Ground and Ground Water Management at Sellafield - PowerPoint PPT Presentation

1 / 16
About This Presentation
Title:

Ground and Ground Water Management at Sellafield

Description:

WWII Royal Ordnance Factory for production of TNT some evidence of conventional ... Two further generation of plants have followed for the reprocessing of ... – PowerPoint PPT presentation

Number of Views:55
Avg rating:3.0/5.0
Slides: 17
Provided by: BNFL7
Category:

less

Transcript and Presenter's Notes

Title: Ground and Ground Water Management at Sellafield


1
Ground and Ground Water Management at
Sellafield
Presented by Dr Katherine Eilbeck Deputy Head of
Contaminated Land
2
History of Sellafield
  • WWII Royal Ordnance Factory for production of
    TNT some evidence of conventional chemical
    contamination
  • Mid 1940s site adopted to support production of
    atomic weapons materials
  • Two further generation of plants have followed
    for the reprocessing of commercial reactor Magnox
    and Oxide fuels

3
Sellafield in 1946

4
Sellafield in 2004

5
Background
  • 1950s - radioactive waste disposal in trenches
    (pre-Low Level Waste Repository)
  • 1970s silos major leak
  • 1950s and 1970s - medium active leakage from
    Magnox reprocessing facility
  • Miscellaneous spillages, leakages and disposals
    since1951

6
Major Contaminants
  • Caesium-137 and 134
  • Strontium-90
  • Tritium
  • Technetium-99
  • Plutonium-239
  • Non-rads TNT, heavy metals, asbestos, nitrates,
    organics, etc.

7
Conceptual Cross Section
8
Speed at which contaminants move through ground
water
9
Sellafield Ground Water Contamination
  • Conceptual model of contaminant migration
    pathways

10
Short Term Management
  • Safety case Managing the day-to day safety
    implications
  • Best Practicable Means easily implemented
    solutions
  • Leak detection plant audits and identification
    of technology
  • Groundwater monitoring programme
  • Better characterisation of Separation Area

11
Short Term Management
  • Better data management and visualisation tools
  • GIS, IMAGES
  • Better use of the current data and information
  • trending of data
  • Improved numerical modelling capability
  • hydrological, risk, cost, etc.
  • Improved site water balance

12
Sellafield Groundwater monitoring wells
13
The Website
14
Mid Term Management
  • Management of contaminated groundwater while the
    contaminated ground remains in place
  • Conceptualisation of Separation Area
  • Assessment of appropriate remediation /management
    technologies for the plumes and accessible areas
    of contamination
  • Implementation of appropriate technology

15
Long-term risks associated with source terms
  • Off-site risks will be less than required to
    necessitate remediation, assuming institutional
    control
  • Major risks are well-water risks. There are no
    current or anticipated users of this water.
  • Could leave in-situ if site remained under some
    form of institutional control in terms of risk
    but possible that this would not prove acceptable

16
Summary of below ground contamination issues at
Sellafield
  • Contaminated groundwater is not a new issue
  • Monitoring has been carried out for decades
    monitoring network recently improved
  • Currently undertaking a 15 million project to
    better understand the contamination under
    Separation Area
  • A new and growing in house contaminated land
    capability are placing us in a good position to
    manage current and future technical requirements
  • Measures to accelerate remediation under
    investigation
  • This is a long-term issue so data and information
    management is key
  • Understanding contaminated land issues are key
    for determining the next use of the site
Write a Comment
User Comments (0)
About PowerShow.com