Title: Muon PDT Commissioning Status


1
Muon PDT Commissioning Status
  • Neeti Parashar
  • Northeastern University
  • for the
  • DØ Muon Upgrade Group

2
  • Which PDTs ?
  • B and C-layer PDTs.
  • All are 3 deck PDTs (72 wires, 3 Front_End
    Boards, 1 Control Board).
  • On east side, on the top.
  • PDTs 111, 121, 131, 211, 221, 231.
  • PDTs Readout
  • The above group of 6 PDTs.
  • PDTs 131 and 231 read before.
  • Noticed synchronization error.
  • ? Crossing numbers mismatch.
  • Critical issue
  • Resolve this sync. Error.

3
PDT Front_End and Readout Setup
FEB
1
CB
Muon Readout Crate
2
PDT
3
MFC
MRC
VBD
VME
Front_End System
A
B
1
12
. . . . . . . . . . . . . .
1
FEB
CB
PDT
2
3
Trigger Framework
Source of all decisions
Front_End System
4
  • Synchronization Error
  • Every other Turn number and crossing number was
    0xFFFF, as monitored by the Readout Crate
    Software.
  • Steps taken to address the problem
  • Sten had to change some jumpers on the Control
    Board (Not an issue).
  • He adjusted the appropriate setting of the
    transmitters and receivers on the cable, without
    which a turn no was lost every 5 sec.
  • Solution Change the hardware equations for CPLD
    to accommodate the propagation time of the new
    frequency multiplier.
  • Critical issue
  • Resolve this sync. Error.

5
  • Tests done
  • Pulser data was run on these 6 PDTs, with a fixed
    crossing and turn no. from the TFW.
  • Result No Synchronization error noticed.
  • Other jobs
  • Some changes have been made in the Front_End
    Readout code, wrt L3 data format, L3 transmission
    and 1553 multiblock transfers.
  • The CBs are set to communicate with the high
    speed UART rate of 2.5 mB.
  • There was a software downloading problem, but
    fixed.
  • MuoExamine revised to dump events with errors.

6
  • What next ?
  • Readout the 6 PDTs successfully, without errors.
  • Everything needed to begin the test is in place.
  • Use L3 filters on the data for hit
    reconstruction.
  • Installation Progress
  • 12 more B and C-layer CBs have been installed.
  • All are on the east side, vertical side.
  • Sufficient gas available to fill these, but the
    process shall halt till we have read the group of
    top 6 PDTs.
  • 6/12 have been tested with pulser, others in
    progress.

7
Plans for the next month
  • Read the 6 top PDTs successfully, without any
    errors.
  • Readout the side 12 PDTs.
  • Readout 18 Central East side PDTs.