Instrumentation%20and%20Controls%20 - PowerPoint PPT Presentation

About This Presentation
Title:

Instrumentation%20and%20Controls%20

Description:

... Timing System, Diagnostic Interlock Layer, Global Network, Machine ... Demonstrate Diagnostics Interlock Layer prototype hardware, software, interface ... – PowerPoint PPT presentation

Number of Views:32
Avg rating:3.0/5.0
Slides: 24
Provided by: mcr996
Category:

less

Transcript and Presenter's Notes

Title: Instrumentation%20and%20Controls%20


1
Instrumentation and ControlsGlobal Group 2
Update since Snowmass
  • Thursday, December 8, 2005
  • Marc Ross (SLAC), for Hans Braun (CERN), Junji
    Urakawa (KEK), convenors.

2
GG2 BCD document
  • represent place-holders
  • not intended to be as complete
  • expected to evolve
  • not necessarily reflect the status of the
    Baseline Configuration
  • Sub-sections
  • Controls Standard Architecture, Timing System,
    Diagnostic Interlock Layer, Global Network,
    Machine Protection, Low level RF, Feedback
  • Integration with Instrumentation, Machine
    Detector Interface
  • Instrumentation BPM, Beam profile monitors,
    Other (intensity, loss, ring)
  • GG2 ILC wiki http//www.linearcollider.org/wiki
    /doku.php?idilc_controlsilc_controls_home
  • thanks to ANL/FNAL

3
BCD editing Who and Status
  • John Carwardine, Frank Lenkszus, Claude
    Saunders, Andrew Johnson (ANL)
  • Hans Braun (CERN)
  • Ferdinand Willeke, Matthias Clausen, Stefan
    Simrock (DESY)
  • Brian Chase, Margaret Votava, Manfred Wendt
    (FNAL)
  • Junji Urukawa (KEK)
  • Grahame Blair (RHUL), Phillip Burrows (QMUL)
  • Ray Larsen, Marc Ross, Steve Smith (SLAC)
  • Status
  • Needs specification review and comment
  • Sections missing
  • Uneven coverage (chapter to chapter)
  • Uneven coverage (need Asian contributors)

4
Standard Architecture
Primary Controls BCD/RDR impact
  • Key concern Availability (co with GG3)
    controls and electrical (DC/pulsed)
  • Availability Workshop Grömitz (12.2005) ?
    Conclusions
  • Electronics in the tunnel is untenable when
  • 1) it is untested
  • 2) the environment is poorly predicted
  • ? understanding the above can lead to an informed
    judgment
  • disappointing BPM performance universally
    reported
  • failures not directly detected ? resolution,
    systematic errors
  • (behavior not included in availSim)
  • High availability cost can be evaluated
  • RD needed
  • (usually cost effective)
  • Redundancy, rather than up-front gold plating,
    is key
  • fix the replacement time (0), rather than the
    lifetime

5
ATCA Advanced Telecom Computing Architecture
  • Since Snowmass
  • Engagement of ATCA developers
  • Demonstrations / Vendor meetings / Standard
    evaluation
  • evaluation of ILC implementation
  • begin active RD
  • procurement of starter kits
  • ATCA includes micro-ATCA which is appropriate
    for moderate development
  • contact with designers of ATCA HA software
  • software and hardware
  • (ANL, FNAL, DESY, SLAC)

6
(No Transcript)
7
Machine Protection
Biggest BCD/RDR impact
  • 9 section topics ranging from beam dynamics,
    instrumentation, controls, dumps and operation
  • BPMs have to work at 1 - for pilot
  • How many and what kind of dumps? ? should have
    been a Snowmass-10 Q.
  • Linac passive dumps (Alt) ? BCD not consistent
  • Informally (not in BCD proposed since Snowmass)
  • 2 x nominal full
  • 1 x 15 MW ½ way undulator charged beam dump
  • in the head-on xing, this could(?) be the back of
    the e main
  • 6 x ½ MW damping ring and BC/linac entrance
  • injector system also need ½ MW class
  • this is a multi-10s M Q

8
LLRF
Big RD/BCD/RDR impact
  • Active since Snowmass
  • Centers at DESY, KEK and FNAL with partners at
    SLAC and universities
  • Priorities
  • interpret specification and distribute
    performance budget
  • parse the work effort
  • understand TTF performance and collaborate on
    improvements ? are there fundamental problems?
  • TTC Technical board discussion
  • Americas LLRF coordination ? Nagaitsev (RF
    coordinator, FNAL)
  • Meet in January with FNAL engineers

9
Beam Position Monitors Resolution / Calibration
Big operational impact
  • Systematic errors
  • 1) Offsets
  • 2) Gain errors
  • 3) Roll error (or coupling)
  • In a cavity BPM, also coupling between position
    and angle of the trajectory or pitch/yaw of the
    beam
  • Combinations of 1-4 will depend on the intensity,
    beam size, bunch length, and position.
  • Errors 1-4 can also depend on environmental
    effects temperature, beam intensity history,
    electrical noise, presence of nearby bunches or
    satellite bunches.

10
Utility of resolution
  • finding sources of instability and related
    failures
  • a sort of insurance policy must evaluate
    incremental cost
  • development of dither detection and feedback
    techniques
  • very useful at LEP / SLC / etc
  • improved speed / reduced step size of beam-based
    calibration procedures
  • Beam based alignment a poorly named BPM
    offset-finding procedure
  • probably most utility of the above 3

11
BPM system cost
  • resolution is the easiest specification to meet
  • depending on the BPM cavity loss-factor (signal
    size), there is a cost threshold as noise figure
    is lowered
  • believed to be below 0.5 um in linac
  • electronics development costs are more a concern
    than production costs
  • mechanical production cost more important
  • robust system required.
  • RD cost

12
Ongoing BPM RD at ATF, TTF, ESA
  • proving cavity BPM systems for ATF2, BDS energy
    spectrometer, linac (esp cleanability), TTF
    HOMs
  • progress since Snowmass
  • TTF HOM BPM system
  • Cavity placement BPM system
  • full implementation (80 channels)
  • installation 11.2005
  • expect um performance
  • 2K/channel
  • ATF2 Cavity BPM undertest now
  • ESA Cavity BPM tests begin early 06
  • Development of cavity BPM system for FEL
    undulator

13
Beam Profile Monitors (laserwire)
possible long insertion
  • design of emittance measurement system at BD
    entrance
  • Grahame Blair draft ? real design document
  • complex interplay between technology, beam
    optics, backgrounds, basic physics(?)
  • what are accuracy/precision requirements?
  • How much space is needed for a few percent
    system?
  • long system recommended discussion needed
  • BCD content ?

14
Ongoing discussion and RD
  • BCD
  • 3 sets DR to linac
  • 3 sets in the linac (the Euro set 10 20 50)
  • 2 sets / BD side (first one high accuracy)
  • Cost
  • Development of 2m warm insert
  • advised
  • Large E/d extraction systems (WG2 BCD) ?
  • Expect first precision UK laserwire scans at ATF
    next week
  • new PETRA / UK system laser
  • KEK optical cavity design work
  • SNS multi-IP, long laser transport system ?
    working visit early 06
  • Meeting January 30, 2006

15
PETRA two scan planes
ATF extraction line laser wire IP single scan
dimension
16
ILC bunch mechanics
  • What are the inter-bunch timing constraints?
  • interplay with ILC footprint, controls
    (MPS/timing), and beam dynamics
  • post-Snowmass
  • Much misunderstanding of basic limitations
  • impact of undulator source decision
  • impact of DR kicker pulse rise/fall time
    asymmetry
  • draft by Heiko Ehrlichmann (DESY) (12.2005)
  • presentation in tomorrows parallel session
  • special invitation to hear this critical topic
    detailed

17
conclusions
Heikos conclusion slide
  • if the overall kicker pulse length can be small
  • and a high flexibility in operation parameter
    choice is required
  • gt long damping rings with equal circumference,
    every bucket filled
  • taking into account all strong geometry
    restriction
  • if the kicker pulse fall time is expected to be
    long
  • gt gaps for the kicker pulse needs
  • taking into account the reduced flexibility
  • HF frequency changes during the damping times
    could be used for shifting bunch patters between
    two LINAC pulses, but are not able to relax the
    flexibility or geometry restrictions

18
Controls RD testing and paradigm creation
Summary
  • Evaluate industrial HA architecture standards
    for applicability to ILC electronics systems,
    subsystems, hardware, and software.
  • Demonstrate proof-of-principle HA conceptual
    designs of control system backbone and
    representative control system applications.
  • Demonstrate Diagnostics Interlock Layer prototype
    hardware, software, interface to control system.
  • Demonstrate timing and rf master oscillator
    distribution system performance (dominated by BC
    requirements)
  • Adopt appropriate facility-wide hardware and
    software standards for controls, instrumentation,
    and subsystem interfaces.

19
Between Controls and Instrumentation
Feedback/forward RD
Summary
  • built in to the layout
  • feedforward performance not demonstrated
  • what is needed?
  • feedforward under test at ATF (QMUL)
  • fast feedback
  • under test at ATF
  • system planning DESY (XFEL) (SLS - PSI)
  • BPM-in-noise test at ESA
  • important for IP deflection feedback BPMs

20
Instrumentation RD
Summary
  • Test facility usage
  • instrumentation a large part dominant test-beam
    use
  • define expectations
  • develop international working level partnerships
  • ATF, TTF, ESA, A0, Other (smaller, proposed)
  • there are only 2 large pulsed SCRF machines TTF
    SNS RD usage requests disappointingly low in
    both cases
  • we must take advantage of opportunities these
    large SCRF systems provide!
  • existing machines

21
GG2 meetings
Communication is key
  • weekly (started 10.2005) EU/AM adjusted
  • presentations from outside ILC
  • SLS, CERN
  • Draft agenda (the whole year!)
  • planned face to face meetings

22
FNAL Organization
Who we are example
  • Fermilab interests are distributed.
  • CD Patty McBride, Margaret Votava, Vince
    Pavlicek
  • BD Manfred Wendt (Instrumentation), Jim Patrick
    (possibly), Brian Chase
  • TD Jerzy Nogiec (possibly)
  • PD Geoff Savage
  • Controls work as part of ILCTA_at_FNAL
  • CD Ron Rechenmacher, Luciano Picolli, Gustavo
    Cancelo
  • AD Dennis Nicklaus, Sharon Lackey, Brian Chase
  • TD Ruben Carcagno, Jerzy Nogiec, Andrzej Makulski

23
Friday agenda
  • scope definition and anti-definition
  • GG2 / RDR matrix row interaction
  • communication paths
  • bunch timing mechanics presentation
  • Heiko Ehrlichmann (DESY)
  • RDR plans
Write a Comment
User Comments (0)
About PowerShow.com