Adjusting the - PowerPoint PPT Presentation

1 / 22
About This Presentation
Title:

Adjusting the

Description:

Register operational meter and DMP relationship. ... Includes vendor system changes to Market Information Systems (MIS) and ... – PowerPoint PPT presentation

Number of Views:26
Avg rating:3.0/5.0
Slides: 23
Provided by: darrenfi7
Category:

less

Transcript and Presenter's Notes

Title: Adjusting the


1
Adjusting the Dispatch Instructions to the
Defined Metering Point (DMP).Functional
Deferral 6 (FD-06)
  • Market Operations Standing Committee (MOSC)
  • April 23rd, 2003

2
Background
  • March 2000, the TP was informed that certain
    functionalities would be deferred beyond the
    November market commencement date.
  • FD-06 - Adjusting Dispatch Instructions to the
    DMP
  • Requires mapping of the operational meter data to
    the point of sale.
  • Impacts CMSC as the dispatch instruction is
    currently treated as occurring at the operational
    meter.
  • Technical Panel (March 7, 2000) deemed the
    deferral to be acceptable and staff should assess
    the impact of high loss situations if any. The
    Panel noted that the losses could be
    significantly larger when viewed as a portion of
    CMSC.
  • Current thinking shows that both over and under
    payments to dispatchable facilities can occur.

3
What will change?
Operational Meter
DMP
RWM
  • TODAY
  • Dispatch Instructions (DI) and Market Schedules
    (MS) are issued to the Operational Meter.
  • Dispatch and dispatch compliance is measured at
    the Operational meter.
  • Settlement (CMSC) uses the DI and MS referenced
    to the operational meter.
  • Actual output and energy payment is based on the
    AQEI which is the RWM actual converted to the DMP
    using a correlation factor.

4
What will change?
Operational Meter
DMP
RWM
  • FUTURE
  • Dispatch Instructions (DI) and Market Schedules
    (MS) are issued to the Operational Meter for
    realtime dispatch BUT are converted to the DMP
    prior to settlements.
  • Dispatch and dispatch compliance is measured at
    the Operational meter.
  • Settlement (CMSC) uses the DI and MS referenced
    to the defined metering point.
  • Actual output and energy payment is based on the
    AQEI which is the RWM actual converted to the DMP
    using a correlation factor.

5
Current Status
  • The IMO has filed for, and received an exemption
    for the period of March 1st to August 1, 2003.
  • Conditions of the exemption include
  • Provide a detailed study to identify and better
    understand the implications on the marketplace
  • Identify and understand the impacts associated
    with implementing the functionality (Market
    Participants and the IMO)
  • Determine whether or not the implementation of
    this functionality will materially benefit the
    marketplace and
  • Stakeholder recommendations with Market
    Participants.

6
Options Going Forward
  • Option A
  • Considering the impacts, remove the functional
    requirement and retain existing settlement
    calculation.
  • Option B
  • Implement the functionality
  • Register operational meter and DMP relationship.
  • Translate the dispatch instructions and market
    schedule quantities to the DMP after the dispatch
    day but prior to settlement determinations.

7
Areas of Discussion Today
  • Market costs to implement loss calculations.
  • IMO costs to meet the intent of FD-06.
  • Meter Evolution.
  • CMSC Evaluation.
  • Issue Evaluation.

8
Market Costs to Implement
  • The actual implementation details are not
    finalized at this time but there are two general
    approaches currently under debate
  • Option A - Where the operational meter is
    registered with the IMO similar to the RWM, a
    correlation factor will be determined and used
    by the IMO. This factor would reflect, with some
    accuracy, installations with loads between the
    operational meter and RWM operational meter
    inaccuracy. Cost estimated to be 700K split
    evenly between the IMO and MP.
  • Option B - Where the IMO uses simple losses from
    the operational meters. (Installations with loads
    between the the operational meter and RWM would
    need further consideration.) Cost estimated to be
    320K.

9
IMO Costs to Implement
  • Initial assessment indicates system costs of
    about 350K.
  • Includes vendor system changes to Market
    Information Systems (MIS) and Settlements
    systems, testing and documentation.
  • Costs associated with Option A (IMOs portion)
    350K 50K/year maintenance.
  • Resource costs are not as well defined but based
    on previous experience defining the RWM/DMP
    relationship this activity could take upwards of
    two years.
  • Includes the calculation and registration of loss
    factors in cooperation with dispatchable
    participants for 300 meters.

10
Total Costs
  • Total estimated costs are
  • Option A 1 million
  • Option B 700 thousand

11
Meter Evolution
  • Some new meter installations have hybrid meters
    with the RWM and operational meter at the same
    source.
  • If this evolution continues then the
    functionality is no longer required.
  • Issues such as divergent standards for repair may
    impede this evolution
  • Operational metering repairs are required, due to
    real-time impacts, within a relatively short
    period (24/48 hours).
  • RWM errors due to the Validate, Edit, Estimate
    (VEE) process have to be resolved within 6 days.
  • MSP costs to maintain the operational meter may
    overwhelm the savings associated with the single
    meter design.

12
Quantifying CMSC Impacts
  • Import and Export CMSC is unaffected due to the
    use of schedules for settlement.
  • Preliminary review indicates that OR CMSC
    payments are also unaffected due to schedule
    versus actual settlement.
  • Due to the limited amount of CMSC associated with
    nuclear facilities these facilities are not
    considered to be large contributors to the market
    impact.

13
Assumptions and Examples
  • Primary impact of this functionality is on the
    CMSC quantity. The following examples express MW
    differences between CMSC quantity today and a
    post implementation quantity.
  • Dispatch instructions are issued to the
    operational meter for real-time operation of the
    facility. The translation, of the dispatch
    instruction and market schedule quantity, to the
    DMP would occur after the dispatch and prior to
    settlements.
  • The examples assume 100 compliance with the IMO
    dispatch instructions at the operational meter.
  • For illustration purposes, losses in the example
    are 1 from the operational meter to the DMP.

14
Assumptions and Examples
  • Existing CMSC calculation rules
  • Constrained ON calculations for generators use
    the lesser of the actual output at the DMP or the
    dispatch instruction.
  • Constrained OFF calculations for generators use
    the greater of the actual output at the DMP or
    the dispatch instruction.
  • Definitions
  • Market Schedule MS
  • Dispatch Instruction DI
  • Actual output at the DMP AQEI
  • Losses of 1 f

15
Current vs. Future - Constrained ON
Operational Meter
DMP

Today Future the RT dispatch is to a DI of
150MW.
TODAY MS 100 MW DI 150 MW AQEI 148.5
MW CMSC Quantity 48.5 MW
16
Current vs. Future - Constrained ON
Operational Meter
DMP

Today Future the RT dispatch is to a DI of
150MW.
TODAY MS 100 MW DI 150 MW AQEI 148.5
MW CMSC Quantity 48.5 MW
FUTURE MS 99 MW DI 148.5 MW AQEI 148.5
MW CMSC Quantity 49.5 MW
This illustration shows that during a constrained
on event the constrained participant is
receiving less CMSC than if the functionality
were implemented.
17
Current vs. Future - Constrained OFF
Operational Meter
DMP

Today Future the RT dispatch is to a DI of
150MW.
TODAY MS 200 MW DI 150 MW AQEI 148.5
MW CMSC Quantity 50 MW
18
Current vs. Future - Constrained OFF
Operational Meter
DMP

Today Future the RT dispatch is to a DI of
150MW.
TODAY MS 200 MW DI 150 MW AQEI 148.5
MW CMSC Quantity 50 MW
FUTURE MS 198 MW DI 148.5 MW AQEI 148.5
MW CMSC Quantity 49.5 MW
This illustration shows that during a constrained
off event the constrained participant is
receiving more CMSC than if the functionality
were implemented.
19
Rules of Thumb
  • Constrained ON
  • With the AQEI defining the CMSC quantity the
    participant, without the functionality, is being
    paid less today by an amount equal to the market
    schedule quantity, prior to adjustment,
    multiplied by the loss factor or.
  • CMSC Underpayment f MS pre

20
Rules of Thumb
  • Constrained ON
  • With the AQEI defining the CMSC quantity the
    participant, without the functionality, is being
    paid less today by an amount equal to the market
    schedule quantity, prior to adjustment,
    multiplied by the loss factor or.
  • CMSC Underpayment f MS pre
  • Constrained OFF
  • The participant, without the functionality, is
    being paid more today by an amount equal to the
    difference between the market schedule and
    dispatch instruction quantities, prior to
    adjustment, multiplied by the loss factor or.
  • CMSC Overpayment f MS pre - DI pre

21
Quantifying the Issue
  • Are Market Participants adjusting their offers to
    compensate for differences between operational
    meters and DMP?
  • IMO experience shows that the majority of meters
    have little or no losses between operational
    meter and DMP.
  • Are the benefits of implementation greater than
    the costs?

22
Next Steps
  • Finalized detailed assessment of impact to the
    market.
  • Ongoing Market Participant stakeholdering (MOSC
    and TP).
  • Develop recommendations for next MOSC and future
    TP meetings.
  • Develop action plan based on those
    recommendations.
  • Prepare to meet the Exemption obligations.
Write a Comment
User Comments (0)
About PowerShow.com