Title: Congestion Management Settlement Credits
1Congestion Management Settlement Credits
2Market Design Principles
- The price of energy at each time and place should
reflect the marginal cost of producing or not
consuming one more unit of energy (at that time
and place) - Dispatchable market participants should be
compensated for the effects of constraints
3Congestion
- Occurs when physical capability of the
transmission system cannot meet market
requirements
4Operating Profit
5Operating Profit
- Operating Profit is the difference between
operating cost and revenue - Market Rules written assuming participants bid
and offer based on marginal benefit/cost - Marginal Cost - Cost of producing next MW
- Marginal Benefit - Benefit of consuming next MW
6OP Revenue - Cost
Price (/MWh)
30
25
MCP 20
15
10
5
100
80
60
40
20
0
MQSI60
Quantity (MW)
7Skill Check
8Skill Check
- Generator A offer
- 0-20 MW 15
- 21-30 MW 25
- 31 - 40 MW 100
- Dispatched to 30 MW
- Load B bid
- 0-10 MW 1,000
- 11-20 MW 500
- 21-30 MW 20
- Dispatched to 20 MW
If MCP is 30, what is the OP for A and B?
9Congestion Management Settlement Credits
10Congestion Management Settlement Credit
- CMSC payments are based on the difference between
the Operating Profit that would result from the
Market Schedule and Operating Profit resulting
from the Dispatch Instruction
11Market Schedule
no transmission line limit
- Requirement is
- 190 MW
- Gen 1 100 MW
- Gen 2 90 MW
- MCP 20
- GEN 3 does not run
Region 2
Region 1
12Transmission Congestion
Generator 1 100 MW 15
Load 190 MW
Generator 2 100 MW 20
Generator 3 100 MW 25
150 MW transmission line limit
- Requirement is
- 190 MW
- Gen 1 100 MW
- Gen 2 50 MW
- Gen 3 40 MW
- MCP 20
Region 2
Region 1
13CMSC
- For Generator 2 in this case
- MQSI 90 Offer 20
- DQSI 50 MCP 20
14CMSC
- For Generator 3 in this case
- MQSI 0 Offer 25
- DQSI 40 MCP 20
15Gen 1- Constrained Off
Load 190 MW
Generator 1 100 MW 15
95 MW limit
Generator 2 100 MW 20
Generator 3 100 MW 25
150 MW transmission line limit
- Requirement is
- 190 MW
- Gen 1 95 MW
- Gen 2 55 MW
- Gen 3 40 MW
- MCP 20
Region 2
Region 1
16Constrained Off Payment
- Generator 1
- Market Schedule 100 MW
- Dispatch 95 MW
- Offer 15 /MWh
- MCP 20 /MWh
17Gen 2 - Constrained Off
Load 190 MW
Generator 1 100 MW 15
95MW
Generator 2 100 MW 20
Generator 3 100 MW 25
150 MW transmission line limit
100MW
- Requirement is
- 190 MW
- Gen 1 95 MW
- Gen 2 55 MW
- Gen 3 40 MW
- MCP 20
Region 2
Region 1
18Constrained Off Payment
- Generator 2
- Market Schedule 90 MW
- Dispatch 55 MW
- Offer 20 /MWh
- MCP 20 /MWh
19Constrained On Payment
- Generator 3
- Market Schedule 0
- Dispatch 40 MW
- Offer 25
- MCP 20 /MWh
20Constraint Payments
- When Actual Quantity Different than Dispatch
Quantity
21Gen 1- Constrained Off
Load 190 MW
Generator 1 100 MW 15
95 MW limit
Generator 2 100 MW 20
Generator 3 100 MW 25
150 MW transmission line limit
- Requirement is
- 190 MW
- Gen 1 95 MW
- Gen 2 55 MW
- Gen 3 40 MW
- MCP 20
Region 1
Region 2
22Constraint Payments
- MQSI 0 MW, DQSI40 MW, AQEI 50MW
- MCP 20 Offer 25
23CMSC for a Dispatchable Load
- Load may be dispatched off or on
- Any time constrained and unconstrained are
different, possibility exists for CMSC
24CMSC for a Dispatchable Load
- E.G.
- Load A bids for 100 MW at 2,000
- Market Clearing Price 100
- Load A is dispatched to only 75 MW
- At a bid price of 2,000 Load A will be scheduled
by the unconstrained algorithm for all 100 MW
25CMSC for a Dispatchable Load
- Bid 2,000 MCP 100
- MQSI 100 MW, DQSI 75 MW
- CMSC OP(MQSI) - OP(DQSI) (2,000 -
100) x 100 - (2,000 - 100)
x 75) 1900 x 100 - 1900 x 75
47,500 - The lost Operating Profit is 47,500
26Negative CMSC
- CMSC payments bring the participant back to the
market schedule operating profit - Generally CMSC payments will be a top-up to
restore operating profit - Sometimes the schedule would lead to lower profit
than dispatch instructions
27CMSC
- CMSC payments bring the participant back to the
market schedule operating profit - While CMSC can be negative, it is more often a
payment to participants - The cost of CMSC is recovered from loads based on
their activity in the market