Title: AMS Tracker Thermal Control System TTCS
1AMS Tracker Thermal Control System (TTCS) TTCS
Progress report TIM-meeting, October 24-28,
2005 NLR-team J. van Es, M.P.A.M. Brouwer, B.
Verlaat (NIKHEF), A. Pauw, G. van Donk, T.
Zwartbol, SM. BardetSun Yat-Sen University team
ZH. He, KH. Guo, JQ. Ni, SS. Lu, XZ. Wang, XM.
Qi, TX. Li, YH Huang INFN-AMS-team R.
Batiston, M. Menichelli et al.CAST-team Z. Hou,
J. Zhang et al. MIT-team V. Koutsenko, Cai, A.
Lebedev
2Presentations
- TTCS overall progress, component progress
safety issues, J. van Es (NLR) - TTCE progress, thermal modelling progress, Z. He
(SYSU) - More detailed presentations during splinter
meetings - TTCS Accumulator design review CAST, Thursday
1000-1200 - TTCS Mechanical splinter, Wednesday 1400-1600
- TTCS Thermal modelling meeting, SYSU, Wednesday
830-1030
3AMS Tracker Thermal Control System (TTCS) TTCS
overall progress, component progress safety
issuesCERN, October 24-28 October,
2005 NLR-team J. van Es, M.P.A.M. Brouwer, B.
Verlaat (NIKHEF), A. Pauw, G. van Donk, T.
Zwartbol, SM. BardetSun Yat-Sen University team
ZH. He, KH. Guo, JQ. Ni, SS. Lu, XZ. Wang, XM.
Qi, TX. Li, YH Huang INFN-AMS-team R.
Batiston, M. Menichelli et al.CAST-team Z. Hou,
J. Zhang et al. MIT-team V. Koutsenko, Cai, A.
Lebedev
4Contents
- System design
- Box design
- TTCS Start-up
- Component progress
- Pump status
- Valves, APS/DPS
- Evaporator
- Condenser (freezing)
- Heat Exchanger
- OHP
- Pre-heaters
- Accumulator
- Safety status
5Issue P3.0 25-07-2005
6Issue S3.0 25-07-2005
7TTCS Box design
- Mechanical design team is reinforced by Corrado
Gargiulo (INFN) for box design - SYSU will perform detailed analyses on box and
component (accumulator) design - Progress
- Bolt sharing with a.o. main radiator bracket
solved New draft mechanical box design available
detailing on-going - Components interfaces 90 finalised (see
components) - Preliminary stress analyses (SYSU) show
sufficient margin -
8TTCS box design
9TTCS box design
10TTCS box design
11TTCS box design
12TTCS Start-up
- Actions to tackle start-up problem decided on TWG
meeting at NLR - Investigate possible super-critical pump start-up
(PDT/NLR/CAST) - Start-up analyses of orbital cases (SYSU/CGS)
- Start-up radiator design decisions
- Investigation of severity of the problem
(b-angles) -
13Super-critical start-up
- PDT pump tests are being performed right now
- Pressure head measurements
- suction capability with air or vapour
- Design is based on the MER-rover pump which has
been tested for 24 hour with closed valves
(circumstantial evidence) - Accumulator transition tests from super- to
sub-critical state will be implemented in EM
testing to verify wetting of the wick after
super-critical start-up -
14TTCS Start-up Modelling
- Start-up analyses have been performed reported
by SYSU/CGS - Assumptions
- Hot and coldest case orbital data selection by
JS. - AMS start-up configuration
- New box lay-out with start-up radiator
- start-up radiator white-painted
- side walls covered by MLI
-
15TTCS Start-up results
- Primary box
- Primary box can start-up from -75 b 60
16TTCS Start-up results
- Secondary box
- Secondary box can start-up from -35 b 75
17TTCS Start-up modelling
18TTCS Start-up modelling Freezing check
19TTCS Start-up summary and remarks
- Start-up radiator improves the TTCS start-up
capabilities - No freezing problem is present in the box with
the start-up radiator - Always one TTCS-loop able to start-up in AMS
start-up configuration - Additional analyses required for start-up in
AMS-on configuration - Supercritical start-up is investigated. If
possible it is detrimental for pump lifetime
(however a system operational decision and
option) and makes switch between P and S at all
times possible -
20Component Status
- Pump (PDT)
- Design Review at PDT
- Electronically pump design is progressing well
- Motor design mature (proven design)
- BBM curve test performed
- pump can deliver more flow then required
- Impeller adaptations are being implemented to
have better control - Hall effect sensor issue solved (no Pressure
dependence) - Super-critical start-up testing on-going
- Planning EM delivery early December 2005
21Component Status
- Valves (BE)
- Bradford Engineering BV
- pst-file with envelope on its way (smaller
envelope) - Electrical interface specification update (in
specs doc) - APS DPS (CETC)
- China Electronics Technology Group Corporation
(CETC) is selected as supplier - Supplier specifications are available
- Contract to be signed next week
22Component status
- Evaporator (NIKHEF) (shown in Tracker
presentation) - FM inner rings ready
- FM outer ring in manufacturing
- Condenser (NLR/UNIG)
- Condenser design is freeze proof
- Condenser tubing resistant for MDP of 3000 bar at
5 ?C - Low-T resistant thermostats are available
- However transport tubing on conical flange can
reach Tlt-55 ?C (freezing) after 160 hours -
23(No Transcript)
24Component status
- Condenser safety conclusion (TWG meeting at NLR)
- Transport tubing have to show leak before burst
- approval required from safety panel
- Advantage is that the condenser manifolds can go
back to the old upper trunnion bridge locations
with shorter (lower pressure drop) condenser
lines - Condenser design progress (NLR/UNIG)
- CTE difference between Inconel tubing and
aluminium plate - Glue test sample in manufacturing at CERN
-
-
25RAM
Condenser tubes supported by radiator diagonal
strut
Condenser manifold locations at the inside of the
USS upper trunnion bridges.
WAKE
Two tube support beams
Primary TTCS
Circular tube routing using outer cylinder
generic hole pattern
Secondary TTCS
26Component status
- Heat Exchanger (NLR)
- EM manufacturing upto finalisation
- QM design change agreed
- Split of two-phase part exterior to HX (to avoid
phase separation during ground testing) - Pre-heater design (NLR)
- Preliminary design finished
- Heaters designed and selected
- Detailed mech design on-going
NLR Manufactured EM
27Component Status
- OHP-design (NLR)
- Heaters selected
- Thermal Modelling
- Mechanical design finalised
- Structural analyses to be performed
28Component Status
- Accumulator (CAST)
- Accumulator component testing
- heat pipe testing
- test programme defined
- Accumulator EM design
- Pressure calculations
- Wick calculations
- Structural design
29Component Status
- Accumulator (CAST)
- EM manufacturing on-going
- QM design to be started
- More details and review on design in splinter
session on Thursday -
Accumulator shell
Accumulator with wick structure
30Safety Status
- Pressurised systems table almost complete
- Component information coming in APS, DPS, valves
(TBD) - Mechanical
- Mechanical material and component list far from
complete (suppliers information needed) - Structural analysis for box and components to be
finalised - Thermal Models are running and can provide safety
information - Radiator heater design updated