AMS Tracker Thermal Control System TTCS - PowerPoint PPT Presentation

1 / 30
About This Presentation
Title:

AMS Tracker Thermal Control System TTCS

Description:

TIM-meeting, October 24-28, 2005. NLR-team: J. van Es, M.P.A.M. ... Condenser tubes supported by radiator diagonal strut. 26. Tracker Thermal Control System ... – PowerPoint PPT presentation

Number of Views:26
Avg rating:3.0/5.0
Slides: 31
Provided by: JVa3
Category:

less

Transcript and Presenter's Notes

Title: AMS Tracker Thermal Control System TTCS


1
AMS Tracker Thermal Control System (TTCS) TTCS
Progress report TIM-meeting, October 24-28,
2005 NLR-team J. van Es, M.P.A.M. Brouwer, B.
Verlaat (NIKHEF), A. Pauw, G. van Donk, T.
Zwartbol, SM. BardetSun Yat-Sen University team
ZH. He, KH. Guo, JQ. Ni, SS. Lu, XZ. Wang, XM.
Qi, TX. Li, YH Huang INFN-AMS-team R.
Batiston, M. Menichelli et al.CAST-team Z. Hou,
J. Zhang et al. MIT-team V. Koutsenko, Cai, A.
Lebedev

2
Presentations
  • TTCS overall progress, component progress
    safety issues, J. van Es (NLR)
  • TTCE progress, thermal modelling progress, Z. He
    (SYSU)
  • More detailed presentations during splinter
    meetings
  • TTCS Accumulator design review CAST, Thursday
    1000-1200
  • TTCS Mechanical splinter, Wednesday 1400-1600
  • TTCS Thermal modelling meeting, SYSU, Wednesday
    830-1030

3
AMS Tracker Thermal Control System (TTCS) TTCS
overall progress, component progress safety
issuesCERN, October 24-28 October,
2005 NLR-team J. van Es, M.P.A.M. Brouwer, B.
Verlaat (NIKHEF), A. Pauw, G. van Donk, T.
Zwartbol, SM. BardetSun Yat-Sen University team
ZH. He, KH. Guo, JQ. Ni, SS. Lu, XZ. Wang, XM.
Qi, TX. Li, YH Huang INFN-AMS-team R.
Batiston, M. Menichelli et al.CAST-team Z. Hou,
J. Zhang et al. MIT-team V. Koutsenko, Cai, A.
Lebedev

4
Contents
  • System design
  • Box design
  • TTCS Start-up
  • Component progress
  • Pump status
  • Valves, APS/DPS
  • Evaporator
  • Condenser (freezing)
  • Heat Exchanger
  • OHP
  • Pre-heaters
  • Accumulator
  • Safety status

5
Issue P3.0 25-07-2005
6
Issue S3.0 25-07-2005
7
TTCS Box design
  • Mechanical design team is reinforced by Corrado
    Gargiulo (INFN) for box design
  • SYSU will perform detailed analyses on box and
    component (accumulator) design
  • Progress
  • Bolt sharing with a.o. main radiator bracket
    solved New draft mechanical box design available
    detailing on-going
  • Components interfaces 90 finalised (see
    components)
  • Preliminary stress analyses (SYSU) show
    sufficient margin

8
TTCS box design
9
TTCS box design
10
TTCS box design
11
TTCS box design
12
TTCS Start-up
  • Actions to tackle start-up problem decided on TWG
    meeting at NLR
  • Investigate possible super-critical pump start-up
    (PDT/NLR/CAST)
  • Start-up analyses of orbital cases (SYSU/CGS)
  • Start-up radiator design decisions
  • Investigation of severity of the problem
    (b-angles)

13
Super-critical start-up
  • PDT pump tests are being performed right now
  • Pressure head measurements
  • suction capability with air or vapour
  • Design is based on the MER-rover pump which has
    been tested for 24 hour with closed valves
    (circumstantial evidence)
  • Accumulator transition tests from super- to
    sub-critical state will be implemented in EM
    testing to verify wetting of the wick after
    super-critical start-up

14
TTCS Start-up Modelling
  • Start-up analyses have been performed reported
    by SYSU/CGS
  • Assumptions
  • Hot and coldest case orbital data selection by
    JS.
  • AMS start-up configuration
  • New box lay-out with start-up radiator
  • start-up radiator white-painted
  • side walls covered by MLI

15
TTCS Start-up results
  • Primary box
  • Primary box can start-up from -75 b 60

16
TTCS Start-up results
  • Secondary box
  • Secondary box can start-up from -35 b 75

17
TTCS Start-up modelling

18
TTCS Start-up modelling Freezing check

19
TTCS Start-up summary and remarks
  • Start-up radiator improves the TTCS start-up
    capabilities
  • No freezing problem is present in the box with
    the start-up radiator
  • Always one TTCS-loop able to start-up in AMS
    start-up configuration
  • Additional analyses required for start-up in
    AMS-on configuration
  • Supercritical start-up is investigated. If
    possible it is detrimental for pump lifetime
    (however a system operational decision and
    option) and makes switch between P and S at all
    times possible

20
Component Status
  • Pump (PDT)
  • Design Review at PDT
  • Electronically pump design is progressing well
  • Motor design mature (proven design)
  • BBM curve test performed
  • pump can deliver more flow then required
  • Impeller adaptations are being implemented to
    have better control
  • Hall effect sensor issue solved (no Pressure
    dependence)
  • Super-critical start-up testing on-going
  • Planning EM delivery early December 2005

21
Component Status
  • Valves (BE)
  • Bradford Engineering BV
  • pst-file with envelope on its way (smaller
    envelope)
  • Electrical interface specification update (in
    specs doc)
  • APS DPS (CETC)
  • China Electronics Technology Group Corporation
    (CETC) is selected as supplier
  • Supplier specifications are available
  • Contract to be signed next week

22
Component status
  • Evaporator (NIKHEF) (shown in Tracker
    presentation)
  • FM inner rings ready
  • FM outer ring in manufacturing
  • Condenser (NLR/UNIG)
  • Condenser design is freeze proof
  • Condenser tubing resistant for MDP of 3000 bar at
    5 ?C
  • Low-T resistant thermostats are available
  • However transport tubing on conical flange can
    reach Tlt-55 ?C (freezing) after 160 hours

23
(No Transcript)
24
Component status
  • Condenser safety conclusion (TWG meeting at NLR)
  • Transport tubing have to show leak before burst
  • approval required from safety panel
  • Advantage is that the condenser manifolds can go
    back to the old upper trunnion bridge locations
    with shorter (lower pressure drop) condenser
    lines
  • Condenser design progress (NLR/UNIG)
  • CTE difference between Inconel tubing and
    aluminium plate
  • Glue test sample in manufacturing at CERN

25
RAM
Condenser tubes supported by radiator diagonal
strut
Condenser manifold locations at the inside of the
USS upper trunnion bridges.

WAKE
Two tube support beams
Primary TTCS
Circular tube routing using outer cylinder
generic hole pattern
Secondary TTCS
26
Component status
  • Heat Exchanger (NLR)
  • EM manufacturing upto finalisation
  • QM design change agreed
  • Split of two-phase part exterior to HX (to avoid
    phase separation during ground testing)
  • Pre-heater design (NLR)
  • Preliminary design finished
  • Heaters designed and selected
  • Detailed mech design on-going

NLR Manufactured EM
27
Component Status
  • OHP-design (NLR)
  • Heaters selected
  • Thermal Modelling
  • Mechanical design finalised
  • Structural analyses to be performed

28
Component Status
  • Accumulator (CAST)
  • Accumulator component testing
  • heat pipe testing
  • test programme defined
  • Accumulator EM design
  • Pressure calculations
  • Wick calculations
  • Structural design

29
Component Status
  • Accumulator (CAST)
  • EM manufacturing on-going
  • QM design to be started
  • More details and review on design in splinter
    session on Thursday

Accumulator shell
Accumulator with wick structure
30
Safety Status
  • Pressurised systems table almost complete
  • Component information coming in APS, DPS, valves
    (TBD)
  • Mechanical
  • Mechanical material and component list far from
    complete (suppliers information needed)
  • Structural analysis for box and components to be
    finalised
  • Thermal Models are running and can provide safety
    information
  • Radiator heater design updated
Write a Comment
User Comments (0)
About PowerShow.com