EVLA Advisory Committee Meeting - PowerPoint PPT Presentation

About This Presentation
Title:

EVLA Advisory Committee Meeting

Description:

It may be necessary to consider descoping aspects of the EVLA ... Alternatively, there are some delay' options. ... It is unwise policy to remove frequency bands. ... – PowerPoint PPT presentation

Number of Views:20
Avg rating:3.0/5.0
Slides: 23
Provided by: aoc9
Learn more at: http://www.aoc.nrao.edu
Category:

less

Transcript and Presenter's Notes

Title: EVLA Advisory Committee Meeting


1
Scientific Impact of Descopes
  • Rick Perley
  • Version 3may06, 12PM

2
The Problem
  • Contingency is getting short.
  • It may be necessary to consider descoping aspects
    of the EVLA
  • We can consider descopes in one or both
  • Hardware
  • Software
  • Alternatively, there are some delay options.
  • I review here the impact of these options on the
    scientific productivity of the EVLA.

3
Hardware Descopes
  • We have considered
  • Removal of one or more bands
  • X, Ku, S, Ka are the possibilities
  • Reduction of bandwidth from 16 to 8 GHz.
  • Reduce number of outfitted antennas.
  • Removal of special solar observing hardware.
  • Items 1 and 2 were discussed last year.

4
Bandwidth Reduction
  • Significant savings possible but mostly in
    correlator. Not our money to save, and
    politically very tricky.
  • Our savings come from DTS system. But, much of
    the needed components for all antennas already
    purchased.
  • Scientific impact 40 loss of continuum
    sensitivity per unit time at K, Ka and Q bands,
    less on Ku. None other bands.
  • It is too late to obtain significant savings
    through this descope option.

5
Band Descopes
  • Bands we could consider
  • Total Parts Only
  • S-Band 1.4M 400K
  • X-Band 1.0M 200K
  • Ku-Band 1.3M 200K
  • Ka-Band 1.2M 200K
  • I consider the scientific implications of each
    band listed.

6
X-Band
  • The VLA has a good X-band system operating from
    7.8 8.8 GHz.
  • It has been argued that simply leaving this
    legacy system in place would be sufficient.
  • This is a poor argument
  • Continuum sensitivity will be less than half that
    of C-band.
  • Only spectral observations of transitions lying
    between 8 and 8.8 GHz would be useful.
  • X-band would become both legacy and vestigial.
  • Nevertheless this is the easiest band descope.

7
S-Band vs. U-Band?
  • Removal of X-band might be considered an easy
    decision but the decision of which band is next
    to go will not be easy.
  • The debate of which is more scientifically
    productive will surely pit non-thermal vs.
    thermal science interests.
  • Who is to say what is more valuable?
  • Consider the following

8
S-Band
  • This band will become the band of choice for
    non-thermal imaging
  • Likely better than twice the sensitivity of
    L-band.
  • Twice the total bandwidth,
  • At least three times the available (RFI-free)
    bandwidth
  • Nearly 1.5 times the efficiency.
  • We anticipate superb performance from this band.

9
Examples of Key Lost Science
  • TBD? (Do we need to)?

10
Ku-Band
  • This is a key thermal science band.
  • Transition zone (from optically thick to
    optically thin) for the highest EM HII regions.
  • Dozens of molecular and atomic spectral
    transitions.
  • Lowest frequency where precise dust emission
    observations can be made (lowest optical depth to
    dust extinction).
  • Lowest frequency ( highest redshift) for key
    high frequency molecular studies (e.g. CO 1-0 at
    z 5.8).
  • Could be argued this is the highest really good
    band for non-thermal science.

11
Examples of Key Lost Science
12
Ka-Band?
  • Early in the project, this badn was identified
    for accelerated development rich science mine!
  • Relatively unexplored spectral region, esp. good
    for thermal emission processes.
  • Hundreds of molecular spectral transitions.
  • Low sky emission between H2O and O2 emission.
    Decent efficiency, excellent Tsys.
  • Testing of the designed horn/polarizer is about
    to begin.
  • We could review this decision, if necessary.

13
Ka-Band Science
  • Thermal Science!
  • HII regions, dusty obscured disks, star forming
    regions.
  • Hundreds of spectral transitions.
  • Hi-z lines.
  • Excellent continuum sensitivity far better than
    Q-band, even for optically thick thermal
    emission.

14
My Opinion
  • Full Frequency Coverage a Primary Goal of this
    project.
  • Any retreat is an admission of failure by NRAO
    (and by AUI!)
  • The science impact of band descopes is enormous.
    At least 10 years would be needed to recover a
    descoped band.
  • If we must cut back, then an acceptable
    compromise is to simply purchase the parts, and
    build the new systems in post-construction years.
  • This, in essence, shifts the implementation costs
    to operations.

15
Solar Mode Descopes
  • Not a lot of money (200K)
  • Scientific impact limited to the solar
    community and solar science.
  • Solar community use of VLA is now very light
    (nearly non-existent).
  • Only two bands (L-band and one other, currently
    not identified) budgeted for special solar mode
    systems.

16
Implementation Descope?
  • A suggestion has been made to reduce the number
    of EVLA-outfitted antennas.
  • Savings limited in many areas we have already
    bought in bulk for the whole project.
  • Very strong science impact
  • Point-source sensitivity reduced by linear
    fraction.
  • Imaging capability (particularly for complex
    fields) reduced by a greater fractions
    baselines rise as N2.
  • This descope would affect all bands, all
    observers, all programs, all science.
  • I think this idea is a non-starter. It should
    be dismissed at the highest level, now.

17
Software Descopes
  • Software in three major areas
  • MC
  • E2E
  • Post-Processing.
  • We consider MC as sacrosanct. The group is of
    just-sufficient size.
  • Post-processing group already minimal
    sub-critical. No fat here!
  • We look at e2e for descope opportunities.

18
Descopes in e2e?
  • Level 2 and Level 3 software e2e deliverables
    already descoped.
  • Budget is currently unable to provide all Level
    1 deliverables.
  • Three more staff needed to achieve Level 1
    deliverables.
  • This does not include extra staff for imaging
    algorithm RD.
  • Approximately 1M of contingency already utilized
    in addressing shortfalls in e2e.
  • Could review Level 1, for further descopes.
  • Probable course of action is to delay some
    deliverables.
  • Effect would be to move some to operations.

19
E2E Descope Options
  • (A list of Level 1 deliverables which would be
    deferred/removed, should we have to go this route
    )
  • (Perhaps a reminder that e2e, and the One
    Observatory, is an NRAO/AUI obligation, and that
    the failure of the 2000 DMD model is not the
    fault of the EVLA Project).
  • (Hence, more resources from NRAO/CV, and AUI, are
    needed).

20
Deferment Options
  • Although not formally a descope, perhaps the
    best options are to defer planned capability.
  • Hardware Already mentioned that costs could be
    offset into future operations by purchasing
    early, with implementation deferred until post
    2012.
  • Not a great option, but doable, deferring xxxK
    to future generations.
  • Risk Much better receivers might be available
    later? (I doubt this, given the existing
    capabilities).

21
Deferment Options
  • Software.
  • Clearly an area where deferment is possible
    even likely
  • Real-time scheduling Can be done by a person
    indefinitely, until good software can be written.
  • Automatic image generation Can be done by
    trained individuals until more automated systems
    can cover harder and harder configuration/frequenc
    y/weather combinations.
  • Post-processing software. Although development
    of improved algorithms is non-deferrable, we can
    match scheduling of tough experiments
    (full-field, noise-limited, high-resolution
    polarimetric imaging at L-band, for example)
    until the software is ready.
  • Nothing new in this done by the VLA.
  • Other examples

22
Summary
  • Advertised scientific productivity of EVLA
    requires all hardware and software deliverables
    to be met.
  • It is unwise policy to remove frequency bands.
    History shows recovery will be at least a decade
    away.
  • All software deliverables in e2e are key for full
    scientific usage especially by those not
    trained to be radio astronomers.
  • The preferred solution is an increase in the
    budget sufficient to keep us on track and on
    time. Estimate of this 5M. ( only 6 of
    total EVLA1 budget).
  • The acceptable, but not preferable, means is
    deferment of promised capability into the
    operational years.
Write a Comment
User Comments (0)
About PowerShow.com