Title: Corps Expectations for Constructing
 1Corps Expectations for Constructing
- Masters Level Tips for Success
2MILCON Transformation
- Timeliness 
- Drastic improvements needed 
- Cost 
- Customers want reductions based upon budgetary 
 constraints (design to 70 PA)
- Quality 
- Generally speaking, customers are pleased
3Feedback to USACE
- Corps wants input from members of the Architect / 
 Engineer and Construction industry regarding best
 practices via
- NSPE Professional Engineers in Construction (PEC) 
 Community Website
- Knowledge Forum for contract administration
4Quality
- Our metrics tend to focus on time / schedule 
 which can be symptomatic of quality.
- ASCE Manual 73 Quality in the Constructed 
 Project defines quality as the fulfillment of
 project responsibilities stated by the designer,
 professional, and constructor.
5Responsibilities / Requirements
- Responsibilities are tasks expected to be 
 performed as specified by contractual agreement.
- Requirements are what a team member expects or 
 needs to receive during and after participation
 in a project.
6Quality
- Quality hinges on the degree to which the 
 requirements of project participants are met.
- Focus on practices and procedures that encourage 
 participants to express their requirements with
 clarity.
7Contracting Strategy
- Influences composition and organization of the 
 construction team.
- The responsibilities of the constructor and the 
 owner.
- The participation of qualified personnel. 
- Procedures for enforcing contract terms and 
 conditions.
8Contracting Strategy
- Best-Value Procurement 
- Evaluate proposals (other than cost) 
- Past performance 
- Key personnel 
- Contractors approach to managing quality / 
 schedule / cost
- Team Experience (Prime and Subcontractor)
9Certification and Staffing
- CQC personnel must be certified through a course 
 titled Construction Quality Management for
 Contractors.
- Specification 01451 requires supplemental CQC 
 personnel that must be directly employed by the
 prime contractor and have no other duties but
 quality control.
10QCS
- Specification Section 01312 requires the use of a 
 Corps provided comprehensive construction
 management software for the expedient and
 effective management of quality on construction
 contracts.
11Timeliness
- Schedule is a readiness issue. 
- For reference on time means all work complies 
 with the approved plans and specifications (no
 deficiencies) on the contract completion date.
- BOD  CCD  No Deficiencies!
12Why Improve?
- If you cannot execute on schedule, execute 
 earlier!
13Goals (NTP to BOD)
- 365 days for PA lt 5M 
- 540 days for PA between 5M and 20M 
- 730 days for PA gt 20M
14Managing Schedules
- ECB No 2002-32  Construction Contract Durations 
 Schedule Slippage
- Best value selection based upon experience, 
 management and past performance (schedule).
- Must evaluate the impact of changes on Critical 
 Path.
- Prioritize and use contingencies to maintain 
 original schedule (accelerate).
1510-Steps
Step-by-step process for timely completion 
utilizing proactive schedule management 
 16Step 1
- ACO Must assure necessary contract requirements 
 are included in Enhanced Specification 01320
- The Standard UFGS Guide Specification 01320A has 
 been enhanced and is to be edited and submitted
 with each BCOE review on all projects requiring a
 NAS Schedule.
- Purpose Provide Resident Engineers, PEs, QARs 
 and Contract Administration Employees an enhanced
 guide specification to improve our performance in
 timely project turnover.
17Step 2
- Prime Contractor Must prepare a reasonable 
 initial (baseline) schedule meeting 4-tests.
- Logical Sequence of the Critical Path (NTP to 
 CCD)
- Utilize the Total Float Sort 
- Review the Critical Path Work Activities for 
 logical sequence
- Earning Curve (cash flow) Evaluation 
- Compare Scheduled Progress to Recommended 
 Progress
- Manpower on the site related to  of duration 
 used
- Utilize NASA Projector 
- Compare rule-of-thumb to Schedule Workers per day 
- Milestone Complete as of  of duration used 
18Total Float Sort
- List of activities showing time available to the 
 critical path or to the completion of the project.
19Milestone Sort
- Listing of project milestones that represent the 
 end of a series of related activities or an
 accomplishment in the course of a project.
20Earning Curve 
 21NASA Earnings Projector 
 22NASA Earnings Projector 
 23Manpower Resource Plot 
 24Milestone/Completion Duration
- Structure Complete (36) 
- Roof Complete (44) 
- Building Dry-In (48) 
- Interior Walls (59) 
- Plumbing Complete (80) 
- HVAC Ductwork (89) 
- CQC Inspection of Entire Facility (93) 
- Prefinal Inspection (98)
25Step 3
- ACO must express serious and sincere interest and 
 commitment at the preconstruction conference in
 the use of the NAS Schedule by the contractor for
 planning control of all of the work activities in
 the contract throughout the entire contract
 duration.
- The Contractors home office, subcontractors and 
 field superintendent must also express their
 sincere interest and commitment to the meaningful
 preparation and use of the NAS Schedule through
 the entire contract at the preconstruction
 conference.
26Managing Schedules
- Recommendations 
- Develop Challenging duration goals and post the 
 dates !
- Inspect what you Expect ! 
- Demand complianceTrack it ! 
27Step 4
- The Contractor (Subcontractors) and the 
 Government must perform a reasonable and
 meaningful monthly evaluation of the updated NAS
 Schedule  to include review of the Contractors
 Narrative Report and plans for corrective actions
 if needed during the following month.
- ACO must require and updated NAS Schedule 
 evaluation meeting with the Contractor and
 Scheduler to evaluate progress on critical path
 milestones, trends, and actual start and finish
 dates to determine if contractor is following the
 NAS Schedule and that Schedule is still
 reasonable.
28Narrative Report
- The contractor should provide a comprehensive and 
 meaningful narrative report with the preliminary,
 initial NAS submittals and all monthly updates.
-  The narrative report should be reviewed by the 
 government representative prior to scheduling the
 second monthly progress meeting with the
 contractor to perform a joint analysis and
 evaluation of the updated NAS schedule.
29Narrative Includes
- Abstract  is / is not on schedule 
- Critical Path  list events 
- Milestones  that must complete this month 
- Discussion 
- Status information 
- Crew Size 
- Activities that need to be pushed 
- List of phases in operation in coming weeks
30Sample Narrative 
 31Milestone Report
- The purpose of the schedule, updates, and 
 analysis is to forecast probable effects on the
 completion date factoring in happenings that have
 occurred to date.
- The theory is  if we do not change our current 
 work plan, this is what will probably occur.
32Step 5
- ACO Must require the Project Engineer and the 
 Superintendent to jointly input (actual start and
 finish dates) data into the LS-AS / LF-AF NAS
 sort weekly during the weekly coordination
 meeting and to monitor the scheduled late start
 and late finish dates as compared to the actual
 start and finish dates observed during each month.
33Late Start / Late Finish Sort
- Created from the Monthly NAS Schedule Update. 
- Excellent Tool for continually monitoring monthly 
 progress.
- A must for determining time impact resulting from 
 contract changes.
34Using the LS / LF Sort
- Must use latest updated NAS (including all mods 
 with time and weather mods).
- LS Dates in chronological order from NTP to CCD. 
- Actual Start  Finish Dates are indicated and 
 compared to the scheduled LS / LF dates  to note
 trends (falling behind).
35Using the LS / LF Sort
- PE  Superintendent must note the float for each 
 activity to identify the critical path.
- PE  Superintendent must agree on the actual 
 start and finish dates. Dates must be entered in
 the sort.
- PE  Superintendent note (if activity is late) 
 and take appropriate action.
36Step 6
- ACO Withhold 10 retainage on progress payments 
 when the NAS schedule float sort indicates any
 negative float and continue until there is 0
 negative float.
37Step 7
- ACO must require the contractor to prepare a 
 supplemental recovery schedule  if the NAS
 Schedule Float Sort indicates negative 20
 work-days or 30 calendar-days
38Situation
- Slipped schedule for the contract (Contract 
 Schedule indicates greater than 30 calendar days
 negative float
- The contractor should prepare a supplemental 
 recovery schedule
- The contractor should select a number of work 
 activities indicated to be on the contract
 critical path-- which are scheduled to be
 accomplished within the next 2-3 months
 (contractors choice for selection of work
 activities)
39Supplemental Plan
- The contractor should then reduce (CRASH) the 
 original durations of all of the selected
 critical work activities such that the negative
 float is reduces to 0 float at the end of the
 selected 2-3 month period and the original
 schedule is regained.
- The contractor must use additional resources, 
 additional crews, and/or overtime shifts.
40Supplemental Plan
- The contractor should submit his supplemental 
 recovery schedule for approval to the Contracting
 Officer.
- The government representative should monitor the 
 contractors performance and progress on his
 accelerated supplemental recovery schedule
 weekly.
41Recovery Plan In-Action 
 42Step 8
- ACO will prepare and recommend an Interim 
 Unsatisfactory Evaluation to the Contracting
 Officer if the contractor is not implementing his
 supplemental recovery schedule during the first
 month of the 3-month recovery period  reducing
 the negative float by increasing manpower
 resources (crew hours/week) for the future
 critical and near critical work activities, as
 indicated in the supplemental recovery schedule.
43Step 9
- ACO must require the contractor to prepare 
 another supplemental recovery schedule  should
 the first supplemental recovery schedule fail to
 result in the recovery of the original schedule.
 The KO may direct the contractor to comply with
 his supplemental recovery schedule and/or
 increase the crew hours/week (adding manpower
 and/or overtime periods) in accordance with the
 FAR Clause for Schedules  FAR 52.236  15
44Step 10
- ACO must consider a Final Unsatisfactory Rating  
 should the contractor fail to implement the
 supplemental recovery schedule as directed.
45Steps for Schedule Management
- 1. ACO Must assure necessary contract 
 requirements are included in Enhanced
 Specification 01320
- 2. Prime Contractor Must prepare a reasonable 
 initial (baseline) schedule meeting 4-tests.
- 3. ACO Must express serious and sincere interest 
 and commitment at the Pre-Construction
 Conference.
- 4. The Contractor (subs included) and the 
 Government must perform two-monthly evaluations
 of updated NAS.
- 5. ACO must require Project Engineer and 
 Superintendent to jointly input AS and AF dates
 into RMS and the NAS Schedule (review weekly).
46Steps for Schedule Management
- 6. ACO withhold 10 retainage when the NAS Total 
 Float sort indicates negative float. Continue
 until zero.
- 7. ACO must require contractor to prepare 
 supplemental recovery schedule if the NAS sort
 indicates negative 20 work days or 30
 calendar-days.
- 8. ACO will prepare and recommend an Interim 
 Unsatisfactory Rating to the KO if supplemental
 schedule fails to reduce negative float
 (3-months)
- 9. ACO must require another supplemental recovery 
 schedule. KO may direct increased crew, hours,
 O/T.
- 10. ACO must consider Final Unsatisfactory Rating 
 should Contractor fail to recover schedule.
47Cost
- In general, costs are acceptable. 
- Others want dramatically reduced costs. 
- Improving costs means 
- Paying attention to small details 
- Getting the design right the first time 
- Managing costs during construction
48Cost Growth
- Unpredictable material and labor shortages 
- Errors in the design 
- Differing Site Conditions 
- User requested changes 
- Shortage of project funds
49Keys for Controlling Cost
- Teamwork and communications 
- Maintaining forward progress 
- Active problem solving 
- Daily positive attitude 
- Maintaining a working partnership
50Summary
- Military Construction Transformation requires 
- Conveying Expectations 
- Sharing tips for success through our communities 
 of practice and professional societies
- Knowing what we devote our most attention and 
 resources to (Education  Training)
- Feedback (PEC and Knowledge Forum)
51For More Informationhttp//www.doklibrary.com/ 
 52Questions?
Establishing  Managing a Reasonable 
ScheduleDOK Practicum on Schedule