Title: U.S. Department of Energy
1U.S. Department of EnergysOffice of Science
OECM Limited-External Independent Review of
the Linac Coherent Light Source
Hanley Lee Federal Project Director DOE Stanford
Site Office October 9, 2007
2Outline
- Purpose of the review
- Project Overview
- Impacts of FY2007 continuing resolution and
funding shortfall - Revised cost and schedule baseline
- Risk and Contingency management
- Conclusion
3Purpose of Review
- EIR based on the limited lines of inquiry
- Evaluate and validate the projects revised cost
and schedule baseline - There is no change in the mission and technical
performance - Recommend to OECM the reasonableness of the
revised cost and schedule baseline
4Project Organization
5Project Overview
1.1 Management, Global Controls
1.1 Management, Global Controls
1.2 Injector
1.3 Linac
1.2 Injector
1.3 Linac
CLO Building
Far Experiment Hall
1.4 Undulator
Far Experiment Hall
Near Experiment Hall
Near Experiment Hall
1.5 X-Ray Transport/Optics/Diagnostics
1.6 X-Ray Endstation Systems
1.9 Conventional Facilities
6Project Overview - continued
- LCLS Mission
- Research and development center for x-ray free
electron laser (XFEL) physics in the hard x-ray
regime and - Provide a facility for the application of XFEL
radiation to experimental science - To achieve the mission, LCLS scope was defined to
build a free electron laser. The scope remains
unchanged in the revised cost and schedule
baseline. - Project is 54 complete as of July 2007
- Civil construction contract is 37 complete
- Overall TEC is 58 complete
- Project performance prior to FY07 was good (PARS
criteria)
7FY2007 Continuing Resolution Impacts
- Project performance degraded rapidly due to the
CR and funding shortfall - Re-directed resources to evaluate impacts,
re-plan activities, and prepare revised baseline
the costs for these efforts are
non-recoverable. - Delayed undulator and controls activities and
procurements until March 2007. - FY2007 funding shortfall cannot be restored until
FY2009 re-plan Photon system activities which
delays project completion to July 2010. - Reporting against the current baseline causes
sharp decline in performance.
8Revised Cost and Schedule Baseline
9Risk and Contingency Management
- Risk Management Process
- Mature process in place used to manage project
risks - Project mitigates risks (through various measures
including VE) without compromising the LCLS
mission and technical performance - Updated monthly
- Provides the basis for cost contingency
- Contingency Management
- Bottoms up development by project staff based on
risks - Centrally managed between LCLS Project Director
and Federal Project Director - Thresholds are defined in the Project Execution
Plan
10Conclusion
- Revised cost and schedule baseline completed with
adequate cost contingency and schedule float - Project mission remains unchanged
- LCLS mission will be achieved with the revised
baseline - Project management systems and processes exists
and working well - Revised baseline is ready for validation