Title: Information Technology Standing Committee
1Multi Interval Optimization
Nicholas Ingman Holiday Inn - Oakville
2Multi Interval Optimization
- Agenda
- Objectives
- Multi Interval Optimization Function
- Dispatch Issues
- Proposed Implementation Schedule
3Objectives
- Operational Stability
- Facility cycling should be reduced relative to
the current operation. - Participants should be made aware of potential
future dispatch instructions. - Improved Transparency
- Manual intervention by IMO Control Room staff in
the dispatch solution will be reduced - Improved Compliance
- Non-compliance with the Dispatch Instructions
will be reduced
4Objectives
- Improve Market Efficiencies
- Constraint payments caused by limited ramp
capability should be reduced compared to present
dispatch. - Improved Operational Reliability
- Resources should be automatically scheduled in
advance of present interval requirements to allow
ramp rate capability to be used to solve for
reliability concerns identified in future
intervals.
5Basic Principles of MIO
- MIO maintains the current optimization objective
as described in the Market Rules - MIO will maximize the gain from trade over a
forward looking horizon of up to 11 intervals
(currently only uses a single interval) - The number of optimized intervals is
configurable, up to a maximum of 11. However due
to performance requirements, the number of
optimized intervals will be limited to 5
(including the dispatch interval).
6Basic Principles of MIO
- The objective function will be configurable such
that each interval's contribution to the overall
optimization has a specific weight. - The optimization will produce a
security-constrained economic dispatch (SCED) for
all dispatchable resources over the optimization
horizon. - The frequency of execution will be every 5
minutes.
7Critical Intervals
- Critical intervals are intervals within the
optimization period that provide the most
efficient optimized dispatch solution as well as
provide most beneficial information to facility
operators. - The critical intervals are used as input to the
MIO calculation, and for preparing the dispatch
advisories. - Where there is a trade off between both
objectives the intervals providing the better
optimization have been selected. - Critical intervals are selected for each interval
based on defined selection criteria
8Output of the MIO Sequence
- The schedules for the first interval are to be
issued to the respective market participants in
the form of dispatch instructions. - The schedules for the remaining critical
intervals are to be communicated to the
respective market participants in the form of
Dispatch Advisories (DA)
9Dispatch Issues
- Market Participants have identified a number of
Real Time dispatch issues that result in dispatch
instructions that generation facilities are
either unable to physically follow or may cause
equipment damage. - As a result, a number of modifications have been
defined for the RTC DSO in an effort to more
accurately reflect the physical characteristics
of facilities
10Reflecting Unit Ramp Capability
- The DSO causes a stutter step in fossil loading
when a unit starts to increase output from either
a steady load or a loading rate less than the
offered rate. This is a result of the snapshot
that reflects the unit actual loading when
calculating the next interval Dispatch
Instruction. - The DSO should account for the initial slow
loading characteristic of non-quick start
facilities. - The unit ramp capability will factor in the most
limiting of two combinations. - Last dispatch and offer ramp rate
- Actual output and maximum ramp rate
11Reflecting Unit Ramp Capability
12Reflecting Unit Ramp Capability
13Operating Reserve Activation
- During operating reserve activations, fixed
constraints are applied to facilities that have
been activated. - A unit minimum constraint should be set
(instead of the fixed) when facilities are
activated for operating reserve. - This is a change from the current practice of
fixing the unit at the operating reserve
activation dispatch level.
14Minimum Loading Point
- Many facilities have a requirement to operate at
or above a minimum output level or loading
point - The RTC DSO should not schedule these units below
this minimum output level unless the unit is
synchronizing or shutting down.
15Start Up and Shut Down
- Treatment of Units Starting Up or Shutting Down
- When a non-quick start unit synchronizes, it must
ramp up to its minimum loading point. - If the unit is dispatched below its minimum
loading point, it must ramp down to zero and be
removed from service. - After a non-quick start unit synchronizes it must
be dispatched to minimum load or above.
16Start Up and Shut Down
- Treatment of Units Starting Up or Shutting Down
- While on line the unit should never be dispatched
below minimum unless predispatch indicates the
unit is to be de-committed in the hour. - The control room operator must manually approve
the de-commitment of a unit (approve dispatching
below minimum to begin the shutdown event) in the
RTC DSO.
17Dispatch Trajectory
- Ensure that thermal units will not reverse
direction without a minimum period (adjustable
variable of 0, 1 or 2 intervals) of steady
operation. - After the minimum period of steady operation, the
unit is available to be normally dispatched.
18Forbidden Operating Range
- Hydraulic units have operating ranges where the
units are unable to maintain steady operation
without causing equipment damage. - Multiple forbidden ranges for aggregated
facilities should be respected, up to a maximum
of 3. - Each forbidden range is to be offered as a
separate price segment.
19Dispatch Advisories
- Issued to all dispatchable market participant
facilities - For each interval, a Dispatch Instruction will be
issued plus the addition of up to 4 dispatch
advisories for future intervals. - Participant specific Dispatch Advisory reports
should be available for all participants to view
on demand from the participants dispatch
workstation. - The report will contain the energy and OR
components of the dispatch advisory and indicate
the specific intervals that each component
relates to. - This report will not contain the Dispatch
Instruction.
20Dispatch Advisories
- Initial implementation via a Private MP Report
- Feasibility Testing is currently underway
- Supporting Infrastructure (APP252) is scheduled
for Release 11.0 - XML Schema and Stylesheets will be published
early next year after review with MIO Working
Group
21Dispatch Advisory - Sample
22Release 8.1 Deliveries
- The following changes are proposed to be
implemented as part of Software Release 8.1 on
December 10 - Reflecting Ramp Rate Capability
- Operating Reserve Activation
- Modifications to PLC to capture resource specific
data (Minimum Loading Point, Forbidden Regions
etc.)
23New PLC Screen
24Proposed MIO Project Schedule
Apr-03
Jun-03
Apr-04
Aug-03
Oct-03
May-04
Dec-03
Feb-04
Requirements and Detailed Design Definition
Build Test
Commissioning and Market Trials
- R 8.1 - Introduction of
- RD Changes for OR
- Respecting Ramp Rate Capability and
- PLC Modifications to capture Resource Specific
Data
Decision to Go - Live
Proposed timeline is dependent on finalization of
participants implementation schedules