Title: Services and Patchpanels Installation


1
Services and Patchpanels Installation
  • Type IV installation
  • Connector in situ work
  • Status of PP3
  • Type II/III
  • Testing

2
Status of Type IV Installation
  • Type IV cables are delivered in double lengths
    with connectors installed at the PP3 end and
    pulled between the UX15 cavern and the US(A)
    halls
  • US side completed (October) 2044 cables
    spares
  • USA side installation started more than a month
    ago
  • Problematic Delivery
  • 692 cables received so far
  • Oct 20 (91 harnesses) 26 Oct (155 harnesses)
  • Delivered as double harness but the total length
    corresponded to single cable length (mistake in
    the request)
  • Installation of the harnesses as single cable
    (246) almost one rack on level 1 completed
  • Test after installation between UX15 and USA15
    more complicated
  • Connectors at PS side are cut and will be re-used
    by the company (part of it)
  • Skipped one week because of delay on sending
    bobbins of raw cable from CERN
  • Nov 16 (193 harnesses/386 cables)
  • Length is right (100 m a piece)
  • All 386 cables (tested) are on hold for
    installation since TileCal cables are being
    installed and TC team is reduced
  • but we are in line for installation
  • Dec 9 (only 44 harnesses/88 cables) after a long
    period
  • No large delivery of new cables due to a weird
    technical problem at the factory
  • Expected complete delivery of harnesses in
    January
  • Installation of type IV is on hold for the rest
    of the year and later on it might be interrupted
    by type ii/iii

3
Connectors in situ
  • Double harnesses will be ultimately cut to
    length (1 meter extra for now) on
  • the PS end and connectors will be installed in
    situ by an external company
  • Tooling has been purchased to make prototypes
    and understand issues
  • of this construction
  • All cables in US15 have been cut to extra length
    and are ready to be
  • worked on
  • First rack (200 cables/connectors) completed
    early in July
  • Work performed by SEDELEC, subcontract of
    KontaktSysteme,
  • that provides the double length cables
  • Many mistakes
  • All cables are fixed now (Petr)
  • New Plan
  • Marzio helped finding a company to do the work
  • Nicolas Massol (TC) contact with companies
  • Worked with Petr Kubik (Prague) to discuss
    technical aspects and qualify samples
  • CPE(Italy) selected and contract has been signed
    3 weeks ago
  • Several meetings including a one full day at CERN
    with CPE senior engineers and
  • phone conversations to improve their methods and
    define all the issues

4
US(A) racks
5
Status of PP3
  • PP3 units are in production!
  • First 100 units were received in October
  • 600 production units arrived 2 weeks ago 400
    just arrived
  • Testing
  • Shaun Roe (initially with Igor Ilyashenko and
    help from Pamela Ferrari and Ewa Stanecka for the
    setup) carries on the testing and burn-in.
  • 60 units can be tested at the time (2 PP3 crates)
    with the current number of test cables available
    40 more cables are under construction
  • 24 hours with monitoring continuity on all lines,
    while varying the dummy load so that the Vcc and
    Vdd currents go to zero and the full power supply
    voltage is seen on the PP3.
  • Voltage limiter test by applying 6V to each PP3
    in turn (manually)
  • Didier Ferrere has also tested one PP3 with a
    module, again simulating the situation where the
    module loses the clock and draws no current,
    while observing Vdd and Vcc with an oscilloscope.
  • He reports no voltage spike observed.
  • Plan to test the entire chain (modules/final
    cables/PP3/PS) in SR1
  • Installation
  • Cables are plugged in a few dummy Patch Panels
    during installation to be placed in the right
    (final) position and are tightened to horizontal
    bars
  • Cables will have to be all removed from the
    current position and plugged in by groups/rows
    when the installation of the real PP3 will occur
  • Ashley French and Scott Moncrieff (Melbourne)
    worked on assembly and installation
  • Estimated installation of 90 units per day
    (limited today by testing capability and
    problems)
  • 4 PP3 crate have been installed so far
  • 15 crates assembled (6 ready to be installed)
  • Problems

6
Type II/III
  • TC management Nicolas Massol, Siggi Wenig and
    team
  • Checks with INEO (St Genis)/Thurmelec (Alsace)
  • Pippa/Sandra/Pepe Bernabeu/Maarit White (prepare
    tables of lengths, QA of qualification samples
    etc.)
  • Martin Postranecky (will probably be checking
    samples of double harnesses at CERN
    organization to be finalized)
  • Installation of dummy PP1 and type II cables
  • Lars Erik Lindquist (Uppsala) Neil Fletcher
    (Liverpool) new technicians (will also get
    familiar with detector in SR1)
  • Andy Nichols, Janet Fraser, Jason Tarrant,
    Patrick Werneke to advise on installation/labeling
    of first examples
  • Routine tests after installation
  • Sandra/Petr Kubik and shift crews
  • Will install PP3s in racks to which type III
    cables arrive with highest priority
  • PPB1 need cable tray covers
  • PPF1 rather more parts needed. Cable clamp
    redesign by NIKHEF. Other parts on order via RAL.

7
Timescale for Type II Services
  • Calorimeter has moved to z0. Access to the
    cryostat is possible
  • ID requests should be via Nicolas Massol.
  • Sector 5 (top) first before end of the year
    (heater cables, and a few DCS cables)
  • Sector 13 (bottom) may also start before end of
    year
  • Sector 3 was supposed to follow sector 5, but
    is held up by problems with arches above detector
    and muon chamber installation
  • Sector 9 horizontal towards USA15 may be the
    first to be installed with SCT fibres and SCT
    power cables. This sector is complicated by the
    flexible chains.
  • Sequence in a sector is
  • Tubes, fibres, heater cables, SCT cables, (Muon
    chambers),
  • TRT cables, pixel cables

8
Sectors
9
Plan for Type II/III cables
  • INEO/Thurmelec are at present making double
    length harnesses with type II cable and type II
    connectors on both ends.
  • Work is proceeding to schedule
  • Problems with raw cable quality so far minor
    compared to type IV
  • Will need to order about 4km more type II (sector
    9 longer) and 10-20km more type III (cables
    generally longer than expected)
  • First barrel cables (sector 3) will have the type
    II ends remade to reduce the tolerance on the
    strip back length to the JST/FCI connectors to
    2mm (could be up to 7mm with the initial
    definition).
  • Samples of the FCT (type III) connector have been
    qualified
  • Need cable trays to be in place to measure
    lengths of type II/III harnesses with trial
    cables before FCT cables are trimmed and FCT
    mounted on type III ends
  • Company will then take 2-3 weeks to do this type
    III work
  • Labels are defined and have been printed for
    sector 3
  • Mapping is defined
  • First barrel dPP1 are at CERN and have been
    verified with production cables and the Ljubljana
    test box
  • Experts must verify that mapping is transferred
    to the cryostat bore

10
Testing
  • Tester designed and provided by Ljubljana
    (Gregor, Erik)
  • 3 Test boxes 2 Laptops test cables
  • Need more test cables which are breaking after
    so much use
  • Lots of problems during the last months but seem
    solved now
  • Test steps (for Type IV)
  • Cables are tested at reception (acceptance test)
  • After being routed from UX15 to US(A)15
    (uncut-double length)
  • After connectors are installed
  • Test steps (for Type II/III)
  • Cables are tested at reception (only samples of
    delivered batches)
  • After installation row by row in the cable tray
  • Shift planner (developed by D. Robinson) works
    very well for planning the activities and have
    people to sign up
  • http//www.hep.phy.cam.ac.uk/si-bin/sctworkplanner
    .cgi
  • (and contact me because of unexpected changing in
    rate delivery/testing problems)
  • What is needed to be able to take a shift
  • take the safety training course (level 1-2-3
    video in B55)
  • Level 4 for working in US15 Oxybox (we have
    them)
  • If you have an AIS LOGIN (used for EDH
    documents), you can follow the course from
    anywhere (even outside CERN) with AIS login by
    accessing http//sir.cern.ch. If you have no AIS
    LOGIN, you need to register at the following
    address level4.training_at_cern.ch
  • make the access request on EDH

11
Current Shift Counts
  • shift hoped to be fulfilled based on core
    participation but adjusted for agreed shifts,
    difference between pro-rata and agreed shifts,
    and cable funding participation - shifts from
    "difference" re-distributed between AUS (1/3)
    Cern(1/3) and countries that had not already
    agreed participation (1/3 equally divided among 5
    countries 0.066)

12
PLAN
13
LINKS Summary
  • SCT Cables Web page
  • http//www-atlas.lbl.gov/SCTcables/
  • Mapping
  • https//edms.cern.ch/document/624679/1
  • Shifts
  • http//www.hep.phy.cam.ac.uk/si-bin/sctworkplanner
    .cgi
  • Safety courses
  • Level 1-2-3
  • http//safety-commission.web.cern.ch/safety-commis
    sion/SC-site/sc_pages/training/basic.html
  • Level 4 with AIS login http//sir.cern.ch.
  • Overall Safety and Health Procedure Document
  • https//edms.cern.ch/cedar/plsql/doc.info?cookie4
    472725document_id593278version2
  • Rack Wizard
  • http//atlas.web.cern.ch/Atlas/TCOORD/Activities/I
    nstallation/Database/rack.htm
  • ID installation