Title: Resource Registration Update
1Resource Registration Update
- Dana Showalter Patrick Coon
- January 23, 2008
2Resource Registration MP 11
- ERCOT has all registration-related data for all
market participants intending to participate in
the Nodal Market on record - Final RARF submittal due December 31, 2007
- Addendum 1 due to ERCOT by January 31, 2008
- Generator-owned transmission elements
- Additional Private Use Network fields
- Additional fields for Gen, CC, and Wind units
- Addendum 2 New for Combined Cycle
- Combined cycle configuration and transition
- More on this later in this presentation
3Resource Registration Status of Submittals (as
of 1-16-08)
- 210 RARFs
- 167 for Generation Resources and 43 for Load
Resources - 635 Units
- 505 Generation Resource units
- 130 Load Resource units
- Includes mothballed units
- Does not include Distributed Generation, Block
Loads, Retired, or Logical/Virtual units (i.e.
Joint Owned) - QSE Scores
- Lowest score carries (i.e. one red the whole
entity is red) - Generation Resources (97.6 of ERCOT Total MW)
- By MW, 51 Green and 20 Amber
- By RARF, 33 Green and 17 Amber
- Load Resources (2.4 of ERCOT Total MW)
- By MW, 50 Green and 46 Amber
- By RARF, 54 Green and 37 Amber
4Resource Registration Status of RARF Submittals
5Resource Registration Status of RARF Submittals
6Resource Registration Status of RARF Submittals
7Resource Registration Status of RARF Submittals
8Resource Registration Status of RARF Submittals
9Resource Entities Missing Submittals
- 28 Resource Entities missing December 31
submittals - 9 Resource Entities missing November 9 and
December 31 submittals - ERCOT Account Managers are contacting these
companies to verify status - Resource Entities missing RARFs may be reported
at the February 7 TAC meeting - MP 11 metric on scorecards to be updated by
January 25 - Contact NodalMarketTransition_at_ercot.com with
questions or clarifications
10Resource Entities Missing Submittals
- No submittals received for one or more units for
the following Resource Entities - DESERT SKY WIND FARM LP (AEP)
- EQUISTAR CHEMICAL LP
- MATHESON TRI_GAS (LAAR)
- MESQUITE WIND LLC (HORIZON WIND)
- OWENS CORNING (LAAR)
- TEXAS BIG SPRING LP
- TEXAS PETROCHEMICALS LP
- VALERO REFINING - TEXAS LP (RES)
- Contact NodalMarketTransition_at_ercot.com with
questions or clarifications
11Resource Registration - CC Changes and Impact
- Combined Cycle units have the opportunity to
submit registration for all configurations - Usage of configurations downstream is not
confirmed - What does this mean?
- All Combined Cycle facilities will need to
complete an addendum for all desired
configurations (including those included on the
RARF) - The addendum will be the source of all
configuration information in the final RARF - Transition information will be resubmitted as
well - ERCOT will host a WebEx to provide an example of
configurations and transitions as well as to
answer questions - ERCOT will provide opportunities for individual
assistance in completing the addendum
12Resource Registration - CC Changes and Impact
- Timeline
- Week of January 28 Release Addendum 2 to
Resource Entities representing CC facilities - Week of January 28 Host WebEx to discuss
Addendum - February 4 15 Meetings with Resource Entities
as needed - To schedule, send a request to NodalMarketTransiti
on_at_ercot.com Please include preferred time (9am,
10am, or 11am) - February 29 Addendum 2 due to ERCOT
13Resource Mapping MP 10
- ERCOT shall ensure that all participating
Generation Resources in the TN Market have
completed their mapping of Resources to Resource
Nodes and Resources to EPS Meters at the
Generation Facility - ERCOT tasks
- Completing snapshots of NMMS
- Preparing mapping worksheets
- One for each Unit to Resource Node (on hold)
- One for each Unit to EPS meter
- Send zip file to Resource Entity Authorized
Representative - Resource Entity responsibilities
- Verify information and return confirmation form
to ERCOT - If problem, work with ERCOT to get it corrected
14Resource Mapping MP 10
- ERCOT shall ensure that all participating
Generation Resources in the TN Market have
completed their mapping of Resources to Resource
Nodes and Resources to EPS Meters at the
Generation Facility - Two Occurrences
- First to verify what we know at this time for
market trials - Oneline
- Resource to Resource Node Map
- Resource to EPS Meter Map
- Verification/confirmation form to send to ERCOT
- Second as an export from NMMS
- Timeline
- Week of Feb 11 Release to Resource Entities
- February 11 29 Complete corrections as needed
- March 7 Confirmation letters due to ERCOT
- June/July Repeat process with exports from NMMS
Dependent on result of Resource Node location
15Resource Registration Looking Forward
- January 31 Addendum 1 due (Generation Resources
only) - January 28 February 29 Addendum 2 due (CC
only) - February 11 March 7 Resource Mapping
- March 15 End of acceptance of EDS 4 RARF and
conclude data validation of data received through
RARF iterative process - March 15 April 7 Hold on RARF submittals to
create final RARF to send to Resource Entities - April 7 April 25 Resource Entities review and
submit certified RARF to ERCOT - From this point on all submittals must be
certified and on the final RARF form - June/July Resource Mapping NMMS verification
Dates may change to meet NMMS or EDS needs
16Questions???
- Any additional questions and all submittals
regarding the registration process or the RARF
should be directed to - NodalMarketTransition_at_ercot.com