GLAST Large Area Telescope: Calorimeter (WBS 4.1.5) - PowerPoint PPT Presentation

1 / 23
About This Presentation
Title:

GLAST Large Area Telescope: Calorimeter (WBS 4.1.5)

Description:

The first two crystal optical test benches have been completed at NRL and have ... Flex cable design for connection of PIN to readout electronics has been iterated ... – PowerPoint PPT presentation

Number of Views:28
Avg rating:3.0/5.0
Slides: 24
Provided by: WNeilJ9
Category:

less

Transcript and Presenter's Notes

Title: GLAST Large Area Telescope: Calorimeter (WBS 4.1.5)


1
GLAST Large Area TelescopeCalorimeter (WBS
4.1.5)
  • W. Neil Johnson
  • Naval Research Lab
  • Calorimeter Subsystem Manager
  • johnson_at_gamma.nrl.navy.mil

2
Calorimeter Subsystem
  • Outline
  • Programmatic Status
  • Lehman Review Recommendation Status
  • Technical Progress
  • Assembly Test
  • Resources
  • Issues / Concerns

3
Programmatic Status
  • In France the CNES Scientific Program committee
    issued positive recommendation and re-confirmed
    the French participation in GLAST.
  • A CNES Preliminary Requirements Review will occur
    in October to authorize the technical approach
    and French organization. This review will secure
    the budget for the implementation phase.
  • Management activities have focused on creating
    CAL WBS, revised plans, schedules, and costs for
    the development and fabrication of the
    calorimeter
  • Interim Design Review held in Paris, June 11
    13, focused on detailed review of the Swedish and
    French responsibilities, interfaces, work flow
    and schedules.
  • Financial problems in France for this FY have
    been resolved and, as a result, the PIN
    photodiode procurement (US) for EM diodes was
    released.
  • Significant efforts have been placed in improving
    or creating CAL documentation for PDR required
    specifications, plans and procedures have been
    identified and responsible persons have been
    assigned.
  • Completed CAL Subsystem Peer Design Review on
    July 27.

4
Lehman Review Recommendation Status
  • Sign and implement international agreements
  • Drafts exist of MoA among participating
    laboratories and of NASA-CNES International LoA.
  • MoA has been updated by US and French
    participants no apparent action on LoA.
    Successful PRR should permit French signatures.
  • Organize French efforts and commitment to roles
    and responsibilities
  • Done. Documented in MoA and WBS.
  • Develop bottoms up resource-loaded schedule
  • Done. Delivered to PMCS on 7/20/01. Revisions
    continue.
  • Update the cost estimate and assign adequate
    contingency
  • Bottoms up costing completed. Contingency
    analysis on-going. Overall funding and profile
    are problems.
  • Resolve PIN diode glue problems
  • Resources have been applied. Test and selection
    program identified. Backup solution identified.
    Tests are continuing.
  • Define responsibilities for procurement,
    qualification and testing of ASICs
  • Done. SLAC designs and tests prototypes. NRL
    does the rest.

5
Technical Progress
  • CsI Crystals
  • The first two crystal optical test benches have
    been completed at NRL and have been shipped to
    Sweden.
  • First metrology test bench has been completed in
    Sweden.
  • First 24 crystals from Amcrys-H have been
    received and tested in Sweden.
  • The crystals were generally as expected although
    several crystals were slightly out of
    specification. These out of spec conditions were
    generally either over sized or incorrect light
    tapering along the crystal.
  • PIN Photodiode
  • 1st photodiode delivery expected Aug 15th.
  • Flex cable design for connection of PIN to
    readout electronics has been iterated with
    mechanical and electrical engineering.

13 CsI Crystals from Amcrys-H
BTEM PIN diode and flex cable
6
Technical Progress (2)
  • Crystal Detector Elements (CDE)
  • New baseline for CDE includes optical wrapping
    (VM2000) attached to CsI crystal rather than
    applied to structure walls.
  • Mylar tape on corner bevels holds 4 VM2000
    strips.

7
Technical Progress (3)
  • PIN Photodiode CsI Crystal Bonding
  • Studies of potential bonding material continue at
    IN2P3 and NRL.
  • IN2P3 contract with CETIM to model the bonding
    problem
  • Rejects hard epoxies
  • Soft epoxy and silicone are OK.
  • Bonding Plan
  • Test soft epoxy silicone elastomer with primer
  • A vacuum gap is the backup solution.
  • Thermal (-30C to 50C) cycling in vacuum
    environment tests between glass and CsI with
    surface preparation.
  • The type of bonding for the EM will be chosen
    after 12 thermal-vac cycles. A set of
    photodiodes that are larger than CAL diode will
    be bonded on CsI and ultimately tested for 100
    cycles.
  • Aging tests ( thermal cycling and irradiation)
    are performed on these glues with particular
    attention to transparencies
  • Bonding for FM will be reviewed after completion
    of test program and experience with EM
    fabrication.

8
Technical Progress (4)
  • Pre Electronics Module (PEM)
  • Verification Model 2 (VM2) tooling has been
    designed and is being fabricated
  • Baseplate design has been modified to meet LAT
    Grid stiffness requirements.
  • Preliminary thermal and structural analysis have
    been completed.
  • VM2 will contain 12 CDE and 84 mass dummies
  • Science performance evaluation before LAT PDR

9
Technical Progress (5)
  • First prototype GCFE1 ASIC received at SLAC in
    June 01
  • Contains all functionality
  • Analog Multi-gain amplification, shaping,
    auto-range gain selection, trigger
    discriminators, five 7-bit DACs
  • Digital VHDL synthesized and auto placerouted
    digital circuits (10,000 gates) for
    configuration/mode registers, writeread
    state-machine, data-acquisition state-machine
    logic, etc.
  • Digital circuits are fully functional, tested up
    to limit of test-box, 40 MHz, (f20 MHz is
    nominal)
  • Found capacitor-to-capacitor short of
    calibration-circuit to gain-selection circuit.
    Bug discovered in linear capacitor extract
    software
  • Analog amplifier and shaper are functional after
    cut of trace on chip
  • Single range calibration, charge-amplifier with
    external gain select, shaping, post-amplification,
    auto-ranging, acquisition sequence,
    rail-amplifiers, trigger discriminators are fully
    operational. Performance tests are in progress.
  • 2nd Version GCFE2 received last week, has
    Single-Event Upset hardened registers
    incorporated
  • 3rd version GCFE3 with short fixed to be
    submitted July 28.

10
Assembly Test in Europe
  • CsI crystals delivered to Sweden at rate of 200
    per month.
  • Starts early. Last crystals delivered 5 months
    before needed.
  • PIN photodiodes delivered to France at rate of
    600 per 5 weeks.
  • Delivery rate not a problem for Hamamatsu.
  • CDE Assembly and Test at rate of 200 per month
    ( 6 days per crystal)
  • PEM Assembly in France requires 7 weeks per
    module
  • Assembly, Metrology
  • Cosmic muons
  • Environmental Thermal vac vibration (TBR)
  • Final test (cosmic muons)

Total Processing Time 9 weeks per module
11
Module Assembly and Test Schedule
  • Duration of assembly and test phases (working
    days for each Module)

Phase Module Module Module Module
EM QM, 1-2 3-6 7-16
PEM Acceptance 14 9 8 5
Elect Integration 25 14 10 9
Calibration 12 6 5 4
Environmental 28 17 11 11
Pre-ship Verification 10 7 6 6
Margin 5 5 8 8
Total per Module 94 58 48 43
  • The challenge sustained receipt, assembly, test
    and delivery of a module every two weeks.
  • One PEM arrives at NRL every two weeks.
  • Five Modules in process at once.
  • One Module ships to LAT Integration Site (SLAC)
    every two weeks.
  • (but last Module arrives at SLAC five weeks
    before required date.)

12
Assembly and Test Schedule
Module Planned Module Delivery Date LAT Schedule Integration Date Weeks delivery is early
Qual Model (FM A) 13 May 03 15 Aug 03 13
Flight Spare (FM B) 03 Jun 03 15 Aug 03 10
Flight Model 1 29 Jul 03 03 Nov 03 14
Flight Model 2 19 Aug 03 03 Nov 03 11
Flight Model 3 27 Aug 03 02 Jan 04 18
Flight Model 4 10 Sep 03 02 Jan 04 16
Flight Model 5 24 Sep 03 15 Jan 04 17
Flight Model 6 08 Oct 03 15 Jan 04 14
Flight Model 7 15 Oct 03 29 Jan 04 15
Flight Model 8 29 Oct 03 29 Jan 04 13
Flight Model 9 12 Nov 03 12 Feb 04 13
Flight Model 10 26 Nov 03 12 Feb 04 11
Flight Model 11 10 Dec 03 26 Feb 04 11
Flight Model 12 24 Dec 03 26 Feb 04 9
Flight Model 13 07 Jan 04 10 Mar 04 9
Flight Model 14 21 Jan 04 10 Mar 04 7
Flight Model 15 04 Feb 04 24 Mar 04 7
Flight Model 16 18 Feb 04 24 Mar 04 5
  • Delivery for integration into LAT
  • Instrument integration schedule specifies
    required Ready For Integration (RFI) dates.
  • RFI rate Two Modules every two weeks.
  • Too much work in parallel, so well start earlier
    and stretch deliveries.
  • Typical delivery rate One Module every two
    weeks.
  • Plan FMs arrive at LAT Integration Site 5 to 18
    weeks earlier than required.
  • Some margin for slippage.

13
Resources - Mass Estimate
Mass Reserve Analysis 90 of reserve held at LAT
level
14
Resources - Power Estimate
Conditioned Power at 3.3 70 V For each AFEE
board (4 / Module)
Power Reserve Analysis 75 of reserve held at
LAT level
15
Resources - Cost Estimate
16
Cost Comparison w/ Proposal
17
Issues / Concerns
  • CAL project is working hard to make up for lost
    time. Additional personnel are being added in US
    and France to support engineering development.
  • Near term schedule to CDR will be a challenge.
    Critical near term milestones include
  • Determination of the PIN diode bonding solution
    and verifying its ability to meet the performance
    and environmental requirements.
  • Completion of VM2 prototype, demonstrating
    science performance (before PDR) as well as
    mechanical design verification (post PDR).
  • Completion of GCFE analog ASIC performance
    testing and obtaining completely functional parts
    for EM fabrication.
  • Completion of EM fabrication and test program
    prior to CDR.
  • Revised CAL cost and schedule have just recently
    (7/20) been submitted to SLAC.
  • CAL funding is insufficient and profile is not
    optimal. Resources lost in FY 02 reappear too
    late (FY 04) to be of much use.
  • More iterations are required
  • Environmental test plan needs more consideration.
  • Cost issues
  • Over-testing issues

18
Backup Material
19
Test Matrix
20
Thermal Simulation of Bonding to CsI
  • Thermal (-30,20) simulation of constraints on
    different glues curing at 20C by CETIM

21
Development Program
  • PEM VM2 Prototype
  • Mechanical Model w/ 12 CDE and 84 dummy crystals
  • CDE Performance testing before LAT PDR
  • Environmental testing completed by Dec 01
  • Front End Electronics
  • GCFE Test Board Radiation Testing - Nov 01
  • VM Board, GCFE GCRC FPGA
  • Functional testing with CDE
  • Radiation testing Jan 02
  • Engineering Model (EM)
  • Form and function of flight units, commercial
    grade parts where required, fully populated PEM
  • Functional testing
  • Environmental testing
  • Beam tests
  • Delivered to SLAC for TDF, software development

22
VM2 EM Development
23
Current Estimate vs Funding
Write a Comment
User Comments (0)
About PowerShow.com