Title: NSPO QM J, JT, and JPD TV Test Preparations
1NSPO QM J, JT, and JPD TV Test Preparations
AMS-02
- Presented by
- Jih-Run Tsai
- Chia-Ray Chen
- National Space Program Office
- July 2003
2Contents
- Test Configuration
- Interfaces
- Electrical
- Mechanical
- Thermal
- Thermal Test Requirements
- Facility Status
- Pre-Test Activities
- Suggestions
- Test Windows
3Test Configuration
- There are three crates and one box (SimDet) will
be installed on thermal baseplate during TV test. - From thermal cycling control standpoint, J and
JPD crates are suggested being installed on
separated test adapters due to different power
dissipation. - SimDet can be thermally isolated from baseplate
with a Teflon block.
J
JPD
JT
SimDet
4Electrical Interfaces
- CSIST and AMS Collaboration will use four 55 pins
of feedthroughs (95-44 CD951 B07H 22-55PS) for
electrical signals and two 24 pins of
feedthroughs (DM5623-37-2-PP) for power. - Optical fiber feedthrough will be used for J
crate during TV test.
5Mechanical Interfaces
- Test adapters provided by NSPO will be installed
between crates and thermal baseplate to simulate
the radiator. - Cho-Therm will be used in the following
interfaces - between test adapters and thermal baseplate to
enhance thermal conduction. - between test adapters and crates to simulate
thermal coupling of flight condition.
crate
Cho-Therm
screws
Test adapter
thermal baseplate
6Thermal Interfaces
- Test heaters and thermocouples will be installed
on thermal baseplate, test adapter, crates inside
and outside to control and monitor temperature
variations during test. - Locations of test thermocouples will be defined
as follows - inside and outside crates by NSPO thermal group
based on test prediction result including
interfaces of PCBs and case for model
correlation. - on chips or parts by CSIST and CERN engineers
for temperature monitoring.
7Facility Status
- Some maintenance on STVC LN2 piping will be
conducted in August. - Some software modification on TDHSHCS-II will be
performed in August.
Thermal Data handling System Heater Control
System (TDHSHCS-II)
Small Thermal Vacuum Chamber (STVC)
8 Test Requirements Temperature Profile
Temperature (Proto-flight Test Level)
Pump Down
Thermal Balance Phase
Return To Ambient
Thermal Cycling Phase
Chamber Environments Pressure?1.0x10-5 mbar
Hot non-operation (85oC)
1 hr
2 hrs Hot soak
2 hrs Hot soak
1 hr
1 hr
Hot Operation (55oC)
Transient Cool-Down
Hot Balance
Ambient
Cold Balance
Cold Operation (-25oC)
Operation (on)
2 hrs cold soak
2 hrs cold soak
Non-operation (off)
Cold non-operation (-45oC)
1 hr
1 hr
1 hr
1 hr
Turn on
Turn off
I
A
B
C
D
E
F
G
H
J
K
L
O
Q
M
N
P
9 Test Requirements Thermal Control Criteria
- Thermal Cycle Testing
- The mounting feet are within 2?C of the specified
proto-flight temperature limit. - No mounted thermocouple is varying at a rate
greater than 1?C/hr as measured over a period not
less than one (1) hour. - Thermal Balance Testing
- No mounted thermocouple is varying at a rate
greater than 0.2?C/hr as measured over a period
not less than one (1) hr. - All heater settings remain unchanged over a two
(2) hour period which will include the 1 hour
period outlined above. - Temperature Transition Rate
- The temperature transition rate shall be limited
to a rate equal to or less than 1?C/min as
measured by the test article control
thermocouples.
10 Pre-Test Activities
- Major tasks will be done by NSPO before J, JT,
and JPD TV test - Crates pathfinder TV test in progress
- MGSE (Test adapter) design and manufacture in
progress - Test instrumentation preparations (test heaters
and thermocouples) materials are ready - Thermal hardware preparations (MLI, Cho-Therm)
materials are ready - Pre-test predictions waiting for CGS thermal
models (J, JT, and JPD) - Hot and cold boundary conditions (radiator
simulator - test adapter) ---- waiting for the
result from CGS - Test procedure need more information about
functional test from CERN
11Suggestions
- In order to test AMS-02 crates more efficiently,
some suggestions are proposed as follows - Please check outgassing data before use them.
- (standard value lt1TML, lt0.1CVCM)
- Please wear gloves in crate handling processes.
- Please clean all bolts with IPA before using
them. - If there is any contamination on crate during
environmental test, please clean the crate before
shipping to NSPO. - Please provide material data sheet for each
crate. - ESD should be avoided (wear wrist-stats at all
time during crate assembly). - Based on the request from AMS-02 test team, hot
cold soak temperatures will be the protoflight
(or acceptance) temperature 1oC.
12Test Windows
- Three test windows are allocated for AMS-02
crates thermal vacuum tests by using NSPO test
facility as follows
10/15/2002
1/15/2003
6/15/2003
9/30/2003
8/31/2003
11/20/2003
ROCSAT-2 Mission Simulation and Launch Site
Operation
ROCSAT-2 TV Test and related activities
1st test window for QM test
2nd test window for QM test
grace period
12/31/2003
08/01/2004
03/15/2004
11/20/2003
12/31/2004
05/15/2005
ROCSAT-3 Spacecraft IT (5 satellites)
ROCSAT-2 Early Orbit Checkout
3rd test window for QM FM test
Possible range for FM test (depending on
ROCSAT-3 IT activities)