Title: Plug-In Migration
1Plug-In Migration A Better Approach to DCS
System Replacement
- Stephen Golemme, Sr Technical Consultant,
Invensys Process Systems
2When to Migrate?
- Threat of unscheduled downtime
- Emerging or new business needs are impossible to
support without new system - No longer cost effective to support old system(s)
- Old system(s) cannot support new technology
- Old system is declared end-of-life
3Issues Vendors Face
- Keep pace with Technology - Need for a next
generation system every 10 - 15 years - Obsolescence of parts
- Costly to maintain and support
- Need for systems that will do more
- Reluctance to compromise new system design to
accommodate the past - Next generation system products have a different
shape and size
4Popular Migration Solutions
- The Bulldoze demolish and start again
- Cable Solutions gut the original cabinet, cable
over to a rack of new equipment, adjust for I/O
mapping - Transition Solutions Replace the HMI, then
controllers, then finally the I/O modules - Gateways integration solution to share data
between and old system and a new system
5ARC Analysts Pros Cons
Migration Strategy Migration Strategy Benefits Challenges
Bulldoze - Rip out and start again (Originally only game in town) Most comprehensive way to migrate to a new system Costly, downtime issues Most impractical solution
Cable Solutions - Gut the original cabinet, cable over to a rack of new equipment, adjust for I/O re-mapping A quick solution for system interoperability. Low risk Fails to address end of life and maintenance issues, temporary solution, can be costly
Transition Solutions - Replace the HMI, then controllers , then finally the I/O modules. Small investment upfront, incremental change Much more costly over time almost double initial quote
Gateways - Integration solution to share data between and old system and a new system Effective solution for migrating to different platform from different supplier Increased footprint, time to install, I/O mapping issues
I/O Replacement - Plug-In to your existing legacy system racks. Very cost effective solution with reduced downtime, easily reversed if necessary Offered by small number of suppliers
6Designed to minimize cost, risk downtime
- I/O modules are manufactured to Plug-In to your
existing legacy system racks. - Reuse existing cabinets, racks, term. assemblies
and field wiring - No I/O mapping issues - exact match
- Minimum process downtime
- 100 new system (workstations, controllers and
I/O modules) - Full system warranty
7Plug-In DCS I/O Modules
- One for one I/O board replacement
- Meets or exceeds I/O capacity of legacy cards
- Lines up exactly with I/O points
- Manufactured using same components as traditional
I/O modules - Automatic bootup on installation
- Fully redundant I/O bus - no single point of
failure
8Unique Plug-In Solution
- Step 1 pre-install new workstations
controllers - Step 2 set process in steady state mode
- Step 3 replace I/O modules attach network
connectors - Step 4 loop check
- Step 5 start up process
- Step 6 making product saving money - day 1
!!!
And Its Reversible !!!
9Lowest Installed Cost
Eliminated installation rewiring costs
10Lost Production due to downtime
11Lowest Risk Solution
- Site Survey audit
- Hardware application review
- Requirements docs, design docs, test plans,
validation plans, implementation plans - Automated tools for database conversion and full
system documentation - Full system FAT off-site
- Switchover done in hours, not days or weeks
- Non-destructive, fully reversible
Migration Centers of Expertise
12Protect your investment
- Vendor should assume responsibility for the
entire system new old - Future upgrade paths and plans should be clearly
identified years ahead of schedule - Ensure your investment is protected and you are
supported for a lifetime!
13A Case Study WDPF Westinghouse Migration
- NL Hydro A Nalcor Energy Company, Holyrood,
Newfoundland Hydro - Migration of a 1990s Vintage Westinghouse WDPF
DCS - Informed by Vendor - no support after 2005
- Hardware Failures becoming more frequent.
- Island power system dictated fast, reliable
upgrade 2 weeks! - Foxboro migration selected
- Needed a cost effective, low risk migration
solution with minimum process downtime. - Partner that provides ongoing service support
locally - Proven experience
- New system must be better, not just a functional
replacement - Results
- 100 new system leveraging IPS integrated
portfolio of technology - Brand new DCS for 75k on 4M project
- Minimum downtime installation commissioning
to completion - 1 week! - Localized strong partnership with the IPS team
improved troubleshooting of process problems. - No more end-of-life issues, with backwards
compatibility guaranteed
14Plug-In A Better Approach to DCS System
Replacement
- 30 - 40 below a bulldoze solution
- Reuse the wiring, cabinets, nests, etc things
that dont fail - No I/O mapping issues
- No interim/throwaway solutions
- Easily reversible
- 1 small outage (1 day) away from a new system
- Check our references - please !!!
15Plug-In To...
- Foxboro Spectrum SPEC200
- Honeywell TDC2000 TDC3000
- Bailey NET90 INFI90
- Fisher PROVOX S10 S20
- Westinghouse WDPF
- Siemens Moore APACS
- Taylor Mod300
16To learn more visit the Invensys booth