RNO installation guide
  • Roland Trice
  • SuperJANET 5 Rollout Manager

2
RNEP Requirements paper
  • E-mailed to MANS list
  • Describes installation details
  • Readiness certificate
  • Does not need signing
  • E-mail to Verizon (Eddie Holloway)
  • Electrical test certificate
  • Will need a signature
  • Some copies available today

3
Racks
  • Verizon will not re-use existing racks
  • Insufficient battery capacity
  • Risk of service disruption
  • Installation and decommissioning

4
Standard Rack Build
  • New rack 600mm square 2200mm tall
  • Unless physically impossible
  • Four hour battery stack
  • Unless specifically declined
  • Cable access from beneath the floor
  • Unless there is no false floor
  • New fibre will be installed at both RNEPs

5
Power
  • RNEP to provide 16 amp commando socket
  • 20 amp type-D MCB at the EDU
  • Ensures breakers in the rack trip before those in
    the EDU

IP44SPLASHPROOF200 - 250V50 - 60 Hz16
AMPS MK Electric Product code K9201 BLU
6
Power
  • Building earth bonding point
  • Rack will be earthed to this point
  • RNEP must provide an electrical test certificate
  • Conformant to 16th edition of IEE regulations
  • Good general level of lighting

7
Standard Rack Build
  • A fully loaded cabinet weighs 211Kg,
  • Cabinet shell and sides 110 KgEaton APS 3
    rectifier 35 Kg4 batteries 50
    KgCiena CN4200 10.5 KgOptical patch
    panel 5 Kg

8
CN 4200 environmental specs
  • Ambient Temperature 5o C to 50o C
  • Relative Humidity 5 to 85 (non-condensing)
  • Cooling available for maximum 375 W
  • Power consumption between 5-11 amps

9
CN 4200 optical presentation
  • All SDH links present as
  • Single-mode fibre
  • 1330 nm
  • Short Reach
  • FC/PC connectors
  • All GE links present as
  • Multi-mode fibre
  • 850 nm
  • SC/PC connectors

10
Connections
  • Production IP service
  • 10 Gbit/s or 2.5 Gbit/s SDH
  • Other Production Services
  • GE
  • UKLight equipment to UKLight Core
  • 10 Gbit/s SDH
  • Other research bandwidth
  • GE

11
Other equipment
  • Some RNEPs will continue to house other JANET
    equipment
  • UKLight Metro Director or 3600
  • Small services router
  • Servers
  • OOB router
  • Power management system
  • One or two RNEPs may gain new kit
  • Need to rationalise this equipment

12
Other equipment
  • Please tell me about the JANET kit you have
  • Where it is
  • How many racks it is in
  • How much space it occupies within the racks
  • Rack layouts would be really good ?
  • Aim to minimise the space we use
  • NOSC will liaise with individual RNOs

13
Post installation
  • Link acceptance testing
  • Will be performed by the NOSC
  • Will test to loopback at R-PoP
  • Verizon will leave all active circuits looped
    back
  • Loopback cable useful for future testing or new
    provision
  • QA by Verizon and RNO after installation
  • Your chance to ensure your facility is left as
    you want it

14
R-PoP issues
  • Site surveys
  • Verizon will be arranging for Feb/March
  • Verizon will compile site report for RNO UKERNA
  • Wayleaves
  • THE major hassle in SJ4
  • Please warm up your estates people now
  • Problems (Great Crested Newts)
  • Tell me as soon as possible

15
The culprit
16
Questions?