2Belkomur Project History
- In the middle of the 1930s a railway
construction began in the planned Belkomur
location. In 1944 the railway Kotlas-Vorkuta
connected Pechora Coal Basin and Cherepovets
Metallurgical Works. In 1953-1954 the railway
construction in the Russian Polar Region was
stopped.
3(No Transcript)
4- In 1995 a large-scale meridional project was
proposed. The aim of the project was to link the
cities of Arkhangelsk, Syktyvkar, Kudymkar and
Perm by means of a railway called Belkomur. - The project design was based upon the General
Scheme of Railways Development in Russian
European North.
5Railway network development in the Urals and
Russian European North
6The project operator is JSC Interregional Company
Belkomur
Public share in the capital is 97
7In early 1998 the company Belkomur started
construction of the northern part of the railway
simultaneously from both directions.
8Construction of the bridge over the r. Vashka,
Udorsky District, the Republic of Komi
9The Idea of Belkomur Project
- The project implies a construction of a new
aligning railway 1252 km long, including a new
construction of 795 km, the rest is
reconstruction and modernizing of the existing
lines.
10Belkomur consists of two parts Northern and
Southern
11Belkomur consists of two parts Northern and
Southern
12The new railway is of strategic importance for
Russia since it will provide a direct connection
of the Urals and the Republic of Komi to the
ice-free ports in Arkhangelsk, Murmansk and
Northern Europe.
13Belkomur Project Objectives
- Railway network development in Russian European
North - Infrastructural dead-ends liquidation
- Reduction of transportation distances
- Including idle territories into economic
activities - Railway transportation cost savings
14Project Implementation Stages
- 1st stage Northern Link construction of
Karpogory-Vendinga rail way - 1st order construction of
Karpogory-Vendinga rail way by start-up complex - 2nd order reaching full capacity of the
rail way Karpogory-Vendinga
15Project Implementation Stages
- 2nd stage Southern Link construction of
Syktyvkar-Perm rail way1st order construction
of Syktyvkar-Perm rail way2nd order reaching
full capacity of the rail way Syktyvkar-Perm
16Integrated program for industrial and
infrastructural development of the Republic of
Komi, Perm Region and Arkhangelsk Region
17(No Transcript)
18General financial and economic details General financial and economic details General financial and economic details
Total amount of investment RUR bln. 350
RF Investment Fund assets/private investors assets RUR bln. 75/275
Gross growth in industrial production RUR bln. per year 90
More jobs Number 25 000
Projects payback period
private investment / RF Investments Fund Years 3-15 / 6.5
Revenues to all budgets RUR bln. per year 25
IRR (internal rate of return) 27
19Brief description of the project participantsThe
Republic of Komi
- About RUR 110 bln. of total investments till
2012. - 23 mln. tons of cargo flow per annum (2006)
- Over RUR 20 bln. industrial output growth
by 2010-2012. - 40 - 50 cargo flow increase by 2010-2012.
- Projects included in General Scheme (2007)
- Yarega Mining and Chemical Plant
construction - Vorkuta project
- Bauxite and Alumina Plant construction
- Step Project
- Udora and Troitsko-Pechorsk Pulp-And-Paper
mills projects
20Perm Region Bereznikovo-Solikamsk Industrial Hub
- RUR 120 bln. of total investments till 2012.
- Over RUR 20 bln. industrial output growth
by 2010-2012. - 30 40 cargo flow increase by
2010-2012.Projects included in the Complex
Program (2007) - JSC Uralkaliy project
- JSC Silvinit project
- JSC Solikamskburprom project
- LLC Soda-Chlorat project
- JSC Bereznikovsky Sodium Plant project
-
21Arkhangelsk Region
- Deep-Water Port
- 45 mln. tons of annual cargo turnover
- RUR 45 bln. of total public and private
investments - Over 9,000 jobs
- Servicing ships up to 70,000 tons
dead-weight - 55 km rail way included in the Rail Ways
Development Strategy till 2030
22Projected cargo flows
23(No Transcript)
24Construction of the new railway Belkomur within
Eurasian Transport Corridor
25Construction of the new railway Solikamsk Gainy
Syktyvkar Arkhangelsk within transport
corridor North East West (NEW)
26The major interregional projects within Russian
part of the Northern Transport Corridor
- Karpogory-Vendinga-Syktyvkar-Kudymkar-Perm
- railway
- Ledmozero-Kochkoma railway
- Kotlas motor-road bridge
- Road transport communication within roadway
networks in the Republic of Karelia and
Arkhangelsk Region - Road transport communication within roadway
networks in Arkhangelsk Region and the Republic
of Komi
27A new railway Solikamsk Gainy Syktyvkar
Karpogory Arkhangelsk (Belkomur)
- Total railway length 1252 km
- New construction 795 km
- RUR 75 bln. of total investments
28(No Transcript)