Title: Report on ILC-Americas
1Report on ILC-Americas
- G. Dugan
- Cornell University
ILC-European Regional Meeting
2The Global Design Effort
Formal organization begun at LCWS 05 at
Stanford in March 2005 when Barry Barish became
director of the GDE
Technically Driven Schedule
3GDE Elements of the Near Term Plan
- Baseline configuration and Reference Design
Report - Begin to define Configuration (Aug 05)
- Baseline Configuration Document by end of 2005
- Put Baseline under Configuration Control (Jan 06)
- Develop Reference Design Report by end of 2006
- RD Program
- Coordinate worldwide R D efforts, in order to
demonstrate and improve the performance, reduce
the costs, attain the required reliability, etc.
(Proposal Driven to GDE)
4ILC-Americas Organization
5ILC-Americas program support
- The program is supported in the US by DOE and NSF
and is growing
Agency FY04 FY05 FY06
DOE/HEP (K) 19,600 22,600 25,000
NSF/EPP (K) 128 118 NA
Presidents budget
(Numbers exclude detector RD)
6ILC-Americas Program
- Main Linacs
- Superconducting module fabrication and test-
Fermilab,JLab, ANL, LANL, MSU, Cornell, SLAC - RF power sources and controls- SLAC, LLNL,
Fermilab - Machine design and simulation- SLAC, Fermilab,
Cornell - Sources
- Design and simulation- SLAC, LLNL, Cornell
- Damping rings
- Machine design and simulation- LBNL, Fermilab,
SLAC, ANL, Cornell - Component prototyping- SLAC, LLNL, Cornell
- Beam delivery systems
- Design and simulation- SLAC, BNL, Fermilab
- Component prototyping- BNL
- Global Systems
- Availability and machine protection- SLAC,
Fermilab - Site development- Fermilab, SLAC
7Main Linacs-Superconducting Module Fabrication
and Test
- SCRF development and test capabilities in the US
are distributed over a number of labs (Fermilab,
JLab, Cornell, MSU, LANL) - To consolidate and focus the efforts, Fermilab
has received a proposal for a Superconducting
Module and Test Facility (SMTF) to be constructed
at Fermilab. Signatories include all major US
institutions with significant SCRF experience,
plus a number of international labs. - This proposal provides a framework for the
development of a US-based capability in the
fabrication and test of high-gradient
superconducting accelerating structures for the
ILC.
8SMTF Proposal Cavities
Enhance infrastructure at Fermilab/ANL for cavity
treatment and testing establish process for
repeatable production of high-performance (35
MV/m, Qgt1010) cavities
- Acquire cavities from US industry, ACCEL, KEK
utilize existing lab facilities to process
cavities
4 ACCEL
Cavity Fabrication FNAL SMTF
4 AES
4 KEK
Early 06 Joint FNAL/ANL BCP facility
Processing Jlab/Cornell/ANL
Cavity Processing FNAL ANL
Vertical Testing Cornell/Jlab
Vertical Testing FNAL
Spring 06 Horz. Test Cryostat
Horizontal Testing Fermilab
Cavity to String Assembly
Achieve 35 MV/m by FY08
9SMTF Proposal Cryomodule design and fabrication
- Acquire TTF cryomodule components from US
industry and DESY assemble cavity strings and 2
cryomodules in new Cryomodule Assembly Facility
(FY06-07) develop 4th generation (ILC)
cryomodule design
8 Cavities US/ ACCEL Built/US processed
4 Cavities KEK Built/US processed
10Proposed Cryomodule Assembly Facility at Meson
Polarized Area at Fermilab (MP9)
11SMTF proposal Cryomodule testing and
industrialization
- Cryomodule testing
- Test cryomodules, measure key performance
parameters (TRC), in a new High-power Test
Facility (HPTF) - Single module power tests Meson Lab
- Beam tests, using the relocated A0 photoinejctor
New Muon Lab - Industrialization
- Develop and support start-up industrial
production capability in the US transfer cavity
and cryomodule technology pursue paths to
large-scale industrialization and design for
manufacturing.
12High power test facility at Fermilab
New Muon Lab
13Main Linacs High-gradient RD
Cornell Re-entrant 1.3 GHz cavity Single cell Nb
cavity, 70 mm TESLA-like aperture achieved 46
MV/m at Q 1010. Hpk 1755 Oersted, Epk 100
MV/m
JLab Single crystal 2.2 GHz cavity Single
crystal BCP surface rms 27 nm. Typical BCP
surface rms 1247 nm, EP 251 nm
14Main linacs RF power sources and controls
- Development at SLAC, Fermilab and LLNL
- Baseline modulators and klystrons, LLRF and
controls developments at SMTF - Alternate modulator designs for reduced
cost/improved reliability and performance
SNS-style, Marx generator, series-switched (DTI) - Klystron development acquire 10 MW L-band MBK
tubes, evaluate options and alternatives (sheet
beam) - Coupler improvements beyond TTF-3 design
- Evaluate RF distribution system options, new
circulator designs - L-band test facility at SLAC (ESB) (FY06/07)
15SLAC End Station B L-Band RF Test Facility
- Build two L-band test stations next to NLCTA in
ESB - Test modulators and klystrons
- Provide rf power for NC accelerator structures
and couplers
16Electron and Positron Sources
- Electron source SLAC, Fermilab
- Continuing photocathode development, begin laser
and gun development - Positron source SLAC, LLNL, Cornell
- Studying target design for undulator,
conventional, and Compton sources - Radiation damage
- Thermal shock / beam damage
- Engineering issues (high rotation speed, remote
handling) - Capture and optics studies
- Normal conducting capture structure design and
fabrication - Complete E-166 polarized positron production
(summer 2005)
17Damping rings
- Development at LBNL, SLAC, Fermilab, ANL, Cornell
- Damping ring design and simulation
- Optics, tuning studies, collective effects
- Wiggler design and optimization
- SEY studies for electron cloud
- Laboratory measurements at SLAC
- Building three chambers for PEP-II installation
to verify solutions - ATF at KEK
- Instrumentation, Beam studies, ATF Kicker
development, FONT/Feather
18Damping Ring Optics
6 km ring
Injected beam
Tracking with injected positron beam in Fermilab
6 km design indicates essentially no loss after 1
damping time
After tracking
- New optics proposed based on PEP-II
non-interleaved sextupole correction ? Pi-cell
and FODO cell designs
Dynamic aperture in Dogbone Damping Ring designs
17 km ring
TME (DESY TDR)
Pi-cell (low a Pep-II)
19Main linacs- Beam Line Design and simulation
- Bunch compressor design SLAC, LBNL, Cornell
- Multiple stage designs are being considered for
reduced energy spread or reduced bunch length - Main linac emittance tuning SLAC, Fermilab,
Cornell - Evaluating emittance tuning procedures
- Considering implications on linac design
(Stronger or weaker lattice desired? BPM
resolution? Laser-straight linac required?
Tolerance to stray fields? Benefits from RF
cavity HOM BPMs?) - Quadrupole alignment and vibration studies SLAC
- BPM, Laser wire, cavity diagnostics tests SLAC,
with TTF, ATF and LCLS
20Global systems-availability and machine protection
- Availability and downtime modeling- SLAC, with
DESY - More to it than just MTBF and MTTR
- Expanding a time-domain simulation written for
USLCTOS - Currently studying impact of low-intensity
conventional positron source in conjunction with
undulator source - Machine protection - SLAC, with DESY
- Just getting started. Current work classifying
scenarios which lead to single-pulse or
single-train damage
21Global systems Civil/Site development
- Sample site development efforts focused on
Illinois site(s) near Fermilab. - Fermilab and SLAC civil engineers are evaluating
five sample sites using a site considerations
matrix-common methodology for all regional sites - The current effort is not intended to select a
potential site, but rather to understand from the
beginning how the features of the sites will
affect design, performance, and cost.
22Global systems Civil/Site development
- Civil design ( tunnels, shallow/deep, terrain
following) tied to site features - Comparison will be made to an ideal reference
design to highlight advantages and disadvantages
- Milestone Descriptions
- Milestone One Snowmass 2005
- Complete Comparative Site Assessment Matrix with
Collaboration with Asian and European Regions - Milestone Two December, 2005
- Identify a Sample Site for Inclusion into the
Reference Design Document - Milestone Three December, 2006
- Complete Conventional Facilities Portion of the
Reference Design Document
23Conclusion
- ILC-Americas is getting organized and
co-ordinated. - A robust program is being developed, in support
of the GDE goals of a baseline configuration this
year, and a reference design report by the end of
2006. - ILC-related RD efforts in the Americas are
growing. To optimally utilize the available
resources, we need to fully co-ordinate the RD
efforts across the regions. This will be one of
the most important functions of the GDE.
24Beam Delivery System
- Optics design and layout (SLAC, Fermilab, UK
groups) - Study variations of BDS with different crossing
angles, collimation systems, L, etc ? understand
tradeoffs - ATF-2 at KEK
- Demonstration of new FFS using ATF beam
- Proposal is being assembled detailed
contributions to be defined - Specialty magnets (SLAC, BNL)
- SC final quadrupoles are being prototyped at BNL
- End Station A Test Facility (SLAC, UK and
University groups) - MDI instrumentation studies, collimator wakefield
studies - Construct IR mock-up
25End Station A Test Facility For Prototypes of
Beam Delivery and IR Components
Collimator design, wakefields (T-480) BPM energy
spectrometer (T-474) Synch Stripe energy
spectrometer (T-475) IP BPMs, kickers EMI
(electro-magnetic interference) IR Mockup
http//www-project.slac.stanford.edu/ilc/testfac/E
SA/esa.html