Polarized 3He Target System - PowerPoint PPT Presentation

About This Presentation
Title:

Polarized 3He Target System

Description:

Extended magnetic shielding on BigBite fringing field. Conceptual design on laser optics lines ... Fringe field: P. Brindza. Safety, documents: J. P. Chen ... – PowerPoint PPT presentation

Number of Views:13
Avg rating:3.0/5.0
Slides: 21
Provided by: jian114
Category:

less

Transcript and Presenter's Notes

Title: Polarized 3He Target System


1
Polarized 3He Target System
  • Overview
  • Design
  • Vertical Polarization
  • Spin-Flip
  • Oven/Ladder/Enclosure/Access
  • Laser/Optics/Cells
  • Polarimetry
  • Safety/Documents
  • Installation/Switch-over
  • Milestone, Manpower and Responsibilities

2
3He Target Overview

3
Design Progress
  • Progress (Estimated gt90 person-weeks 3 months
    ago)
  • Completed items
  • Layout for all four experiments
  • New vertical Helmholtz coils and support
  • New RF coils for vertical polarization
  • New oven system
  • Oven support in the target lab
  • Target collimators
  • Replacement support for horizontal Helmholtz
    coils
  • New cells (with side pull-offs)
  • Extended magnetic shielding on BigBite fringing
    field
  • Conceptual design on laser optics lines
  • Conceptual design on vertical Compass

4
Oven System

5
Oven being assembled in the target lab

6
Target Cell

7
Laser Optics

8
Remaining Items for Design
  • Remaining design items (total lt 20 person-weeks)
  • Main support Structure
  • Supports for
  • Target drive, Target Collimator, new RF coils,
    Ref. cell
  • Target enclosure and windows
  • Target ladder and pick-up coils
  • Laser optics lines (including EPR,
    spectra-analyzer) and support
  • Personnel access
  • Safety interlock
  • Compass mounts

9
Progress in the target lab
  • Spin-flip test (mostly complete)
  • RF sweep NMR on 3He works
  • EPR works
  • New support for horizontal Helmholtz coils
    installed
  • New oven and support arrived, being assembled
  • Two new cells manufactured and to be tested
  • Cell characterization (density and window) setup
    ready
  • Optical fibers and combiners ordered
  • 5-to-1 combiners delivered, tested and problems
    found

10
Spin-Flip Test

11
RF sweep NMR on 3He

12
EPR

13
Planned tests in the target lab
  • Install new oven, test
  • Test new cells
  • Characterizing new cells
  • Test new components
  • Test new optics
  • RF sweep water calibration
  • Combine polarization measurements with spin-flip
  • Spin-flip signal to DAQ
  • LabView communication with EPICS

14
Other Components
  • Compass (Kentucky) Conceptual design complete
  • complete design, manufacturing and test
  • Vertical coils (order placed, delivery next
    month)
  • setup in new target lab, align and field
    mapping
  • then move to EEL target lab, integrate
    with horizontal coils
  • Lasers 9 in hand, 2 spare diodes new vender
    narrow lasers
  • Cells new contracts with Princeton/Mike Souza
  • medium size (3) pumping chamber,
  • production started, two in hand,
  • plan to produce 1 cell every two weeks
  • WM and UVa groups

15
Vertical Compass Conceptual Design

16
Safety and documents
  • There are a number of safety aspects for the
    target
  • Laser safety eye, skin, fire hazard, LSOP
  • enclosure, alignment, eyewear, training
  • High pressure glass cells explosion,
    radiation, OSP/RWP
  • enclosure, windows, loop around pivot area
  • cell handling face mask, eye and hearing
    protection
  • Reference cell system high pressure, hydrogen
  • Hot Surface/fire hazard from heating
  • Electrical from power supplies
  • Magnetic field
  • All documents will be updated

17
Manpower
  • Designer A. Gavalya, S. Esp (and help from
    others)
  • Students C. Dutta (KY), J. Katich (WM), X. Zhan
    (MIT),
  • Physicists T. Averett (WM, part-time), W.
    Korsch (KY, short-term visit), and J. P. Chen
    (JLab).
  • Postdocs from WM, Duke
  • Help from past students/postdocs.
  • Off-site
  • Cell production/testing at WM, UVa.
  • Compass design/testing at Kentucky.

18
Responsibilities
  • Overall J. P. Chen
  • Design A. Gavalya/ J. P. Chen
  • Vertical coils, holding field, oven system,
    ladder, support, cell characterization, reference
    cell, NMR
  • J. Katich/T. Averett
  • Spin-flip, EPR C. Dutta/W. Korsch
  • Optics C. Dutta/J. P. Chen
  • Software/Labview, communication with EPICS
  • X. Zhan/B. Moffit
  • Compass A. Kolarkar/W. Korsch
  • Fringe field P. Brindza
  • Safety, documents J. P. Chen

19
Installation, commissioning, switchover
  • Coordinate with Ed Folts for installation 4-6
    week for the target
  • Move to the hall, survey
  • Move to pivot, survey, install components,
  • Install optical line support, instrumentation,
    power cables
  • Checkout magnets, measure field direction/survey
  • Install ladder, cells, survey
  • Install reference cell system, cooling jets
  • Water calibration
  • Laser safety inspection, switch to 3He, laser
    alignment
  • Pumping up, check out spectra-analyzer, EPR
  • Commissioning elastic 3He asymmetry (T and L)
  • Switchover
  • change cell, water calibration
  • change optical line and check alignment, pump-up
  • EPR, temperature test

20
Milestones for Polarized 3He
  • Spin-Flip test done
  • NMR/EPR system working done, keep improvement
  • New oven ready for cell testing/characterization
    April 1
  • Vertical coils test June 1
  • Cell production 10 by July 1, 20 by Dec. 1
  • New target structure Sept. 1
  • Compass Sept. 1
  • Laser optics line Oct. 1
  • NMR FM water (optional) Oct. 1
  • Complete system test Nov. 1
  • Ready for installation Jan. 1, 2008