Title: Basics of Concrete Pavement Intersection Construction
1Basics of Concrete Pavement Intersection
Construction
2Cost Considerations
- Mix
- Day/Night Paving
- Number of Stages Required
- Amount of Concrete/Stage
- Add 5.00 - 300.00/SY
3Production Rate Comparison
Fixed Form 12 Wide 70 120 CY/Hr Slip Form
Paver 24 Wide 10 depth 200CY-400CY/Hr
Reconstruction Mainline New Construction
2500-4000CY/Day
4Construction Staging for Concrete Intersections
5Traffic Flow Traffic Control
- Four Option
- Restricted Traffic Movement - Francis
Division - Partial Closures - Pines Broadway
- Complete Closures - Broadway and University
- Combination of the Above - SR 395 - Yelm,
Clearwater, and Kennewick Avenue
6Francis Division
- 32,000 ADT
- Four lanes required to remain open along
Division. Two in each direction. - Left turns from Division required to remain
open. - One lane required to remain open along Francis
Avenue. - Business were located on all four corners of
the intersection. Access to businesses
required.
7Stage 1
8Stage 2
9Stage 3
10Stage 4
11Stage 5
12Stage 6
13Intersection Complete
14Traffic Flow What The Contractor Noticed
- After the first week of reconstruction traffic
volumes decreased 20 to 30 percent. - Commuters used alternate routes.
- Access for material delivery was not a problem.
- Allowing left turns from Division to Francis
caused long lines along Division.
15Time For Completion
- The reconstruction took 35 working days of which
18 were concrete placing days to complete
3,047.3 cubic yard of concrete.
16Partial Closure - Broadway Pines
- Original Intersection was to maintain traffic
on all legs of the intersection. - After evaluation of traffic control plan WSDOT
allowed closure of Broadway. Therefore no left
turns permitted. - Broadway traffic used alternate routes.
- Pines traffic signals set on green for both
north and south bound traffic. Traffic did not
backup at intersection. - Traffic along Pines was free flowing.
17Stage 1 - Broadway Pines
18Stage 2 - Broadway Pines
19Stage 3 - Broadway Pines
20Combination Closures
- SR-395 Yelm, Clearwater, Kennewick Avenue
- Lane Closures Stages 1,2, 4
- Complete Closure Stage 3, Thursday at 700 PM
to Monday 600 AM. - Late opening penalty of up to 2,400.00 per
hour.
21Time for Completion
- Kennewick Avenue and Clearwater were built
concurrently. This saved a considerable amount
of time. Crews always had a place to work. - In 15 days approximately 3384 cubic yards were
placed in the two intersections. -
22Kennewick Avenue Stage 1
23Kennewick Avenue Stage 2
24Kennewick Avenue Stage 3
25Kennewick Avenue Stage 4
26Time for Completion
- The reconstruction took 19 calendar days of
which 9 of those days they placed concrete. - A total of 1,681 cubic yard of concrete
were placed.
27Kennewick Avenue Thursday Evening
28Kennewick Avenue Thursday Evening
29Kennewick Avenue Thursday Evening
30Kennewick Avenue Friday Morning
31Kennewick Avenue Friday Morning
Photo Courtesy Tri-City Herald
32Kennewick Avenue Friday Morning
33Kennewick Avenue Friday Afternoon
34Kennewick Avenue - Saturday Morning
35Kennewick Avenue Saturday Afternoon
36Kennewick Avenue Sunday Afternoon
37Time Comparison
38Reasons for Success
- WSDOT had several preliminary meetings with
City of Kennewick to discuss impacts and City
concerns. - WSDOT invited businesses to preconstruction
meeting. - WSDOT met with contractors to discuss
feasibility. - WSDOT kept public informed via newspaper,
radio, and television news broadcasts. - WSDOT web page with up to date information.
- WSDOT gave flyers to businesses weekly.
39Reasons for Success Continued
- WSDOT/Acme partnered on the modifications to the
traffic control plan allowing continuous work
operation with increased safety for employees. - Clearwater Kennewick were constructed
concurrently maximizing crew efficiency. - Detailed schedule with known milestones.
- Meeting or beating schedule.
- Something going on all the time.
- Decision makers available to resolve issues.
40Curing
- Use Standard Curing Techniques for PCCP
41Curing
- Blankets to speed up curing in cooler
temperatures.
42Curing
- Using the 705 pound Type III WSDOT mix
Strengths are achieved in 12 to 16 hours
without using the blankets on a typical summer
day. - Ambient temperature has the largest effect on
strength gain. - It should be left up to the contractor whether
to place blankets as needed to meet the opening
to traffic schedule. - The cost for blanketing all the concrete on the
first Kennewick project totaled over 30,000.00.
43Other Factors to Consider
- Maintain constant cross slope from center line
to curb flow line. - Maintain crowns on longitudinal joint lines.
- Maintain a constant joint spacing for ease of
construction. - Physically locate all utilities in the
intersection. - Allow time for sealing prior to traffic switch.
- The more work area available for construction
the quicker construction can be accomplished.
44Other Factors to Consider
- Requiring existing asphalt to be removed with a
mill also reduces time by minimizing earthwork. - If possible design PCCP section for no base
rock. Installation of base gravels are costly
in small areas and add a time to the process.
45Types of Paving
Highways Airports
Slip Form
No Forms Required Wire used for line and
grade. Low Slump Concrete
46Types of Paving
Intersections
Fixed Form
Normally Steel Forms Form Is Mold for
Paving Form Supports Finishing
Equipment Adaptable to Variable Conditions
47Pre-Paving Meeting
- Assess
- Construction sequence/staging
- Order of Work
- Planned Sequence
48Pre Paving Meeting (cont)
- Assess
- Daily Operations
- Start Time
- Hours of Operation
- Paving Methods
- Sampling and Testing
- Safety
- Sawing and Sealing Operations
49Pre Paving Meeting (cont)
- Assess
- Concrete Delivery
- End Dumps
- 45 minute delivery time
- Load Limits
- Access Routes
- Safety
50Pre Paving Meeting (cont)
- Assess
- Decision Making Process
- Whos in Charge
- Prime, Sub, WSDOT
- Surveying, Sampling Testing, Wire Adjustments
- Go No Go
- Final Acceptance
- Time Lines for Information
51Basic Construction
Grading Forming Placing Curing Sawing Sealing
52Preparing the Grade
- Construction always starts with the subgrade
- Uniformity
- Soil type
- Moisture content
- Density
- Remove pockets of unsuitable materials
- Stabilize unsuitable soils
53Trim Grade and Compaction
- Trim after placement of forms
- Final rolling for compaction
- Final check form line
- Alignment
- Profile
- Depth
54(No Transcript)
55(No Transcript)
56(No Transcript)
57Fixed Form Paving Operations
- Paving form is the mold
- Holds concrete in place
- Establishes grade and alignment
- Serves as tracks for paving equipment
-
58Typical Steel Form
Form Lock
59Side Forms
Side form sections shall be straight, Free from
warps, bends, indentations, Or other defects
Commonly Steel Forms
60(No Transcript)
61Application AdvantagesFixed Form Paving
- Tight tolerances - side clearance
- Multiple changes of width
- Blockouts
- Intersections - quadrants open to traffic
623 minimum
63(No Transcript)
64(No Transcript)
65(No Transcript)
66(No Transcript)
67Application AdvantagesFixed Form Paving
- Maintain quality during shortconcrete supply
- Critical staging for traffic control
- Small inexpensive equipment canplace concrete
- An adaptable system
68(No Transcript)
69Forming Curves
- Similar requirements to regular steel forms
- Depth equal pavement thickness
- Stake in place
- Ends must attach and be tight
70(No Transcript)
71(No Transcript)
72Concrete ProductionandPlacement
Redi Mix Batch Plant Portable Batch Plant
73(No Transcript)
74Placement
75(No Transcript)
76(No Transcript)
77(No Transcript)
78(No Transcript)
79(No Transcript)
80EQUIPMENT
Concrete shall be spread, screeded, Shaped, and
consolidated, with one Or more self propelled
machines
81(No Transcript)
82(No Transcript)
83(No Transcript)
84(No Transcript)
85(No Transcript)
86(No Transcript)
87(No Transcript)
88Critical Factors Fixed Form Paving - Ride Quality
- Proper machine adjustments
- Steady machine progress
- Avoid excessive finishing
- Avoid excessive water on surface
- Straightedge check of slab
89Pavement Steel
90Placing Dowel Bars
91(No Transcript)
92(No Transcript)
93Keyways
94(No Transcript)
95(No Transcript)
96Finishing Texturing Curing
97Finishing
How Much Finishing How Many Finishers
98(No Transcript)
99(No Transcript)
100(No Transcript)
101(No Transcript)
102No Water Added
?
103(No Transcript)
104(No Transcript)
105Surface Smoothness
10 Straightedge
106Texturing
- Transverse Tining
- Longitudinal Tining
- Astro Turf Drag
- Broom Finish
107Microtexture
From Fine Aggregate Particles
Astro Turf Drag or Broom Finish
108Macrotexture
Formed into surface
Transverse or Longitudinal Tining
109(No Transcript)
110(No Transcript)
111(No Transcript)
112Summary of Critical Factors
- Sound grade
- Monitored supply
- Consistent workability
- Controlled Density
113Curing
- Uniform
- Timely
- Check yield
- 150 sq ft/gal
114(No Transcript)
115(No Transcript)
116Saw and Seal Operations
117(No Transcript)
118Joints
- Formed Joints
- Longitudinal Transverse Construction
- Sawed Joints
- Longitudinal Transverse Contraction
119(No Transcript)
120Sawing Transverse Contraction Joints
121(No Transcript)
122(No Transcript)
123(No Transcript)
124(No Transcript)
125(No Transcript)
126(No Transcript)
127Types of Saw Cuts
- Initial Saw Cut (Crack control)
- Widening Cut (Joint sealant reservoir)
128(No Transcript)
129(No Transcript)
130Sawing Window
- Production schedule - Early cut or conventional
Wet Saw
131Temperature and the Sawing Window
- Begins with acceptable raveling
- Ends with significant concrete shrinkage that
induces cracking
Contraction or Differential Shrinkage
Excessive Raveling
Saw
Unacceptable
Late Sawing
Acceptable
Time
132Joint Sawing
Too Early Raveling
Too Late Random Cracking
Concrete Set
Time
133Sawing Window
- Concrete mix characteristics
- Cement type
- Admixtures
- Fast Track
Job Site Operations
134Sawing Window
- Base Type
- Aggregate
- Stabilized
- Open graded
Job Site Operations
135Sawing Window
- Weather conditions
- Ambient temperature
- Wind
- Humidity
- Cloud cover
- Season
Job Site Operations
136(No Transcript)
137Sealant Materials
- Formed-in-place
- Backer rod
- Preformed
Joint Sealing
138Formed-In-Place
Joint Sealing
139Formed-In-Place Joint Preparation
- Flush residue (Widening cut)
- Abrasive Cleaning
- Air Cleaning
Joint Sealant Installation
140Backer Rod Material
- Polyethylene foam (cold)
- Crosslinked polyethylene foam (hot or cold)
Joint Sealing
141(No Transcript)
142(No Transcript)
143(No Transcript)
144(No Transcript)
145Joint Sealant Material
- Preformed
- Polychloroprene elastomeric compression sealant
Joint Sealing
146Critical Factors in Sawing and Sealing
- Weather is a constant variable
- Layout/Marking of joints
- Timing of initial control sawing
- Saw depth
147What Could Possibly Go Wrong?
148(No Transcript)
149(No Transcript)
150(No Transcript)
151Fast Track Paving
152?
Questions