Title: Construction Practices for Rigid and Flexible Pipes
1Construction Practices for Rigid and Flexible
Pipes
2Pipe Backfill Detail (4 ft. or less Below
Proposed Base)
3Pipe Backfill Detail (gt 4 ft. Below Proposed
Base)
4Notes
- The reinforcement fabric shall be rolled out
parallel to the centerline of the road and shall
be placed as shown in the details. The fabric
shall be placed so that it is taut and the fabric
shall be pinned on the 1.51 and 201 transition
using 6 minimum pins. The pins shall be placed
at a 15 spacing along all edges and at all
corners prior to placing fill on the fabric. The
reinforcement fabric shall be measured by the
actual surface area covered to the nearest square
yard. No allowance will be made for overlaps. - The aggregate base course Cl 3 or Cl 5 backfill
shall be compacted in layers not to exceed 6
inches using a hand-held vibratory plate
compactor or a hand-held mechanical tamper to the
top of the pipe and within a distance of 2 feet
on either side of the pipe. - This standard corresponds to new/replaced
centerline pipes only (including ramps). It does
not include pipes in approaches.
5Problems Encountered with Centerline Pipes
- Poor Compaction Around Pipe
- Heaving of Shallow Pipes Due to Frost Action
- 201 transitions are not installed properly
- R1 Reinforcement fabric is not installed properly
- Pipes in a submerged condition should be
dewatered prior to backfilling to allow adequate
compaction
6Pipe Compaction
7Backfilling Around Pipes
Cannot overstate the importance of maintaining
lift thickness and using proper compaction
equipment.
8Compaction Equipment
9(No Transcript)
10Settlement Over Culverts
11Settlement Over Culverts
12Heaving of Large Structural Plate Pipe I-94
13Use of High Density Foam to Limit Frost
Penetration
14Compaction and Box Culverts
15Heave Over Shallow Box Culverts Pipes
16Construction Alternatives for Rigid and Flexible
Pipe
- 2007 Construction Conference Annual Meeting
- March 2007
- John Wolf
- NDDOT Materials Research Division
17Pipe Alternatives being used by the NDDOT
- Polymer Coated Corrugated Steel Pipe
- Under consideration as an allowable alternative
for centerline culverts. - Specified through the use of a Special Provision.
- Currently used by a number of DOTs as an
allowable pipe alternative to RCP. - High Density Polyethylene (plastic) Pipe
- Used as an allowable pipe alternative for
approach pipe conduit. Also under consideration
for centerline culverts. - Included on NDDOT Standard Drawings D-714-14 and
D-714-17. - Currently used by a number of DOTs as an
allowable pipe alternative for culverts and storm
drains.
18Benefits of Rigid and Flexible Pipe
- Rigid Pipe (i.e. RCP)
- Very durable against almost all conditions.
- Requires low minimum fills for live loading.
- Does not rely as heavily on high levels of
compaction for structural support. However,
adequate compaction is still needed to prevent
settlement and some structural support. - Flexible Pipe (i.e. CMP and HDPE pipe)
- Reduced material and installation costs.
- Material weight is greatly reduced.
- Reduced number of sections and joints.
- Utilizes engineering properties of supporting
soils. - Coatings and material selection can provide
excellent service life in the proper application.
19Load Distribution of Rigid and Flexible Pipe
- Rigid pipe transfers most of the pipe load
through the pipe walls to the pipe bedding.
Minimal deflections (2 or less). - Flexible pipe supports the pipe load with both
the pipe walls and the surrounding soil envelope.
Some deflection is allowed.
20Background on Polymer Coated CSP
- Installations dating back over 30 yrs
- Used by an expanding number of DOTs
- Montana, California, Nebraska
- KLJ has used coated pipe on county projects for
nearly 20 years. - Completed NDDOT Projects
- NH-7-002(057)033 in 2006
- NH-7-002(055)043 in 2006
- NH-2-281(026)030 in 2006
- IM-5-094(034)053 in 2006
- Hwy 16 S of Golva in 2003
- Upcoming Projects
- AC-TIP-5-012(030)046
- HPP-TES-1-804(023)072
21What do we want to look for?
- Padded spacers used during Transport.
- Pipe secured and handled with straps or padded
equipment. (NO CHAINS!) - Repair any damaged coating prior to installation
with manufacturer provided coating material. - Trench is shaped to a height deep enough to cover
the pipe and the minimum fill. - Make sure joints are tightly secured with
connection bands coated with polymer coating. - Compact aggregate backfill in 6 lifts with
vibratory compactors.
22Transporting Handling
- Padded Spacers used to separate pipe.
- Secured and handled using nylon straps.
23Damaged Coating
- Damage can be caused by shipping and unloading.
- Unloading should be done under the
supervision NDDOT inspector. - When handled according to the SP procedure,
significantly less coating damage was identified.
24Repair material and procedure
- Repair procedure are identified in the SP for
Polymer coated CSP. - Repair material is provided by the pipe
manufacturer. - Repair material can be applied using a paint
brush and requires minimal set time before the
product can be handled (less than 5 min).
25Trench Installation
- Trench should be constructed according to
approach pipe detail. - For pipes installed before the roadway
embankment has been placed, embankment should be
placed at the location of the pipe prior to the
trench excavation.
26Placing the Pipe
27Compaction
Vibratory compaction in 6 lift thicknesses. Well
compacted fill around the pipe helps to support
the pipe load. Well compacted material reduces
settlement and deflection in the pipe.
28Compaction (continued)
- Fill directly over the pipe should be free of
any rocks that may cause point loading on the
pipe. - Minimum fill height is 12 for AASHTO H-25
loading. - Live loads for construction traffic shall be in
accordance with the manufacturers recommendation.
29Minimum Cover for Flexible Pipe Under Temporary
Loading
- Construction vehicles sometimes exceed design
loads, and warrant a temporary live load
consideration. - Mounding and compacting additional cover over the
pipe may be necessary during construction in
situations where pipe has little cover. - The Modern Sewer Design, Fourth Edition gives the
following guidelines for min cover requirements
assuming the AASHTO H-25 load distribution - 1 foot for vehicles between 0 and 30 tons
- 2 feet for vehicles between 30 and 60 tons
- 3 feet or more for vehicles over 60 tons
30Finished Installation
31High Density Polyethylene (HDPE) Pipe
32- PE pipe has been used as a liner for
rehabilitated culverts. - Flowable fill has been used in some urban areas
to limit trench size and reduce the need for
compaction. - HDPE is being used by city municipalities in
North Dakota. - HDPE was estimated to save 20 to 30 over RCP on
a recent Bismarck city project.
33Bennifits of HDPE Pipe
- Meets requirements for AASHTO H-25 loads with a
12 inch min cover with proper backfill material
and compaction. - Reduced installation time and material cost.
- Withstands aggressive environments.
- Becoming increasingly used and available locally.
- Improved hydraulic characteristics.
- Very light and easy to handle. Does not require
special equipment to install.
34Construction Considerations for HDPE Pipe
- HDPE pipe requires trench installation.
Embankment shall be placed to the top of the pipe
zone prior to installation. - Aggregate backfill shall be used around the pipe
according to D-714-14. - The 6 aggregate bedding shall be loosely
compacted to allow for pipe seating. - When live loads are present, minimum cover shall
be as determined by the manufacturers
recommendations. - Use corrugated steel end sections one size larger
then the specified pipe (common Industry
practice). - Mandrel testing shall be performed by the
contractor under the supervision of an engineer
to check for 5 deflections in accordance to
standard 714.03 A.9.
Pipe Conduit Detail D-714-14
35Summary
- Cost savings of Polymeric CSP are evident.
- Savings of 17 to 53 of RCP prices were seen in
the 2006 projects. - An average cost savings of 34 of the project bid
price for RCP. - The saving on IM-5-094(034)053 based on 2005
average bid price for 1210 feet of storm drain
was over 140,000. - Material costs and alternative bids will help
reduce the bid price. - Flexible pipe are structurally capable of
performing as centerline culverts when the design
requirements are followed. - Flexible pipe can be installed with smaller
equipment and in less time than RCP.
36Questions?
John Wolf Materials Research North Dakota
DOT 701-328-6915 jowolf_at_nd.gov Sources Modern
Sewer Design, Fourth Edition 1999. Published by
the American Iron and Steel Institute