Title: AMS02 Thermal control system status report
1AMS-02 Thermal control systemstatus report
- M. Molina CGS
- X. Zhu SDU
- I. Corradino CGS
2- TCS Structural Test Article status report
- X. Zhu 20 min
- AMS Thermal analysis status
- I. Corradino 20 min
- TOF TV tests and model correlation
- M. Molina 20 min
- Final remarks on TCS FM Manufacturing
- TVT in LSS Friday 28th July
3Structural Test Article (STA) for Crates and
Radiators
Presented by X. Zhu (SDU)
- CGS A. Assenza, M. Olivier
- SDU S. Zhang, J. Cheng, J. Zheng, W. Zheng
4Contents
- Mechanical parts production (Crates)
- Status of Radiator STA
- Structure Analysis
5Mechanical parts production
- Total 440 pieces
- Drawing OK
- Already Finished
- 376 pieces, 85
- All completed by
- End of August, 2006
6Mechanical parts preassemble
U Crate
JT Crate
7Mechanical parts preassemble
S Crate
UPD
8Status of Radiator STA
- Heat pipe profiles
- Insert testing manufacturing
- Radiator panels
9Heat pipe profiles
- Material AL Alloy 6063 T5
- Material situation purchased
- For main radiators 52 Pieces
- For tracker radiators 14 Pieces
10HP profile for radiators
STA for Main Rad
STA for Tracker Rad
11HP Manufacture
Die
Extrusions
HP profiles have been produced by extrusions (6
m pieces available) (no filling and no surface
treatment)
12Inserts design and sample testing
- Aluminum alloy inserts are bonded in sandwich
panels - Sandwich panels are Rohacell with aluminum skins
- 15 samples (per insert type and per test type,
tension and shear 15 x 2 x 2) are required to
determine the allowable shear and tension force - The 15 samples must be built with the same
materials and processes as the FM
13Insert manufacturing for STA and test samples
- Material AL 7075 T7351
- Material situation purchased
- 89 inserts already machined, out of
- 299 for STA
- 30 for test samples
14Insert samples manufacture and testing
- Open issues
- SDU facilities are not suitable for large
sandwich panels construction - Therefore external companies need to be found for
STA radiator and test samples manufacturing - Specialized companies will be looked for in China
and chosen with the support of CGS - Target date for specialized company selection is
end of August 2006 - Backup solution is Plyform (Italian company)
15STA radiator panels skins
- Material (skins) AL 5052 H32
- Material supplier has been already identified
- Material will be available in 2 months after
ordering - Structural analysis (still ongoing at SDU) must
provide limit loads not to be exceeded during STA
test.
16Radiator panels Foam
Material supplier has been already identified
from Degussa China Branch. Material will be
available in 3 weeks after ordering
17Adhesive
- REDUX 312L the bonding between
- the face sheet and foam, insert ,
- heat pipes.
- REDUX 840 the bonding between
- foam and insert, heat pipes.
- Supplied by Hexcel China branch
- Limited shelf timewill be purchased as needed
18New Structure Analysis (ongoing)
- Reason
- To simulate the resultant loads in the WAKE
radiator that correspond to the actuator loads
being applied to the USS-02 during STA static
test. The loads have been recently selected by
JS. - Aim
- Ensure that the WAKE radiator is not overloaded
during the test - To see how closely some of the regions of the
WAKE radiator match flight stresses or loads.
19Structure Analysis
- The analysis is being done by J.Zheng (SDU) and
M.Olivier (CGS).
20Summary
- The production of STA crates will be completed by
the end of Aug. 2006. - STA crates will be shipped from SDU to CERN on
1st,Sep. 2006 - STA radiator panels need be completed by the end
of Dec. 2006, to be delivered to CERN by the end
of Jan. 2007 - STA RADIATORS DELIVERY SCHEDULE IS CRITICAL AND
ALTERNATIVES ARE UNDER INVESTIGATION
21AMS-02 Thermal analysis ISS new configuration
and survey status.I.Corradino (CGS)
22Outline
- Summary of changes on ISS thermal model
- From version 4 revision 4 (v4r4)
- to version 5 revision 3 (v5r3).
- Survey analysis status for hottest and coldests
cases determination - 1000 rays in Monte Carlo simulation
- Completed cases
- 15000 rays
- Completed cases
- I/F data delivered
- Future steps
23ISS v4r4 configuration
24ISS v5r3 configuration
25ISS configuration changes
- The changes to ISS configuration consist of the
removal of two main elements - SPM (Science Power Module, i.e. the Russian
tower) - CAM (Centrifuge Assembly Module).
26ISS v4r4 geometrical model
27Detail of SPM and CAM modules
v4r4 v5r3
28ISS update orbital cases selection
- In April 2006 when generating I/F data for TTCS
(SYSU) a shadowing effect was found due to the
Centrifuge Assembly Module at high Beta angles.
CAM Is not to be in the final ISS configuration - Therefore initial simulations
- Beta75
- Beta0 due to the zenith location of the russian
tower - These two cases were assumed to be as the ones
with larger impacts after the changes. - Later on the survey was expanded to the whole
beta range
29Survey analysis (1)
Model AMS-02 TMM version 4.1
- Major differences wrt previous version (ver. 3.4)
- New thermal models for
- BCS camera,
- TRD Gas Box,
- HVE and HVR bricks,
- CABLES,
- SUPPORT BARS
- Updated thermo-optical properties for Vacuum Case
and USS. - Changed MLI distribution on USS or mass saving
purposes.
30CAM shadow (view from sun)
31CAM shadow (view from sun)
32AMS TMM v4.1
33Model updates
CABLES
TRDGB
Support bars
HVE/HVR
BCS Camera
34Clear anodized
- USS02 changed t/o properties
MLI
Beta Cloth
Silver Teflon
Version 3.3
Version 4.0
35Survey analysis (2)
- Complete survey of AMS-02 thermal behaviour
-
- The survey covers
- 7 Beta angles (-75, -60, -30, 0, 30, 60, 75)
- 37 Attitudes
- Yaw (-15, 0, 15)
- Pitch (-20, 0, 15, 25)
- Roll (-15, 0, 15)
worst cases classification for each detector
Total number of cases 259
36Survey analysis (3)
- NOMINAL orbital parameters
- Solar flux 434.6 BTU/Hr-ft2
- Earth IR 76.4 BTU/Hr-ft2
- Albedo 0.27
- Altitude 215 nm
- End Of Life T/O properties
37Approach
- Major concern Computational time for Geometrical
Model simulations - Decreasing of 1 order of magnitude in number of
rays ? 1000 rays per surface (in place of 15000) - Case sorting for each subsystem.
- Possible sorting errors ? accurate analysis (15K
rays) for five worst cases (hot and cold) for
each subsystem.
38Survey output example (1)
Subsystem TRD
Survey 1k ray sorting (5 cases)
39Survey output example (2)
Subsystem TRD
Coldest according to 1k ranking
Survey 15k ray accurate analysis (5 cases)
Second hottest according to 1k ranking
40Survey output example (3)
Subsystem TRD
Survey 15k ray accurate analysis (5 cases)
41Lesson learned
- 1k vs 15k rays sorting can be different
- 1k rays temperatures should be only used for
ranking purposes, because of - Environment (Nominal vs Cold/Hot)
- Simulation accuracy (1000 rays only)
42Current status of the thermal analysis
43I/F DATA delivered to TRD group(28th june 2006)
44Future Steps
- 15 k Survey completion
- Generation of 5 hottest and 5 coldest plots for
each detector - Collection of the survey results in a document
- I/F data delivery to
- TTCS
- CAB
- other subdetectors on requests
45TOF TV-TB test
- Prepared by C. Vettore (CGS)
- and S. Borsini (SERMS)
- Presented by M. Molina
46Lower TOF positioning in TVC
47Lower TOF positioning in TVC
48PRE-TEST ACTIVITIES
- Waiting the TRR pre-tests have been done on the
L-TOF to - assess the time needed to reach high vacuum
conditions with TOF - cleaningless (outgassing?)
- venting from honeycomb ?
- virtual leakage from Poron (approx.
30 liters in the TOF)! - familiarize with the thermal response to T
gradients - (realistic evaluation of the test duration)
49FIRST LTOF DEPRESSURIZATION
P (mbar)
Time (min)
48 hrs only to reach (nearly stable) conditions
for high vacuum (5 x 10-2 mbar)
504th LTOF DEPRESSURIZATION
P (mbar)
Time (min)
(Only) 22 hours needed to reach the high vacuum
conditions
51FINAL LTOF DEPRESSURIZATION
P (mbar)
Time (min)
(Only) 14 hours needed to reach the high vacuum
conditions!
52PRE-TEST TEMPERATURE PROFILE
External Sensors
53Internal Sensors
The internal sensors temperature rate is lower
than the external sensors gradient
54TOF TV-TB TEST
- TEST STATUS
- The Lower TOF flight model has been tested at
S.E.R.M.S. in the Thermal Vacuum Chamber (TVC)
during the period May 26th June 9th 2006. - TEST PROFILE
- The maximum and minimum TRP temperatures are
summarized in the following table
55Lower TOF TEST PROFILE
56TEST SENSORS MOUNTED ON Lower TOF
- 44 sensors have been located on the external
structure of the L-TOF - 1 not working. ? NCR
- 14 sensors have been located inside the Lower
TOF. These are the Temperature Reference Points
(TRP). - 1 not working. ? NCR
57Lower TOF TRPs TEMPERATURES
58Lower TOF TVC PRESSURE
NCR
59TEST SUCCESS CRITERIA
- Acquisition of temperatures of TOF in hot/cold
stabilized condition (TB test) for sufficient
number of relevant points for thermal
mathematical model correlation purposes. - DONE
- Definition of the Maximum/Minimum CP temperature
with respect to the maximum/minimum PMT (TRP)
allowed temperatures. - DONE
- Heaters and thermostats nominal operations (in
terms of dissipation and duty cycle) - DONE
- Survival (minimum) temperature definition with
heaters enabled. - DONE
- Minimum switch-on temperature is reached using
the heaters. - DONE
- Internal thermal design is performing according
to the specification, i.e. the internal heat
dissipating sources are well sunk to the TOF
body, hence showing small delta-T. - DONE
60REPORTED NCR (1/2)
- 2 NOT WORKING SENSORS
- Internal sensor (14) does not monitor a trp and
the sfec board temperature is correctly measured
by other 3 sensor - External sensor (6) is a redundant one. after
having verified the correct functioning of the
main sensor, no corrective actions have been
taken - THE MEASURED POWER CONSUMPTION FOR THE SFEC BOARD
HAS BEEN LARGER THAN PREDICTED (NAMELY 320 mW
instead of 130 mW) HAS NOT BEEN CONFIRMED DURING
THE TEST - SFEC power consumption does not affect TRP
behaviour and it has no impact on the test
objectives
61REPORTED NCR (2/2)
- ACCIDENTALTEST INTERRUPTION, with pressure raise.
- Facility emergency procedure. the vacuum
specified condition has not been respected for
less than 25 minutes. - 2 HOUR INTERRUPTION OF DATA ACQUISITION during
the beginning of the first descent phase (from
HOT operative to COLD non-operative) - Chamber temperature brought up to the value of
the hot stabilization. problem was solved.
62MODEL CORRELATION (1/5)
MODEL VALIDATION SUCCESS CRITERIA The adopted
correlation criteria are as follows Temperature
level criteria The average of all the temperature
deviations (measured value minus predicted value)
has to be less than /- 2C Where N is the
number of temperature measurements
points. Standard deviation criteria The standard
deviation of the temperature differences between
measured and predicted data has to be lower than
3C, namely
63MODEL CORRELATION (5/5)
- The following parameters had to be tuned to
correlate the model - CONTACT CONDUCTANCES
- PMT BRACKET TO TOF CARBON FIBER BOX
- X 10
- PMT BRACKET TO HONEYCOMB SUPPORT
- X 5
- SFEC BOARD THERMAL CONDUCTANCES TO CARBON FIBER
BOX - / 30
- COMPOSITE MATERIAL CONDUCTANCES
- HONEYCOMB SUPPORT CONDUCTANCE (IN PLANE)
- X 5
64MODEL CORRELATION (2/5)
Criteria ?TAV lt 2C STD_DEV lt 3C
65MODEL CORRELATION (3/5)
TRPs temperatures before and after correlation
66MODEL CORRELATION (4/5)
Control Points temperatures before and after
correlation (control points sensors are
positioned on the external structure of the Lower
TOF)
67MODEL CORRELATION (5/5)
- The following parameters had to be tuned to
correlate the model - PMTS BRACKET TO BOX CONTACT CONDUCTANCE IN BOX
X/-X - Initial value 0.006 W/K ? final value 0.09
W/K. - PMTS BRACKET TO HONEYCOMB SUPPORT CONDUCTANCE
IN BOX Y/-Y - Initial value 6.23E-03 W/K ? final value
3.1E-02 W/K. - CONDUCTANCE WITHIN PMTS HONEYCOMB SUPPORT IN
BOX Y/-Y - Initial value 1.08E-02 W/K ? final value
5.4E-02 W/K. - PMTS SUPPORT TO BOX CONDUCTANCE IN BOX Y/-Y
- Initial value 2.49E-02 W/K ? final value
4.98E-02 W/K. - SFEC THERMAL CONDUCTANCES from board to carbon
fiber box - Initial value 1 W/K ? final value 0.035 W/K.
68Coming Thermal tests
- E-crate retest Aug 2006 INFN PI
- ECAL QM Sept 2006 CGS
- CDD TVT Oct 2006 JS
- TTCS EM end of 2006 SYSU/NLR
- RHV TVT End 2006 CIEMAT
- UPS TVT Early 2007 NSPO
- Ucr.and UPD Early 2007 SERMS
- ACC TVT Early 2007 RWTH, Aachen
- TRD GB (QM) Late 2006 RWTH, Aachen
69TCS FM HARDWARE MANUFACTURING
- Top level identified products are the following
- Main and tracker radiators
- MLI
- Cryocooler TCS
- CAB TCS
- Responsibilities for TCS FM hardware
manufacturing are being discussed