Title: Is DesignBuild Right for My Next Parking Garage
1Is Design/Build Right for My Next Parking Garage?
- Presented by Donleys
- Source Material from
- PDI Project Delivery Institute
- CII Construction Industry Institute
2Agenda
- Construction Delivery Systems
- Explanations
- Advantages Disadvantages
- When does Design/Build Make Sense?
- The Process of Procuring Design/Build Services
3Delivery Systems
Project Delivery defines the relationships, roles
and responsibilities of parties and the sequence
of activities required to design and construct a
facility.
4Types of Delivery Systems
- General Contracting (Design/Bid/Build)
- Construction Management
- Design/Build
- Integrated Project Delivery (IPD)
5The General Contracting System
Preconstruction
Design Complete--Project Bid to Multiple GCs
6General Contracting Elements
- Owner contracts separately with designer and
contractor - Designer provides Complete design documents
- Owner warrants to contractor completeness and
accuracy of drawings - Contractor guarantees to construct to the
drawings specifications for amount of bid - Contractor manages project through construction
phase to schedule, quality and budget (bid amount)
7General Contracting Advantages
- Competitive nature of bidding process results in
a competitive price as designed - General Contractor takes on the risk of
performance of all subcontractor contracts - General Contractor guarantees completion of
project per bid amount (per drawings)
8General Contracting Disadvantages
- Greater potential for changeorders due to
misunderstandingof drawings, incompleteness - Potential for overages on bidday resulting in
- Delays in construction
- Redesign costs
- Reduction in scope
- After the fact value engineering alternatives
- No constructability review
- Less control over subcontractor quality
- Higher likelihood of a combative vs. partnering
approach between owner, architect and contractor
9The Construction Management System
Preconstruction
10The Construction Management System
Construction
11Construction Management Elements
- Early involvement of CM during the
Preconstruction Design Phase - Estimating, value engineering, constructability
services provided during Preconstruction - Guaranteed Maximum Price
12Construction Management Advantages
- Early accurate knowledge of cost
- Earlier GMP based on more thorough knowledge of
project - More control over subcontractor selection
- Coordinated early purchase of owner equipment
- Reduced construction cost through
constructability review - Less likelihood of change orders through
constructability review - Savings from GMP to the owner (open book
accounting) - Reduced involvement/management by owner
- Greater level of management information provided
to the owner
13Construction Management Disadvantages
- Potential increased overhead and general
conditions - Competitive bidding is limited to the
subcontractor level - Public entities cannot always use CM At Risk,
taking away advantages of - GMP
- Risk of subcontractor default
14The Design/Build Contracting System
Construction
Preconstruction
Design Builder
Architect
15Design/Build Advantages
- Partnering team approach
- GMP commitment at project start
- Reduced design time
- Reduced construction time
- Design Builder has totalresponsibility for
design, cost, schedule - Single source responsibility for warranty
- Optimize value engineering and constructability
- Reduced cost
16Additional Advantages to Competitive
Design/Build Procurement
- More Choice - Multiple design approaches
- Less up-front cost - Limited up-front expenditure
even if
bridging architect is used - More qualified candidates
- Ability to compare guaranteed costs of
alternative designs
17Performance of Various Delivery Systems
- Unit Cost Construction Speed Delivery Speed
18Performance Evaluations of Delivery Systems
Comparisons
Source PDI - Project Delivery Institute CII -
Construction Industry Institute
19Selecting the Proper Delivery System
- Project Characteristics
- Scope Change Potential
- Owner Characteristics
- Impact of Risk on Project
20Selecting the Proper Delivery System
Project Characteristics
- Is the schedule critical to the organization?
- Are the owners project requirements easy to
define? - Is low cost a key factor in the project?
- Is an early guaranteed cost a major advantage?
Consider D/B Delivery Method
21Selecting the Proper Delivery System
Scope Change Potential
- Is the project in the early design phase?
- Is there room for flexibility in the design
approach?
Consider D/B Delivery Method
22Selecting the Proper Delivery System
Impact of Risk on Project
- Is the owner risk aversive?
- Is a guaranteed price earlier in the design phase
important to - Funding?
- Board acceptance approval?
- Schedule?
- Determining scope?
- Management acceptance of program?
- Could an overages at the end of the design
dramatically impact - Management approval acceptance?
- Schedule?
- Funding?
- Scope?
- Operations?
Consider D/B Delivery Method
23Selecting the Proper Delivery System
Owner Characteristics
- Has the owner built similar facilities?
- Is there available staff accessible to make
decisions early on? - Does the owner want to minimize involvement in
day to day management? - Is the owner in an environment where Design Build
is possible?
Consider D/B Delivery Method
24Key to Successful Design/Build
- Good initial program definition / bridging
document with defined owner requirements - Qualified evaluation of proposals
- Qualified Design/Build candidates - experienced
at - Type of Construction (garage)
- Design/Build Construction Process
- Program Administration during Construction Phase
25(No Transcript)
26OverviewThe Design/Build Process
27Design/Build Team Selection Process (Phase 1)
Shortlist
28Design/Build Team Selection Process (Phase 2)
Proposals
Review of Proposals Optional Presentation
29Design/Build Design Completion Construction
(Phase 3)
Selection
Owner / Design Builder Meetings
30Design/Build Construction
- How to Procure
- What to Expect
31- Define your ideal team
- Should include experienced specialists in
Functional Design, Structural Design,
Architectural Design Construction
Team Requirements
32Design/Build Request For Qualifications
- Experience with the type of construction
- Architect
- Engineer
- Contractor
- Experience with the Design/Build delivery system
- Experience of the individuals on the team
- Experience of the team working together
33- Define your ideal team
- Should include experienced specialists in
Functional Design, Structural Design,
Architectural Design Construction
Team Requirements
- Define what you want (the RFP)
- Outlines owner requirements to D/B
candidates, including - Number of spaces, levels
- Façade and other desired design features
- Required structural system
Design Requirements
34Typical RFP Requirements
- Minimum Number of Spaces
- Structural Systems
- Maximum Footprint
- Maximum Floors
- Minimum Design Life
- Architectural Guideline
- Minimum System Standards
- Electrical
- Mechanical
- Revenue Control
- Other Program Requirements
- Guaranteed Base Price and any Alternates
35(No Transcript)
36(No Transcript)
37- Define your ideal team
- Should include experienced specialists in
Functional Design, Structural Design,
Architectural Design Construction
Team Requirements
- Define what you want (the RFP)
- Outlines owner requirements to D/B
candidates, including - Number of spaces, levels
- Façade and other desired design features
- Required structural system
Design Requirements
- The Value of Choice
- Design/Build allows the owner to select the best
design from the concepts of each Design/Build
proposer.
The Design Proposals
38The Proposal What You Get
Functional Elements
39The Proposal What You Get
Structural Elements
40The Proposal What You Get
Architectural Elements
41- Define your ideal team
- Should include experienced specialists in
Functional Design, Structural Design,
Architectural Design Construction
Team Requirements
- Define what you want (the RFP)
- Outlines owner requirements to D/B
candidates, including - Number of spaces, levels
- Façade and other desired design features
- Required structural system
Design Requirements
- The Value of Choice
- Design/Build allows the owner to select the best
design from the concepts of each Design/Build
proposer.
The Design Proposals
- No Surprises
- Eliminates wasted design time
- Compare Design vs. Price
- Speeds the approval completion process
GMP Early in the Process
42Guaranteed Maximum Price
43- Define your ideal team
- Should include experienced specialists in
Functional Design, Structural Design,
Architectural Design Construction
Team Requirements
- Define what you want (the RFP)
- Outlines owner requirements to D/B
candidates, including - Number of spaces, levels
- Façade and other desired design features
- Required structural system
Design Requirements
- The Value of Choice
- Design/Build allows the owner to select the best
design from the concepts of each Design/Build
proposer.
The Design Proposals
- No Surprises
- Eliminates wasted design time
- Speeds the approval completion process
GMP Early in the Process
- Fast-Track, without Fast-Track Pricetag
- Design construction phases overlap
- Project delivery as much as 33 faster than
design-bid-build
Early Construction Start Finish
44Early Construction Start Finish
45Architectural Design Options
46Is Design/Build Right for My Next Parking Garage?
- Presented by Donleys
- Source Material from
- PDI Project Delivery Institute
- CII Construction Industry Institute