Critical Path Scheduling - PowerPoint PPT Presentation

1 / 82
About This Presentation
Title:

Critical Path Scheduling

Description:

It is the longest path through the project time wise. ... How will weather affect future activities? Are there any trends apparent? ... – PowerPoint PPT presentation

Number of Views:80
Avg rating:3.0/5.0
Slides: 83
Provided by: billmc46
Learn more at: https://www.cns.ou.edu
Category:

less

Transcript and Presenter's Notes

Title: Critical Path Scheduling


1
Critical Path Scheduling
2
Planning Scheduling Process
  • Identify project activities
  • Estimate activity durations
  • Develop the project plan
  • Schedule project activities
  • Review and analyze the schedule
  • Implement the schedule

3
CPM Basics
4
Only Three Inputs Required
  • Break scope into separate activities
  • Estimate durations for each activity
  • Define relationships between activities

5
Example Build a Spot Footing
  • Break into separate activities
  • Excavate to required grade
  • Place forms
  • Tie rebar
  • Place concrete

6
Example Build a (Big) Spot Footing
  • Estimate activity durations
  • Excavate to required grade 1day
  • Place forms 2 days
  • Tie rebar 3 days
  • Place concrete 1 day

7
Example Build a Spot Footing
  • Define relationships

Excavate
Place forms
Place concrete
Start
Tie rebar
8
Now for some
9
Forward Backward Pass
1
2
4
2
4
6
6
7
7
6
6
4
4
2
2
1
2
5
6
3
10

1
2
4
2
4
6
6
7
7
6
6
4
4
2
2
1
2
5
  • The critical path determines PROJECT duration
  • It is the longest path through the project time
    wise.
  • The early times equal the late times on the
    critical path.
  • The difference between the early times and late
    times is float

6
3
11
(No Transcript)
12
ACTIVITY IDENTIFICATION
13
Activity Definition
  • A discrete part of the process with the following
    characteristics
  • Usually consumes time
  • Usually consumes resources
  • Has definable start and finish
  • Are assignable to a single supervisor
  • Are measurable

14
Activity Categories
  • Administration
  • Mobilization / Demobilization
  • Procurement
  • Construction
  • Start-up and Testing

15
Data for Activity Identification
  • Plans and specs
  • Quantity take-off
  • Estimate
  • Contract
  • Pre-construction meetings

16
Criteria for Sub Division of the Work
  • What work has to be done?
  • Where will it be done?
  • Who will be responsible?
  • When will it be performed?
  • How will you do it?

17
Level of Detail
  • Purpose
  • Complexity of Work
  • Time frame
  • Owners requirements
  • Draws based on completed activities?

18
Activity Description
  • Should stand alone
  • Clear
  • Concise
  • Verb (location) Object i.e. Paint west wall

19
Work Breakdown Structure
  • Hierarchical organization
  • Allows consolidation at various levels
  • Outline format

20
Estimating Durations
21
Time Unit
  • Years, Months, Weeks, Days, Hours
  • Use whole numbers and be consistent

22
Determining Duration
  • Duration Work Quantity/ Production Rate
  • Work Quantity - The amount of work to be done
    expressed in units that can be measured in the
    field to report progress.
  • Production Rate - The amount of work (same units
    as work quantity) that a certain crew averages
    per unit of time.

23
Resource Availability
  • Assume material will be available
  • Assume equipment will be available
  • Choose most efficient crew mix
  • Avoid planned overtime

24
Factors Affecting Productivity
  • Nature of the work
  • Labor and equipment productivity
  • Management skill
  • Material and equipment availability
  • Seasonal conditions
  • Work restrictions
  • Quality of work
  • Concurrent activities

25
Sources of Quantity Productivity Data
  • QTO
  • Estimate
  • Experience
  • Outside information
  • Estimating guides (Walkers, Means)
  • Industry and trade organizations
  • Manufacturers, fabricators, and suppliers
  • Specialty Contractors

26
Bar Charts
  • Also called Gantt Charts

27
Advantages
  • Traditional Method
  • Easy to construct and read
  • No computer needed
  • Easily produced by all scheduling software

28
Disadvantages
  • Difficult to depict precedence relationships
  • Difficult to show effects of change

29
Process
  • Identify Activities
  • Estimate Durations
  • Develop Activity Sequence
  • Construct Bar Chart

30
Types of Activity Relationships
  • Physical
  • Safety
  • Resource
  • Preferential

31
Additional Information
  • Cash Flow
  • Resource Loading

32
Fenced Bar Charts
  • Show relationships between activities
  • Limited to a few activities

33
ACTIVITY NETWORK DEVELOPMENT
34
Network Models
  • AON
  • PDM
  • AOA
  • PERT

35
Network Model Characteristics
  • Discrete Activities
  • Deterministic Durations
  • Deterministic Logic
  • Activity Flow

36
Network Elements
  • Activities
  • Milestones
  • Relationships
  • Physical
  • Safety
  • Resource
  • Preferential

37
AON
  • Unique Activity Number
  • Unique Description
  • Estimated Duration
  • Relationships to other Activities
  • Beginning and Ending Activities

38
Logic
39
Logic Errors
  • Incorrect Logic
  • Redundant Logic
  • Logic Loops
  • Hangers

40
Activity Numbers
  • Used to identify the activity
  • Can have a structure used to categorize
    activities (WBS)
  • Possible Categories
  • CSI Division
  • Responsibility
  • Location
  • Activity type (NIC, Change order)

41
Other Codes
  • Group and sort activities
  • Coordination with estimating and accounting

42
Network Schedule Calculations
  • Early Start
  • Early Finish
  • Late Start
  • Late Finish
  • Total Float
  • Free Float
  • Critical Path

43
Forward Pass
  • Calculates the earliest each activity can start
    and finish
  • Calculates the minimum overall duration of the
    project

44
Backward Pass
  • Calculates the latest that each activity can
    start and finish without delaying the project

45
Total Float
  • Late start minus early start or LF - LS
  • The amount of time an activity can be delayed
    without delaying the project
  • Assumes activity started on ES date

46
Free Float
  • The amount of time an activity can be delayed
    without delaying any other activity
  • Assumes activity started on ES date

47
Network Report
  • Activity Description
  • Activity Number
  • Planned Duration
  • Early Start
  • Early Finish
  • Late Start
  • Late Finish
  • Total Float
  • Free Float

48
Critical Path
  • Longest path through network
  • Establishes overall duration
  • Continuous chain of activities with zero float

49
Activity Start / Finish Conventions
  • End-of-day
  • Beginning-of-day
  • Combination

50
Project Calendar
  • Assigns job days (ordinal days) to calendar days

51
Calendar Information
  • Project start date
  • Rest days (week end)
  • Holidays
  • Work days
  • Project calendar (for manual conversions)

52
Multiple Calendars
  • Normal (five, 8 hour days)
  • Elapsed Time ( seven, 24 hour days)
  • Four, 10 hour days

53
Reports and Graphics
54
Communication
  • Who will use information?
  • What format should be used?
  • What information should be included?
  • How should information be organized?

55
Who is the Report for?
  • Construction firms upper management
  • Summary info on progress cost cash flow
  • Owner and designer
  • Summary info on progress cost cash flow
  • Detailed info on key systems

56
Who is the Report for?
  • Project Management
  • Detailed info on whole job for near term
  • Resource information
  • Summary info on progress cost

57
Who is the Report for?
  • Superintendents
  • Detailed info on whole job for near term
  • Resource information
  • Might be better done with spreadsheet
  • Foremen
  • Detailed information on specific systems

58
Format
  • Tabular
  • Narrative
  • Calendar
  • Bar Chart
  • Network diagram
  • Graphs

59
What Information
  • ONLY that which is needed
  • Could a picture be worth 999 words?

60
How Organized
  • Sorts
  • Activity Number
  • Activity Codes
  • Early Start
  • Total Float
  • Etc..

61
Data Transfer
  • Information can be organized for data transfer as
    well as for reporting information
  • To from CAD
  • To from estimating programs
  • To from spreadsheets
  • To from data bases
  • To word processing

62
Specifying Scheduling Requirements
  • State format, content, frequency
  • Limit requirements to only data needed
  • Handouts

63
Reviewing and Analyzing the Schedule
64
Reviewing the Schedule
  • Is the schedule complete?
  • Are durations reasonable?
  • Are relationships complete?
  • Are the calendars correct?
  • Does the scheduled finish meet contract
    requirements?
  • Are all contractual requirements met?

65
Analyzing the Schedule
  • Is the critical path(s) reasonable?
  • What activities are near critical?
  • How does the work flow?
  • Are there conflicts between concurrent
    activities?
  • Are resources over or under allocated?
  • Can subs and suppliers meet their scheduled
    dates?
  • Are any activities scheduled out of season?

66
Short Interval Scheduling
67
Two general types of scheduling
  • Overall Project (what we have been talking about)
  • Day to day
  • Look ahead scheduling
  • Production scheduling
  • Differentiated by whos doing it and why

68
Look Ahead Scheduling
  • Coordinate wide array of work over a short time
  • Greater attention to balancing resources

69
Production Scheduling
  • Detailed schedule for a particular process
  • Often uses a smaller time unit for durations
    (hour)
  • Matrix schedules (ie. resource usage view in MP)

70
(No Transcript)
71
Updating the Schedule
72
Purpose Of Updating The Schedule
  • Evaluate Project Status
  • Predict Completion Date
  • Create A Historical Record

73
Baseline Schedule
74
Frequency of Updates
  • Project complexity
  • When an unexpected event occurs
  • When Specified

75
Step By Step Procedure
  • Gather activity status information
  • Determine schedule status
  • Analyze schedule status
  • Modify and revise the schedule
  • Analyze the revised schedule
  • Implement the updated schedule

76
Activity Status
  • Actual start date
  • Actual finish date
  • Percent complete
  • Work in place
  • Time expended
  • Cost incurred
  • Resources used
  • Remaining duration

77
Gathering Status Info
  • Direct observation
  • Update meetings
  • Field progress reports
  • Turnaround reports
  • Photographs videotapes

78
Analysis of Updated Schedule
  • Against what baseline is this schedule compared?
  • What is the planned completion date?
  • Has the critical path shifted?
  • Where have the floats changed?
  • How will weather affect future activities?
  • Are there any trends apparent?
  • Have there been any scope changes since last
    update?

79
Modify Revise Schedule
  • Revise the network logic
  • Revise activity durations
  • Adding or deleting activities

80
Record Keeping
  • Code notes and calculations to activities
  • Keep both hard and electronic copies of each
    iteration of the schedule

81
Using the Schedule to analyze the Impact of Change
  • Isolate change
  • Calculate schedule with without change

82
Out of Sequence Work
  • Only happens on non-physical logic relationships
  • Two choices
  • Preserve Schedule Logic (usually preferred)
  • Eliminate Schedule Logic
Write a Comment
User Comments (0)
About PowerShow.com