Title: Undulator Schedule Update
1Undulator Schedule Update
David Schultz
- People
- Status
- Project schedule
2New responsibilities in Controls
- Enzo Carrone has joined LCLS and the Controls
Department as the Deputy Controls Head for LCLS.
3BTH looking east
4Backfill operation over Beam Dump and FEE
5Electron Beam Dump
6Finishing the Final Floor Slab in X-ray Tunnel
7Installing re-bar in the Far Experimental Hall
8LTU stand installation
4/21/08
9Undulator girder assembled at SLAC
10LCLS installation and commissioning time-line
First Light in FEE
FEE/NEH Install
First Light in FEH
PPS Cert. LTU/Dump
CD-4 (7/31/2010)
X-Rays in NEH
FEH Hutch BO
LTU/Und/Dump Install
FEH Install
PEP-II run ends
now
J
F
M
A
M
J
J
A
S
D
J
F
M
A
M
J
J
A
S
O
N
D
J
F
M
A
M
J
J
O
N
A
A
M
2008 2009
2010
Down
PPS
LTU/Und Comm.
Re-commission Inj/BC2 to SL2
NEH Operations/ Commissioning
Linac/BC2 Commissioning
FEE Comm.
April 18, 2008
11Undulator girder assembly schedule
Near the Project critical path
P3 dates
Now in progress
RFI
We are 1 month ahead of schedule. ANL component
delivery is now sufficient to support assembly.
12Undulator Schedule
- Near the Project critical path
- Assemble Grider 10 8/11/08 We are 1 month
- Assemble Grider 20 9/23/08 ahead of this
- Assemble Grider 30 11/17/08 schedule.
- Racks due 6/15
- Install
- Connect power
- Terminate cable plant 1/15 (P3) Need some way to
do - Checkout system checkout sans racks.
13Summary
- Installation has begun in the LTU.
- Installation in the Undulator and Dump areas
waits for area co-occupancy. - Installation of pedestals begins next week in
U-Hall. - Starting with drilling the floor.
- Girder assembly is just about underway. Critical
Path. - About a month ahead of schedule
- Lets keep it that way!
- Need BFWs and BPMs at a rapid pace.
- Rack connection will lag. Need to check support
movers early, need to check racks early.