Title: LARP Magnet Program Steve Gourlay
1LARP Magnet Program Steve Gourlay
Directives Program Goals, Priorities Implementat
ion - Management FY05 Summary FY06
Plans Summary Issues and Challenges
2Directives
- DOE Guidance
- It is our firm intention that the LARP
activities serve to explore the limits of the
technologies described herein. While the end
products of LARP will be applied to the LHC, LARP
is not intended to be an engineering or
construction service organization to that
facility. - The LARP is not intended to replace existing
base program support at the various laboratories
in superconducting magnet development and other
ongoing areas.
3Directives
- CERN Guidance Letter from Lucio Rossi (CERN
representative) - We strongly believe that the major steps in the
near term are - Construction of a quadrupole model, full
cross-section, with parameters that are really - significant for the LHC upgrade G ? 250 T/m , ?
? 90 mm (of course the larger the - better).
- Construction of simple systems that may address
the long magnets issues. - The manufacturing of a successful prototype for
2009 is real vital to the whole magnet - program, on both side of the Atlantic. Year 2009
is crucial since, according to the today - plan set by the CERN DG, is when basic decisions
on CERN future large projects will be - taken . . .
4Nb3Sn technology - appears to be the only
candidate for a substantial improvement - could
open upgrade scenarios such as 'dipole-first' Im
portant issues related to long Nb3Sn magnets need
to be addressed by vigorous RD The effective
Nb3Sn filament diameter (gt100 ?) is too large
(Material development required.) The choice of
the coil aperture is driven more by the power
density limit than by the beam acceptance An
estimate of the radiation parameters of the
magnets requires extensive simulations based on
detailed knowledge
5Gradient As a Function of Bore Size
Current LHC
mm
6Magnet Program Goals
- Provide options for future upgrades of the LHC
Interaction Regions - Demonstrate by 2009 that Nb3Sn magnets are a
viable choice for an LHC IR upgrade - (Developed in consultation with CERN and LAPAC)
- Focus on major issues consistency, bore/gradient
(field) and length
1.
- Predictable and reproducible performance
- TQ models (1 m, 90 mm aperture, Gnom gt 200 T/m,
Bcoil gt 12 T) - Long magnet fabrication
- LQ models (4 m, 90 mm aperture, Gnom gt 200 T/m,
Bcoil gt 12 T) - High gradient in large aperture
- HQ models (1 m, 90 mm aperture, Gnom gt
250 T/m, Bcoil gt 15 T)
7Target Program
Provides basis of many other options, but budget
is limited
8Program Components
- Focus on main goals
- Scale-up via simple models (CERN and LAPAC
guidance) - Large aperture quadrupoles
- Increase gradient/aperture
- Develop a collaborative infrastructure
- Individuals at each lab are committed to success
- Distribute tasks according to lab strengths
- Initial emphasis on developing technical
capabilities tech transfer - Investment for the future
9Program Implementation
- Model Magnets
- Technology Quadrupoles (TQ)
- Support structure development
- Reproducibility
- Field quality not a priority
- Supporting RD
- Long Racetrack coils (LR)
- Fast start, early feedback
- Practice coils (PC)
- Long cosq
- Defer due to budget/TQ results
- Materials Support
- Strand and cable evaluation
- Provide engineering material
- Long-term RD
- Design Studies
- Emphasize support of TQs
- Diversity to guide program and provide options
- Early effort to integrate labs
- Distribute expertise
- Develop collaborative program
10Management Structure
Magnet Steering Committee
Test Integration Group
Magnet Steering Committee (MSC) Define program,
identify tasks and assign task managers Lab
Representatives G. Sabbi, P. Wanderer, A.
Zlobin Lab Management Representatives S.
Gourlay, M. Harrison, R. Stanek
Lab representatives oversee tasks/sub-tasks at
host laboratory
11Process
- Start with overall program and goals
- CERN input
- DOE input
- MSC input
- L2s and task managers assemble tasks to
implement program - Gourlay/MSC
- Prioritize
- Budget guidance
- Assign tasks to appropriate organization
- Normalize effort, identify specific individuals
for tasks - Develop bottoms-up budget and resource-loaded
schedule - Adjust scope to fit according to priorities
Budget Resources LARP and Core Programs
12FY05 Program
- Great start
- Established ambitious but realistic program
- Excellent work by many people exceeds
expectations based on 1.1M budget - One major adjustment based on CERN input
- Dipole effort at BNL diverted to long magnet
scale-up - Based on small racetrack coil technology
successfully implemented at LBNL and FNAL -
13FY05 Highlights
- Technology Quads (TQ)
- Practice coil winding has begun
- Production cable runs this month
- Test Integration Group
- Already organizing and developing test standards
- No FY05 budget
- First quad (SQ-01) completed in FY04 and retested
in FY05 - LBNL-built, retested at FNAL
14Sub-scale Magnet Series
SC Coil
SM Dipole
SQ Quadrupole
- Cost-effective, rapid turn-around tools for
technology development - RD topics conductor, cable, mechanics,
materials, fabrication procedures - Two-layer SC racetrack coils field range of
9-12 Tesla fully instrumented - Testing in both dipole (SM) and quadrupole (SQ)
configurations
15Subscale Quad SQ01/SQ01b
- Nb3Sn, 110 mm aperture, Bmax gt11 T
- Test at LBNL 92 of short sample
- Analysis, disassembly inspection
- Reassembly w/higher preload
- Second Test at FNAL (SQ01b)
Axial support
Yoke-shell alignment
Yoke-pad alignment
16FY05 Tasks Design Studies
- - A. Zlobin
- Quadrupole
- Shell vs Block P. Ferracin
- Shell mechanical design study G. Ambrosio
- Separation Dipole
- D1 Design R. Gupta
- D1 cooling study T. Peterson
- Cryogenics
- IR Cryogenics Study R. Rabel
Significantly reduced effort moved to long
magnet scale-up
17FY05 Tasks - Materials
- - A. Ghosh
- Strand RD
- Heat treat studies/strand characterization
- Extracted strand studies in support of cable work
- Cable RD
- 1.00 and 1.30 keystone cable for TQs
- Conductor Procurement
- Close ties with DOE Conductor Development Program
- CDP has been instrumental in getting LARP started
- High performance material
- 100k contribution in FY05
- Must maintain a strong program
- Continued development for long term needs
- Maintain viable sources
Two distinct contributions Focused support of
model magnet program RD to provide ultimate
material
18FY05 Tasks Supporting RD
- - G. Ambrosio
- Sub-scale Quadrupole reassembly and test (SQ-01b)
completed - Subscale Quadrupole SQ-02
- Long magnet scale-up
- Prepare for rapid turn-on in 06
- Subscale dipole - discontinued
19FY05 Tasks Model Magnet RD
- - G.Sabbi
- TQ (Technology Quadrupole)
- Emphasis on quench performance, fabrication
techniques, support structure - 1 m length
- 90 mm aperture
- 2-layer coil
- gt 200 T/m
- Merge core program experience
- Distribute tasks
- Exchange/improve fabrication techniques
- Develop analysis approach
- Main Issues
- Support structure
- - Key and bladder (TQ1) vs collared (TQ2)
- - Approach to coil support
20 21Design Studies
- - A. Zlobin
- Reorganize in FY06
- IR Magnets
- Magnetic design and analysis
- Mechanical design and analysis
- Thermal analysis
- Quench protection analysis
- Test data analysis
- Integrate with AP and LARP magnet tasks
- Cryogenics
- IR cryogenics and heat transfer studies
- Radiation heat deposition
- Cryostat quench protection
-
22Materials
- - A. Ghosh
- Priority on providing support for magnet
development - Conductor Procurement
- Strand evaluation
- Cable fabrication and RD
- Should be healthy enough to support work for
future needs
Coordinate with DOE Conductor Development Program
23Supporting RD
- - G. Ambrosio
- Main emphasis is long magnet scale-up via
sub-scale coils - Coil test by end of FY06
- Shell-based support structure scale-up
- Implications for long term
- Associated Tasks
- Oven procurement and installation
- Fixturing and tooling
- Support structure design and fabrication
- Other tasks
- Rad hard materials - 59k, plus core program
support of student - Materials evaluation
- Sub-scale studies
Target
24Model Magnet RD
- - G.L. Sabbi
- Main program focus (Technology Quadrupoles)
- 2-Layer quads, 90 mm aperture, G gt 200 T/m ASAP
- Considerations
- Design approach end loading options, preload
- Fabrication techniques
- Structure options TQS, TQC
-
Convergence through working groups and internal
reviews
Opportunity to arrive at best-of-the-best and
increase confidence in modeling
25Test Integration Group
- S. Feher (FNAL) Leader
- A. Lietzke (LBNL)
- J. Muratore (BNL)
- Coordinate test-relate tasks between labs, reduce
overall costs - Define test goals
- Data format and exchange
- Normalize effort and establish costs
-
26Current Budget
27Budget Comparison
Move TQC tests to FNAL and revise estimates
Eliminate HQ start in FY06
Defer cos2q practice coil to FY07. Allow FNAL to
follow effort on LR at BNL
Decrease Test Integration effort
Reduced PM
2890 Scenario
- Program is already focused and aggressive
-
- Goal is well-defined in terms of schedule and
deliverables - Opt to maintain the goals and assume the increase
in risk - 10 cut is 565k
- I would propose to
-
29Major Milestones
30Core Program Relevance
- A critical mass sufficient to support the LARP
goals requires participation of the core programs - Supports team with a broad range of talents
- Provides resource contingency, infrastructure
- Full FTE capture mutually beneficial
- Provides diversity for an evolving technology
- Development of engineering tools
- Conductor development
- Adds breadth, depth allows risks
31Challenges
- Adjust scope to fit budget can we still
achieve goals? - This is a plan for success
- Budget reductions lead to increased risk
- Can we collaborate at the level necessary for
success? - Increase travel and inter-lab participation in
tasks - Move quickly to converge on technical approach
- Support structures and methods
- Fabrication techniques
- High priority on long magnet scale-up - budget
- Materials characterization and magnet performance
- Adequate supply of usable conductor
- Impact of long-term institutional interests and
program priorities - Core program vs LARP
32Summary
- LARP is a unique opportunity to expand the HEP
technology base - We have an aggressive, focused program to
implement well-defined goals - Progress on all fronts
- LARP and Core programs are complementary
- End result is a stronger, coordinated DOE RD
program - Issues
- Budget
- Quantitative commitment of core program support