DOE Review - PowerPoint PPT Presentation

1 / 25
About This Presentation
Title:

DOE Review

Description:

Coordinators will schedule these activities to maximize efficiency and minimize ... Synchronizing Booster/MI injection (Booster Cogging) MI/NuMI event timing ... – PowerPoint PPT presentation

Number of Views:19
Avg rating:3.0/5.0
Slides: 26
Provided by: aesookby
Category:

less

Transcript and Presenter's Notes

Title: DOE Review


1
NuMI Commissioning
  • Overview
  • CD-4 Goals
  • Planning
  • Pre-commissioning activities
  • Commissioning
  • Summary

2
Overview
  • Commissioning bringing the NuMI facility into a
    state of operation
  • NuMI project activities
  • Off-project activities such as Main Injector
    preparations
  • This definition is slightly modified for the
    Technical Components
  • Commissioning bringing the facility into
    operation using beam
  • Checkout commissioning sub-systems prior to
    beam
  • The MINOS detectors can be commissioned almost
    fully using cosmic rays

3
Overview
  • The NuMI project has retained the responsibility
    for conducting and documenting all checkout and
    commissioning activities
  • Coordinators will schedule these activities to
    maximize efficiency and minimize impact to
    accelerator operations
  • NuMI Commissioning Coordinator Bruce Baller
  • MINOS Near Detector Commissioning Coordinator
    Peter Shanahan
  • Commissioning workshop held in April to define
    checkout and commissioning steps
  • Attended by 35 participants from NuMI, MINOS,
    Operations, ESH, AD management

4
CD-4 Goals
  • The NuMI Project Management Plan describes the
    Technical Commissioning Goals required to meet
    CD-4

5
CD-4 Goals
  • We plan to follow the Main Injector model for
    documentation acceptance of goal achievement -
    Greg Bock memos to Steve Webster with supporting
    documentation
  • Goal 1 ACNET parameter page showing proton
    intensity in NuMI beamline
  • Goal 2 ACNET parameter page showing beam
    position in pre-target display showing beam
    position in the hadron monitor
  • Goal 3,5 Detector measurements of pulse height
    and event length consistent with neutrino
    energies of 2 4 GeV
  • Goal 4,6 MINOS displays of cosmic ray events in
    the near and far detectors

6
Planning
  • NuMI checkout commissioning activities are
    tracked using MS Project
  • Each task is assigned to a responsible person,
    approx start approx duration, notes, device
    status
  • Pre-commissioning activities
  • Main Injector Preparations (65 tasks)
  • NuMI checkout (200 tasks)
  • Administrative Approvals (15 tasks)
  • Operations Preparations (20 tasks)
  • Commissioning
  • NuMI commissioning (60 tasks)
  • Main Injector High Intensity (2 tasks need
    experience)
  • Turnover to Operations (2 tasks)

7
Planning
  • The commissioning plan includes several flavors
    of tasks
  • Canonical off-project tasks that can be readily
    estimated, e.g. Design/build Main Injector
    Batch-by-Batch integrator
  • Main Injector studies that are difficult to
    estimate (e.g. high intensity beam studies) but
    have a well defined result
  • NuMI systems checkout tasks costed in the Master
    Schedule
  • Administrative tasks, e.g. AD DOE approve MI
    safety envelope
  • Checkout steps, e.g Put profile monitors into the
    beam
  • The primary purpose of the plan is to ensure that
    all required tasks are identified and completed
    in the proper sequence

8
Pre-Commissioning Activities
  • Description of pre-commissioning activities
  • Main Injector Preparations
  • NuMI Checkout
  • Administrative Approvals
  • Operations Preparations

9
Main Injector Preparations
  • After commissioning, NuMI will operate in a
    mixed-mode with antiproton stacking at 120 GeV
  • A 1.877 sec MI cycle will accommodate 6 batches
    of 3.3x1013 protons/cycle
  • The Antiproton Source requires 1 batch of
    0.8x1013 protons to be achieved by slip-stacking
  • NuMI will receive 5 batches for a total intensity
    of 2.5x1013 protons
  • Antiproton beam requirements are tighter than
    NuMI
  • Commissioning will be done on a special NuMI-only
    cycle

10
Main Injector Preparations
  • High intensity studies (Damper system)
  • Synchronizing Booster/MI injection (Booster
    Cogging)
  • MI/NuMI event timing
  • Multi-batch intensity measurement
  • MI beam quality inputs to the NuMI Beam Permit
    System (BPS)
  • Orbit and extraction issues

Planned for normal operation Not necessary to
meet CD-4
11
High Intensity Studies
  • The bunch-by-bunch digital damper system (Run II)
    is needed for high intensity
  • Instrumentation, RF cavities and kicker exist
  • Longitudinal dampers operational now
  • Transverse damper board in debugging
  • Start multi-batch mode studies after board is
    fully tested (late June)
  • Demonstrate high intensity multi-batch capability
    before the August shutdown

12
Multi-Batch Pbar Extraction
pbar batch
No cogging
Beam on the pbar target
No dampers
NuMI batches
13
Booster Cogging
  • Booster notch needs to be syncd to the kicker
    and timed to MI batches
  • Booster cogging turned on
  • No losses with lt 3 Booster turns
  • 20 loss with 4 turns

Revolution
Time (ns)
14
Pre-Commissioning Activities
  • Description of pre-commissioning activities
  • Main Injector Preparations
  • NuMI Checkout
  • Administrative Approvals
  • Operations Preparations

15
NuMI Checkout
  • Sub-system checkout tasks are included in the
    master schedule at a summary level to capture
    costs, resources
  • The purpose of the Commissioning Plan is to
    ensure that every sub-system is fully checked out
    before commissioning begins
  • Checkout is a multi-step process that culminates
    in the documentation of readiness by the L3
    manager in the NuMI Beamline electronic logbook
  • The Commissioning Plan identifies a final
    checkout step (200) that requires documented
    completion
  • Notes field defines the required checkout action
    for each sub-system (e.g. magnets Polarity check
    and power testing completed)

16
NuMI Devices
  • Primary beam 49 magnets, 24 BPMs, 10 Profile
    Monitors, 2 calibration targets, 50 loss
    monitors, 4 total loss monitors, 2 toroids, 3
    beam vacuum systems
  • Magnetic shielding check on HV101 string
  • Target hall 6 thermocouples, Budal monitor,
    target helium flow, target/horn drive/position,
    RAW system status (for each module), chase
    cooling system flow/pressure
  • Decay pipe vacuum status/pressure, RAW system
    status
  • Absorber 8 thermocouples, RAW system status,
    leak rate study
  • Hadron/Muon Monitors HV/LV status
  • Beam Permit System 9 input summary checks
  • Safety System 2 administrative checks

17
Pre-Commissioning Activities
  • Description of pre-commissioning activities
  • Main Injector Preparations
  • NuMI Checkout
  • Administrative Approvals
  • Operations Preparations

18
Administrative Approvals
  • Main Injector
  • The MI Shielding Assessment has been revised to
    allow operation at 3.3x1013 protons/cycle
  • In review now
  • MI Safety Envelope will be reviewed and approved
    concurrent with NuMI Safety Envelope
  • NuMI
  • The NuMI Shielding Assessment and Safety Envelope
    will be discussed in Nancy Grossmans talk
  • Commissioning plan includes Accelerator Readiness
    Review, final walkthrough by ESH committee,
    Running Conditions development and approval

19
Pre-Commissioning Activities
  • Description of pre-commissioning activities
  • Main Injector Preparations
  • NuMI Checkout
  • Administrative Approvals
  • Operations Preparations

20
Operations Preparations
  • Controls needs
  • Add NuMI devices to the ACNET database
  • Develop parameter pages
  • Set up BPS and alarms limits pages, sequencers
  • Define device list for data-logging
  • Set up data logger
  • Set up Beam Loss Budget Monitor and Beam Budget
    Monitor
  • Administration Training
  • Develop Search Secure procedures training
  • Develop emergency response procedures training
  • Define access requirements, threshold criteria
    for NuMI operation
  • Develop and conduct operator training
  • Define list of qualified experts

21
Commissioning
  • Commissioning team composed of experts from NuMI,
    External Beams Dept CERN
  • Use the existing NuMI Beamline electronic logbook
    for documentation
  • Commissioning is divided into 11 phases
  • The first 8 will be conducted on a special NuMI
    study cycle with a cycle time of 2 minutes
  • Allows time for evaluation between shots
  • The Beam Permit System (BPS) is administratively
    controlled by the Coordinator by the use of a
    golden file

22
Commissioning
  • MI NuMI setup (4 days)
  • Establish stable 1 batch MI beam (3x1011 ppp) on
    NuMI cycle
  • Start NuMI ramps, ensure devices are reading
    back, data logging, BPS active, AutoTune working,
    NuMI kicker is OFF
  • First Beam to NuMI (3 days)
  • Enable kickers
  • Tune beam to hadron absorber (AutoTune
    semi-automatic)
  • Check function of loss monitors with profile
    monitors in/out
  • Calibrate BPMs
  • Aperture scans (4 days)
  • Scan Lambertson 2 NuMI magnet apertures
  • Declare BPS golden file
  • Start tuning with correctors

Meet CD-4 Goal 2
23
Commissioning
  • Horn Alignment (2 days)
  • Scan horn 1 and horn 2 using neck and cross-hair
    alignment system
  • BPM and hadron monitor response checked
    concurrently
  • Target/Baffle Alignment (2 days)
  • Target/baffle are scanned while in Low Energy
    (LE), Medium Energy (ME) and High Energy (HE)
    positions
  • Hadron monitor response checked concurrently
  • Raise Intensity Check Calibration (1 day)
  • Increase intensity to 1x1012 protons/cycle
  • Check instrumentation calibration

Meet CD-4 Goal 1
24
Commissioning
  • First Neutrinos (2 days)
  • Start horn pulsing log neutrinos in the near
    detector
  • Beam-on and beam-off radiation surveys
  • Multi-batch tuning (7 days)
  • Increase number of batches
  • Check ramp, instrumentation timing losses
  • Reduce cycle time - Mixed-mode (1 day)
  • Start NuMI/pbar mixed mode at 2 sec cycle time
  • Main Injector High Intensity (30 days)
  • Check ramp, instrumentation timing losses
  • Turnover to Operations
  • Document tunes operator training

Meet CD-4 Goal 3,5
CD-4 Met
25
Summary
  • The April commissioning workshop was valuable
  • Recommendations on philosophy, tips
  • NuMI, Operations and AD management agree on all
    points
  • The commissioning plan codifies all major and
    many minor tasks
  • Plan will be updated regularly, posted on the web
    and tracked in weekly commissioning meetings
  • We expect to achieve CD-4 after several weeks of
    commissioning
Write a Comment
User Comments (0)
About PowerShow.com