Aquila, Inc WestPlains Energy Colorado - PowerPoint PPT Presentation

1 / 5
About This Presentation
Title:

Aquila, Inc WestPlains Energy Colorado

Description:

Pueblo Area Plans. General approach is to move load from 69 kV system to 115 kV system. Planning three new 115 kV substations in Pueblo area in the next 3-5 years ... – PowerPoint PPT presentation

Number of Views:22
Avg rating:3.0/5.0
Slides: 6
Provided by: tpuc6
Category:

less

Transcript and Presenter's Notes

Title: Aquila, Inc WestPlains Energy Colorado


1
Aquila, IncWestPlains Energy Colorado
Alan Myers, Manager Transmission Services
2
Aquila Planning Procedures
  • Produce a long-range planning study every three
    years at least 10 years into the future
  • Assess long-range plan for near term budget each
    spring
  • Participate in joint studies with neighboring
    utilities on issues of mutual interest
  • Participate in CCPG regional planning efforts

3
  • Near Term System Needs
  • Load growth in Pueblo
  • Load growth in Canon City
  • Load growth in Cripple Creek/Victor area

4
  • Pueblo Area Plans
  • General approach is to move load from 69 kV
    system to 115 kV system
  • Planning three new 115 kV substations in Pueblo
    area in the next 3-5 years
  • New substations will pick up new load and shift
    some existing load from 69 kV to 115 kV
  • Also plan to add approximately 20 new miles of
    115 kV transmission line in the area

5
  • Canon City and Cripple Creek/Victor Areas Plans
  • Plan to build a new 115 kV line up the Cripple
    Creek area and install a 115/69 kV Substation in
    the next 2-5 years
  • Improvement will support load growth in both
    areas