Title: INTRODUCTION TO CLEAN DEVELOPMENT MECHANISM CDM
1INTRODUCTION TO CLEAN DEVELOPMENT
MECHANISM(CDM)
2Intergovernmental Panel on Climate Change (IPCC)
- IPCC was established in 1988 by UNEP and WMO to
provide policy makers, scientific information on
climate change. -
- IPCC Report concluded that Green House Gases
(GHG) will result in warming of earth by next
century, unless measures were adopted to limit
emissions.
3The United Nations Framework Convention on
Climate Change
- On the basis of Report, United Nations Framework
Convention on Climate Change (UNFCCC) was
formulated in May 1992 for global climate
protection. - India signed UNFCCC on 10th June 1992
- and ratified that in 1993.
4Kyoto Protocol to The UNFCCC
- Kyoto Protocol to the Convention, established the
Conference of Parties (COP) as its supreme body. - COP3 held in Kyoto, Japan agreed to legally
binding set of obligations to reduce their
emissions of GHG.
5- Commits Industrialised Countries (Annex I
Parties / Countries) to reduce their Green House
Gas (GHG) emissions by, on average, 5.2 below
1990 levels in 2008-12 (Phase I). - Individual, quantified emission targets for each
Industrialised Country. -
6Green House Gases
- Six Green House Gases covered
- Carbon Dioxide (CO2)
- Methane (CH4)
- Nitrous Oxide (N2O)
- Hydro fluorocarbons (HFC)
- Per fluorocarbons (PFC)
- Sulphur Hexafluoride (SF6)
7Flexible Mechanisms
- Clean Development Mechanism (CDM)
- Joint Implementation (JI)
- Emission Trading (ET)
8Clean Development Mechanism (CDM)
- Clean Development Mechanism was instituted in
2001 under Kyoto Protocol. - Came into force on 16th February 2005 after
Russia and European Community ratified it. - Major non participants USA and Australia.
9CDM Objectives
- Help Industralised Countries (Annex I Countries)
meet their GHG emission reduction objectives in a
cost effective way. - Contribute to sustainable development of the non
Annex I Countries. - Contribute to the ultimate goal of the convention
i.e., stabilization of GHG concentrations in the
atmosphere.
10Certified Emission Reduction (CER)
- One ton of CO2 reduced through CDM Project, when
certified by CDM EB, is known as CER which can be
traded.
11CDM Rules
- Rules, modalities and procedures of CDM are
defined in - Kyoto Protocol (1997)
- Follow up decisions of Conference of the
Parties (COP), especially Marrakesh Accord
(2001), and - Decisions of CDM Executive Board
12Prerequisites for participation as per Marrakesh
Accord (Non Annex I Countries)
- Participation in a CDM project activity is
voluntary. - Parties participating in the CDM shall designate
a National Authority for the CDM.
13Prerequisites for participation as per Marrakesh
Accord (Non Annex I Countries)
- A Party not included in Annex I may participate
in a CDM project activity if it is a party to the
Kyoto Protocol.
14Prerequisites for participation as per Marrakesh
Accord (Annex I Countries)
- A Party included in Annex I with a commitment
inscribed in Annex B is eligible to use CERs,
issued in accordance with the relevant
provisions, to contribute to compliance with part
of its commitment, if it is in compliance with
the following eligibility requirements. - a) It is a party to the Kyoto Protocol.
-
15- b) Its assigned amount pursuant to Article 3,
Paragraph 7 and 8, has been calculated and
recorded in accordance with modalities for the
accounting of assigned amounts. - c) It submits the supplementary information on
additions to / subtraction from assigned amount -
16- d) It has in place a national system for the
estimation of anthropogenic emissions by sources
and anthropogenic removals by sinks of all
greenhouse gases. -
- e) It has in place a national registry in
accordance with Article 7. -
17- f) It has submitted annually the most recent
required inventory pertaining to emission of
Green House Gases from sources / sector
categorized from annex-A to the Kyoto Protocol
and submission of annual inventory on sinks.
18CDM Organisation Functions
- CDM Executive Board (CDM EB)
- Supervise the CDM projects under the authority
and guidance of the COP -
- Make recommendations on further modalities and
procedures
19- Approve new methodologies related to, baselines,
monitoring plans and project boundaries - Review provisions with regard to simplified
modalities, procedures and the definitions of
small scale project activities
20- Responsible for the accreditation of Designated
Operational Entity (DOE) - Register the validated projects as CDM project
activities - Issue CER according to the emission reduction
verified by DOE
21- Designated Operational Entity (DOE)
- A body (private or public) accredited by the CDM
EB to review projects - Validate proposed CDM project activities
22- Verify and certify reductions in GHG emissions
- Make information obtained from CDM project
participants publicly available, as required by
the executive board, obtain stake holder comments
and get these accounted appropriately
23- Designated National Authority (DNA)
- Parties participating in the CDM shall designate
DNA - Interfaces between project owner and the DOE
24- Facilitate information dissemination
- National CDM Authority, MoEF is the DNA for India
25- Composition of the "National Clean Development
Mechanism (CDM) Authority" -
- 1.Secretary (Environment and Forests),
Chairperson - 2. Foreign Secretary or his nominee, Member
- 3. Finance Secretary or his nominee, Member
26- 4.Secretary, Industrial Policy and Promotion or
his nominee, Member - 5.Secretary, Ministry of Non Conventional Energy
Sources or his nominee, member - 6.Secretary, Ministry of Power or his nominee
Member
27- 7.Secretary, Planning Commission or his nominee
Member - 8.Joint Secretary (Climate Change), Ministry of
Environment and Forests, Member - 9.Director (Climate Change), Ministry of
Environment and Forests, Member-Secretary
28Preparation of Project Design Document (PDD)
- Main Document in the CDM project cycle
- Standardised Format
- General Description of project activity
- Base Line Methodology, Additionality, and Project
boundary
29- Crediting period
- Monitoring methodology and plan
- Estimation of GHG emissions
- Environmental Impacts
- Stakeholders comments
30 Key factors in Project Design Document
- Base Line Methodology
- Existing actual or historical emissions data
- Emissions from a technology that represents an
economically attractive course of action, taking
into account barriers to investment
31 - The average emissions of similar project
activities undertaken in the previous five years
in similar circumstances, and whose performances
is in the top 20 of their category
32- Approval process for New CDM Base Line
methodologies -
- Project proponent , via validator , submit new
methodology to UNFCCC Secretariat - CDM Methodologies Panel obtains two independent
desk reviews - Methodologies Panel formulates preliminary
recommendation
33- Project proponent has 10 days to provide feedback
to preliminary recommendation (improved
methodology if necessary) - Methodologies panel formulates final
recommendation to CDM EB
34- CDM EB rates the methodology based on
Methodologies panel recommendation - A Methodology is approved
- B Methodology may be revised and
- re-submitted without new desk reviews
- C Methodology is rejected and must
- go through full cycle if re- submitted
35- Additionality
- A CDM Project activity is additional, if
anthropogenic emission of GHG by sources are
reduced below those that would have occurred in
the absence of the registered CDM Project
activity, and passes CDM additionality tool
adopted by CDM EB in Oct. 2004
36- CDM Additionality Tools
- Step 0 Eligibility for early CDM
- Step 1 Identification of lawful project
alternatives. - Step 2 Investment analysis, or
- Step 3 Barrier Analysis
- Step 4 Common practice analysis
- Step 5 Impact of CDM Registration
37Baseline and Additionality of CDM Projects
Validation of project design, baseline and
monitoring plan
Emissions baseline
GHG Emissions (t CO 2-eq )
Additional emission reductions
Verification/ certification of emissions
reductions
Emissions baseline
Project implementation
Year
38- Monitoring Plan
- Systematic collection and archiving of data for
estimating GHG/ Baseline emission - For measuring Power Generation
- For estimating or measuring anthropogenic
emissions occurring within the project boundary
of a CDM project activity
39Host Country Approval
- Formal confirmation by the host country that the
project meets sustainable development objectives - National CDM Authority, Ministry of Environment
and Forest, is appointed as the Designated
National Authority (DNA) for CDM in India
40- Sustainable development criteria set by the DNA
- Social well being Employment, alleviation of
poverty - Economic well being Investment consistent with
needs of the people
41- Environmental well being Impacts on the local
and global environment, degradation of resources
human health, pollution etc - Technological well being Transfer of
environment safe and sound technologies
42Validation
- Independent assessment by designated Operational
Entity (DOE) that project meets criteria of the
Kyoto Protocol
43 Validation
- DOE shall
- Review the PDD and supporting documentation
- Conduct site visits
- Interact with stake holders
- Source other relevant additional information from
various sources - Publish the PDD in the web for international
stake holder comments
44 Validation
- A successfully validated project can be submitted
to CDM EB for registration
45Registration
- Automatic registration of submitted projects
unless 3 members of the CDM EB or one of the
parts involved file a request for review within - 4 weeks for small scale project activities
- 8 weeks for large scale project activities
46Registration Fees
- Registration fees between 5,000 and 30,000 USD
are payable to the Executive Board by the project
participants depending on the quantity of
emission reductions
47Registration Fees
48Crediting Periods Timing
- Carbon Credits ( CERs ) can be generated as from
now - Banking by buyer for use towards compliance in
2008-12 - Banking by project proponent for sale in later
years
49Crediting Periods Timing
- Start of Crediting period
- Usually the later of
- (i) CDM Registration, and
- (ii) Start of project operation
- Emission reductions achieved since 2000 could be
credited under certain conditions (
demonstration of additionality, registration
before end of 2005)
50Crediting Periods Timing
- Duration of Crediting periods
- Fixed Crediting period of upto 10 years, or
- Renewable crediting periods of upto 7 years (
maximum 3 X 7 years)
51CDM Project Cycle
Project Participants
Project Design
Designated operational entity
Validation/ registration
Designated national authority of host country
Executive Board
Project participants
Monitoring
Designated operational Entity
Verification/ Certification
Executive Board
Issuance
Certified emissions reductions
52CDM Statistics ( as on 10 Nov. 2005)
- Total projects registered by CDM EB 34
- Registered Projects located In India 8
- Projects under consideration by CDM EB 19
53Registered CDM Projects in India
54(No Transcript)
55Scope for NHPC Projects
- Kambang (2X3 MW) and Sippi (2X2 MW) SHE Projects
- Small Scale Projects / RE Projects
- Projects qualify additionality criteria, being
replacement of DG power, and reduction in
emission through transportation of diesel - Very low IRR
56- Not being perused solely for profit
- Serve social cause
- Approved Baseline Methodology is available AMS-1D
- Consulting Firms have also indicated their
potential for qualification as CDM Projects
57- Nimoo Bazgo (3X15 MW) and Chutak (4X11 MW)
Projects too have potential for qualification as
CDM Projects - Medium Sized Run-of-River Projects
- Projects qualify additionality criteria, being
replacement of DG power, and reduction in
emission through transportation of diesel
58- High cost of Generation
- Very low IRR
- Not being perused solely for profit
- Serve social cause
- Approved Baseline Methodology is available AM0005
ACM0002
59Approved Methodology ACM0002
- Consolidated baseline methodology
forgrid-connected electricity generation from
renewable sources - Applies to electricity capacity additions from
Run-of-river hydro power plants hydro power
projects with existing reservoirs where the
volume of the reservoir is not increased
60Approved Methodology AM0005
- Baseline methodology for small grid-connected
zero-emissions renewable electricity generation - Applies only to small electricity capacity
additions, i.e. less than or equal to 60 MW and
using a 5050 default weighting of the build and
operating margins
61Approved Methodology AMS I.D.
- Grid connected renewable electricity generation.
(Small Scale CDM Projects) - Applies to renewable energy generation units,
such as photovoltaic, hydro, tidal/wave, wind,
geothermal, and renewable biomass, that supply
electricity to and/or displace electricity from
an electricity distribution system that is or
would have been supplied by at least one fossil
fuel or non-renewable biomass fired generating
unit
62Special considerations for Small Scale CDM
Projects
- Recognising the high sustainable development
impacts of small projects, efforts have been made
to encourage such projects by reducing the costs
of going through the CDM project cycle. These
measures include the following
63- Size Limits for Small Scale CDM Projects
- Electricity generation from renewable sources,
upto 15 MW - Energy Efficiency projects saving, upto 15 GWh
per year - Projects reducing, and emitting themselves, upto
15,000 t CO2e annually - Afforestation and reforestation project
activities sequestering less than 8000 t CO2e
annually
64- SSC Projects benefit from simplified rules and
procedures - Simplified PDD
- Use of simplified pre-approved baseline
/monitoring methodologies - Same DOE can validate and verify the project
- Bundling of similar projects is allowed ( within
15 MW)
65- Lower registration fee
- CER issued in 4 weeks instead of 8 weeks
- Bundling of similar projects is allowed
-
66PDD Limitations
- Preparation of PDD including New Baseline
Methodology ( if needed), Baseline Setting and
Monitoring Plan requires experience and access to
vast data needed for assessing the Baseline
Emission. Service of Consultants will be required
for this job.
67Lists of Consulting Firms/ Agencies Consulted
- M/S Mantec- Ecosecurities, New Delhi
- M/S Mitcon Consultancy Services, Pune
- M/S Ernst Young, New Delhi
- M/S Mitsui Co Ltd, New Delhi
- M/S CDM India Expert Group
- World Bank Group
68Consultancy Services Charges
- M/S Mantec- Ecosecurities, New Delhi
- The cost of PDD development, design of a new
methodology (if required), validation,
registration, and verification as given below are
for the account of NHPC and will be paid by
Ecosecurities and deducted from the initial
payment due to NHPC by CERs
69- PDD Development 50,000 USD
- New Methodology Development (if needed)10,000
USD - Validation 30,000 USD
- Registration 5,000 to 30,000 USD
- Verification 5,000 to 10,000 USD per annum
70- Payment Terms
- M/s Ecosecurities will acquire the carbon credits
at the rate of USD 4.50 per metric ton of CO2
equivalent - Payment will be deducted from the initial payment
due to NHPC.
71- M/S Mitcon Consultancy Services, Pune
- Rs 7.5 lakhs 10 of actual fund received by the
project promoters for the first year payable
within seven days on receipt of funds - Charges are exclusive of all travel, lodging
boarding, local conveyance, registration fees and
applicable service tax
72- Payment Terms
- 30 advance with work order
- 30 on submission of PCN or PIN PDD to the
project promoter. - 20 on the receipt of National approval /
endorsement - 20 on signing of agreement with identified
buyer.
73- M/S Ernst Young, New Delhi
- Rs 12 Lakhs 10 of carbon revenue for entire
crediting period, each year, within 15 days from
receipt - Service tax will be extra.
- Charges are exclusive of expenses on travel,
lodging boarding, communication photocopy etc
will be reimbursed to EY at actuals
74- Payment Terms
- 50 on award of assignment and
- 50 on completion of documentation.
75Other Agencies Consulted
- National CDM Authority, MoEF, too was consulted
on 9 Nov. 2005 - No specific guidelines available with DNA
- Doubts and clarifications discussed but no
specific solutions provided
76Uncertainty / Doubts
- Most of the consultants have indicated hesitation
to take up medium and large size HE Projects,
with dam height greater than 15 m and large
reservoir. No specific guidelines however are
available. - Only world bank team indicated that no such
restriction apply for medium and large size HE
projects if they fall under Run-of-river Scheme.
77- No precedent is available for medium and large
size HE Projects (Two projects are under
consideration of CDM EB ) - National CDM Authority has no sufficient
information on all these issues - Present regime has been defined as 2008-2012,
what happens after this is not very clear.
Validity value of CERs beyond 2012 is uncertain
78Essential Requirements
- Implementation of project strictly as planned -
Failing may invite non deliverance penalty - PFR / DPR of the project should indicate
likelihood of availing CDM benefits to make it
financially more attractive
79- CDM Projects are largely consultant driven
- Engagement of consultant for preparation of PDD
including New Baseline Methodology ( if needed),
Baseline Setting and Monitoring Plan and
facilitation with DNA, DOE and CDM EB for
validation , verification, registration and issue
of CERs
80- It is important that a reputed consultant is
engaged for preparing quality documents,
presentations, analysing and getting it through
at all stages, especially each HE Project being
unique will require appropriate handling.
81Meeting with World Bank Experts
- Sh. A. K. Kutty, JS (Hydro) suggested the World
Bank team to contact NHPC in respect of Chutak
Nimoo Bazgo Projects in JK for availing CDM
Benefits - Briefly the salient features the project
details were introduced to the team - Mr. David sought certain clarifications specially
in respect of peaking power, winter peaking and
reservoir storage
82Eligibility of Hydro Projects for CDM Benefits
- Size capacity of the project is immaterial
- It should be ROR scheme
83- The dam height the reservoir area etc. also do
not matter except that the execution should be of
good quality and all dam safety aspects aspects
brought out in PDD are appropriately followed - The methodology ACM 002 will be used
84Role of World Bank the type of agreement / MOU
- The World Bank objective or goal is to create an
environment and building the Carbon Finance
Market - World Bank enters into a LOI with the project
developer
85- In accordance with this LOI, World Bank takes up
full responsibility finances all the fees etc.
for examining the PIN, Carbon Finance Document
(CFD) - Appointment of consultant for preparation of PDD,
appointment of independent consultant for
validation of PDD
86- CFD is a more detailed PIN document containing
financial analysis of the project -
- World Bank facilitates appointment of consultant
in consultation consent with the developer and
submit the PDD to DNA for approval
87- Negotiation for terms conditions for ERPA
- Third party validation of the project signing
of ERPA - Execution phase of the project
88- Commissioning, OM (Maintaining stipulations of
PDD) - Verification of emission reduction every year
- World Bank to buy VERs ( Validated Emission
Reduction)
89- Their agreement will be valid up to 2015 instead
of 2012. - World Bank will buy only 80 of the VERs
generated. Developer is free to trade the balance
20 VERs or converting them to CERs as per his
requirement.
90- The likely amount of fees ( max. to be covered by
them) is up to USD 265000 up to VERs - The likely expenses to be incurred up to CERs is
in the order of USD 275000
91- 60 of the total VERs to be bought by them by
2012 40 after 2012 - There is no penalty clause from them towards
delay in construction/ commissioning or towards
non deliverable VERs
92- Developer has no liability for any payment if the
project is rejected - World Bank works with the consultant experts to
oversee and ensure the quality of documents and
the presentation of documents
93Suggestions
- In the project document like PFR, DPR include the
possibility of covering Carbon Finance Revenue
and include its effect in financial analysis and
how it makes the project more viable feasible
94- presently they would like to work on these two
medium size projects with clear cut additionally
by way of Clean Development Hydro Station
replacing Diesel Power as well as emissions
created during transportation of Diesel to
Laddakh
95- Subsequently they will be moving towards newer
models with medium / large size projects creating
more effective impact on GHG emission reduction - Present rate of the VERs CERs as per them is
USD 5-6 6-7 respectively
96- As World Bank finances the cost including the
cost of examinations, formulations of documents ,
transaction cost of consultant, validation cost,
signing of ERPA getting validated the Emissions
reduction and recovers the cost in lieu of VERs
transaction - World Bank absorbs the cost if the project is not
approved
97- Thank you for your kind attention !
98Renewable electricity generation for the grid
- Energy baseline
- kWh generated
- Emissions baseline
- 800 2400 g CO2 / kWh for a diesel fired grid
depending on size and load factor of diesel
generator (lt 15 kW, 25 PLF2400, gt200kW800)
99- Grid average if linked to a grid involving
several power plants - 50 operating margin, 50 build margin
- Monitoring
- Electricity generated
100The margin calculation
- Operating margin Average of all plants excluding
hydro, geothermal, wind, low-cost biomass,
nuclear and solar - Emission factor energy content of fuels used
(GJ) times carbon emission factor of the fuel (t
CO2 / GJ) times oxidation factor - Challenge in India get reliable heat rates for
all plants
101- Build margin
- Last 20 added or 5 latest additions
- Use the one with higher generation in past year
- Will be prone to sudden changes ( hydro plants
vs. coal plants) - CDM projects are not taken into account
102Example
- Operating Margin
-
- Coal 500 TWh _at_ 1100 g CO2
- Fuel oil 100 TWh _at_ 800 g CO2
- Natural gas 100 TWh _at_ 500 g CO2
- (500.1100100.800100.500) / 700 971 g CO2
-
103- Build Margin
- Total grid 15 GW
- Last 20 3 GW, generation 200 TWh, 800 g CO2
- Last 5 plants 1 GW, generation 80 TWh, 600 CO2
- 800 g CO2
- Weighted at 50 886 g CO2
-
104Huge gap between different generating CERs
- CER (Early Stage) 3 - 7 Euro
- Approved Methodology 6 -7 Euro
- Registered Project 15 Euro
- Issued CER 18 Euro
- EU Allowance 18 30 Euro
105Emission Factors
Source World Bank
106Small Scale CDM Projects benefit from simplified
rules and procedures
- Simplified PDD
- Use of simplified pre-approved baseline
/monitoring methodologies - Same DOE can validate and verify the project
- Bundling of similar projects is allowed
- ( within 15 MW)
107Small Scale CDM Projects benefit from simplified
rules and procedures
- Lower registration fee
- CER issued in 4 weeks instead of 8 weeks
- Bundling of similar projects is allowed
-
108Registration Fees
109Threshold CDM Eligibility Criteria
- Hydroelectric plants with power densities
- ( Installed power generation capacity divided by
the flooded surface area) less than 4 w/m2 cannot
use current methodology. - Hydroelectric power plants with power densities
greater than 4 w/m2 but less than or equal to 10
w/m2 can use the current approved methodologies,
with an emission factor of 90 g CO2eq/kWh for
project reservoir emissions
Contd
110Threshold CDM Eligibility Criteria
Contd.
- Hydroelectric power plants with power densities
greater than 10 W/m2 can use current approved
methodologies and the project emissions from the
reservoir may be neglected.