Title: TRD UCrate electronics Status report
1TRD U-Crate electronicsStatus report
- Wim de Boer, Chan Hoon Chung, Florian Hauler,
Levin Jungermann, Mike Schmanau, Georg Schwering - IEKP - Universität Karlsruhe (TH)
- RWTH-Aachen I
2Outline
- QM2 production status of boardsUDR2, UPSFEv2,
UBPv2, S9011AUv2, S9011B - Assembled UPD-Box
- Cosmics test stand
- Noise performance
- Summary
3TRD(U)-Electronics Overviewafter weight reduction
Ucrate TRD electronic crate UBP TRD
backplane UPD TRD power distribution box
V2
V2
UPSFE TRD power supply for front end UDR TRD
data reduction board JINF data concentrator and
link to higher DAQ for TRD UHVG TRD high
voltage generator UFE TRD front end UTE TRD
tube end UHVD TRD high voltage distributor
removed USCM USCM functionality covered partly by
JINFV2
4Full U-crate with QM2 hardware
UHVG
JINF
UDR2
UPSFE
5Status of U-boards
- UDR2 / UPSFEv2 / UBPv2 / S9011AUv2 / S9011B /
DC-DC converters - QM2 production and testing at CSIST in Taiwan
finished. - December 2004. First slow control tests at
Prevessin (Andrei, Vladimir, Alexei) using JINFv2
with full crate at CERN were successful. - UPD-Box and U-crate currently at Karlsruhe for
UPD-Box integration and system tests. - A second set of U-crate boards (later to be used
for TVT) is ordered from Taiwan for testing and
development at Prevessin.
6Boards to be taken to Europe
- Basically all remaining U-crate boards should be
taken to Europe. - To CERN
- 1 UBPv2
- 3 UPSFEv2 boards
- 6 UDR2 boards
- 5 or 6 UHVG boards (one of the remaining boards
belongs to UG) - 1 JINFv2
- To Karlsruhe/Aachen
- 1 JINFv2 (for Aachen)
7UPD-Box Assembly
- Prototype UPD-Box assembled.
- Electrical tests finished.
- Slow control is working DC/DC converters can be
switched on or off. - Complete system test of U-crate and UPD-Box with
cosmics test stand. - Further system test is foreseen in Aachen
Connection to octagon andoperation with gas
system. Special attention to noise performance. - Ring lug space problems will be solved by raising
middle bus bars with copper washer. - Before entering TVT, customs cable tiers will be
replaced by cable tiers ordered from
Mike/Nichelle. Board will be cleaned.
8Cosmics at Karlsruhe
New cosmics test stand at Karlsruhe for long term
data taking.
Trigger A
PM HV
64 channel strawtube jig
Trigger B
Trigger electronics
Power supply
U-Crate
9Online Event Display
10Cosmics Spectra (UPD-U-crate)
ArCO21300V
ArCO21400V
11Pedestal/Noise (UPD-U-crate)
ArCO21200V
Gas Inlet/Outlet
ArCO21500V
12Summary
- All QM2 boards for TRD are tested and are
available for space-qualification tests. - UPD-Box integration completed. Electrical tests
ok. System tests with U-crate ongoing. - Preliminary tests with cosmics test stand
together by UPD-box and U-crate show no
excessive noise. - First JINFv2 DSP slow control software is
available (by Andrei). S9011AUv2, UPSFEv2 and
UHVG can be controlled and monitored. - OK for flight module production will be given, as
soon as system tests and space qualification
tests have been completed. (TVT, vibration, )
13Power-Up/Failure recovery
Power On (if conditions are safe)
All primary and secondary hardware is on
JMDC (or from ground control) Verify
UPD/U-crate hardware status
OK! Switch off redundant hardware
Not OK! gtManual recovery in control center.or
if problem is known and JMDC has explicit
instructions correct problem automatically
Gas ok?
HV ramping
data taking and slow control monitoring (JMDC)
Problem detection
Known problem Automatic treatment in JMDC
Unknown problem Manual failure recovery in
control center