Challenges for Reliable Offshore Transformers - PowerPoint PPT Presentation

1 / 19
About This Presentation
Title:

Challenges for Reliable Offshore Transformers

Description:

Medium Voltage Transformer has to be designed as generator step-up transformer ... Tins 98 C. Thermal stresses give mechanical stresses and accelerated ageing ... – PowerPoint PPT presentation

Number of Views:34
Avg rating:3.0/5.0
Slides: 20
Provided by: mariod4
Category:

less

Transcript and Presenter's Notes

Title: Challenges for Reliable Offshore Transformers


1
Challenges forReliable Offshore Transformers
  • Dr. Jan Declercq, Raymond Van Schevensteen
  • Pauwels International N.V.
  • Belgium

2
Transformers as critical components
  • Wind turbines are electricity generator units
    therefore all components are critical
  • Mechanical blades, gearbox, tower,
  • Electrical generator, converter, transformer,
    circuit breaker, control unit,
  • Medium Voltage Transformer has to be designed as
    generator step-up transformer and fully
    integrated in wind turbine performance and
    specifications and now Multi Megawatt Turbines
    for offshore installation

3
Operating conditions are different
  • Normal transformer in normal environment1000 kVA
    in apartment

4
Operating conditions are different
  • Generator step-up transformer in WTG

5
Operating conditions are different
  • Generator step-up transformer in wind
    turbineMulti Mega Watt offshore

6
So MMW WTG needs GSU Transformer
  • EHV transmission Generation
  • 100 MW gt220 kV
  • Transmission
  • Sub-transmission 110 70 kV
    Embedded generation
  • Distribution 0.5-4 MW 30 kV

Overloading, power quality, economics,
environment, maintenance, reliability
7
Types of medium voltage transformers
  • Mineral liquid-filled transformers
  • Cast resin transformers
  • SLIM and Bio-SLIM technologyFire
    bio-degradable liquid and Nomex insulation

Same operating range of voltages and power What
about other specifications?
8
Functional Specifications of transformers
  • Power
  • Liquid-filled up to 10 MVA and high voltages 36
    kV and above
  • No load losses
  • As low as possible, always energized
  • Liquid filled 50 less losses compared to dry
    type
  • Ex. 2 kW 8760 h/y 0.05 EUR/kWh per turbine
    per year
  • Load losses at working temperature customized to
    needs
  • Medium voltage
  • 12 kV, 24 kV, 36 kV insulation level up to BIL
    200 kV
  • Low Voltage
  • 400 V, 660 V, 690 V, 1000 V, 3000 V, 6000 V
  • Impedance
  • 6 up to 14 for weak grids
  • Dimensions
  • Mass for nacelle, reduced dimensions, fits the
    door

These specifications are not sufficient to
guarantee performance and reliability
9
Operating conditions Thermal Stresses
  • Average 60 loading but
  • Full loading for several days Short term peak
    overloads Sharp load fluctuations HarmonicsHigh
    er air temperature in turbine

2,000
1,500
1,000
0
200
400
600
800
1000
1200
1400
1600
10
Operating conditions Thermal Stresses
Tins 98 C
Current I Losses RI2 Temperature Lifetime
Load P
Thermal stresses give mechanical stresses and
accelerated ageing So verify insulation
materials, overload tests, higher MVA, cooling
inside
11
Operating conditions Electrical Stresses
  • Different electrical environment
  • Switching surges from Circuit Breakers
  • Overfluxing from overvoltages
  • Lightning strikes
  • Frequency variations
  • Voltage dips
  • Causing higher electrical stresses on electrical
    insulation system
  • Increased risk for initiating Partial Discharges
  • So verify electrical performance, specify extra
    testing
  • Example PD tests, chopped wave

12
Switching surges
RESONANCES IN TRANSFORMER WINDINGS
SOURCE
VICTIM
COUPLING
It is an EMC problem breaker and transformer can
be less compatible in the specific network
arrangement
13
Operating conditions Mechanical Stresses
  • Mechanical environment
  • Compact design
  • Optimized dimensions for inside installation
  • Optimized connections
  • In case of nacelle design, vibration
    testsincluding connection of cables

Verify mechanical design and test
accordingly Verify sensitivity of mechanical
stresses on electrical insulation system
14
Operating conditions Chemical Stresses
  • Environment
  • Cooling air
  • Humidity
  • Dust, salt
  • Aggressive environment
  • People

Verify protection of electrical system Specify
higher IP class, C5 offshore painting, air
filters, extra housing Maintenance interventions
for transformer or peripherial equipment
15
Operating conditions Safety
  • Specify good protection and materialsCast resin
    F1 or class K3 liquid

Cast resin transformer versus silicone liquid
filled transformer tested according Cenelec
16
Operating conditions Safety
  • Tests performed at Ineris France, February and
    April 2004

17
New challenges
  • Wind offshore
  • WTG go to higher MVA ratings from 2 MW to 6 MW
  • Connection voltages mostly 33 kV
  • Extreme reliability (MTBF gt 500 years)
  • Reduced maintenance

So optimize transformer technology, design,
manufacturing and testing to meet the wind
turbine demands
18
New markets
  • Wind offshore
  • gt3 MVA transformers for offshore and nacelle
  • UK, 7 GW projects
  • Belgium, NL 300 MW
  • Spain, 2000 MW
  • Denmark, 400 MW
  • Germany, 68 GW

19
Conclusions for offshore transformers
  • Different transformer technologies are available
    for multi-megawatt turbines
  • Dimensions, losses, reliability (MTBF),
    protection, electrical environment are important
    because the operating conditions in a turbine are
    severe!
  • Fire behavior of dry type and high temperature
    liquid filled transformers are comparable
  • Good protection and prevention is always needed,
    independent of transformer technology
  • Verify compatibility for aggressive offshore
    environment
  • Improve specifications for WTG transformers
  • Improve testing specifications for WTG
    transformers
  • IEC TC14 Transformer Committee will write
    standards for wind turbine use (approved 2005,
    start 2006)
Write a Comment
User Comments (0)
About PowerShow.com