Title: I
1IC Modernization at NPP Dukovany
- C. Karpeta, Scientech LLC-organizational
component - L. Leák, CEZ-Power Generation Division
- J. Rosol, CEZ-Power Generation Division
IAEA Technical Meeting on Increasing Power Output
and Performance of NPPs by improved IC
Systems 29-31 May 2007, Prague, Czech Republic
2Topics to be addressed
- Plant IC system assessment activities.
- Strategies of the IC modernization program.
- Strategies for the licensing process.
- Refurbishment of modules M1 and M2.
- Refurbishment of modules M3, M4, and M5.
- Resolution of the digital computer-based IC
systems important to safety dependability issue. - Operational experience with the innovated modules
M1 and M2.
3Plant IC system assessment activities
- Assessment performed by the French company EdF
and the English company NNC under the EU PHARE
program project ENE/15. It was a mutually
independent deterministic evaluation of the plant
IC system design, which resulted in - providing technical recommendations how to
eliminate the revealed shortcomings - providing system level specifications for
innovation of the individual IC systems - Plant internal audit, which was entirely the
plants own effort. - The individual plant IC systems were evaluated
against the following criteria - Impact on nuclear safety.
- Impact on plant availability.
- Operation and maintenance costs.
- Lifetime, maintainability.
- Compliance with regulatory requirements
- PSA level 1 was applied to evaluate the impact on
nuclear safety. - Simple straightforward methods were used for the
evaluation of the remaining criteria. - Plant external audit, conducted by the ENAC
consortium - It was focusing on safety aspects
4Plant IC system assessment activities- cont.
- IAEA ASSET inspections in 1993 and 1996.
- Practically all events caused by IC failures
were assigned level INES-0. - Evaluation of the IC equipment under the plant
launched qualification program. - The main conclusions of the IC relating parts of
the plant assessments were as follows - No major safety concerns relating to plant IC
systems were raised, although some aspects of the
design did not reflect the best international
practices, such as those of the IAEA safety
guides - Regarding the impact on the plant availability,
no significant IC shortcomings were found out - Significant problems were identified in the
lifetime and maintainability of the existing IC
equipment - Regarding compliance with regulatory
requirements, several areas where improvements
were feasible were identified
5Strategies of the IC modernization program
- Regarding the plant operational safety aspects
- The refurbished IC systems shall be implemented
in order of their significance to safety, with
the reactor protection system having the highest
priority. - For practical reasons, this principle is being
followed by having the program broken down into
two separate projects, i.e. - Refurbishment of the so-called modules M1 and M2,
where those modules encompass the reactor
protection system, the emergency load sequencer,
the post-accident monitoring system, the reactor
power limitation system, the reactor power
control system, the steam generators protection
systems, and the plant process computer,
including the in-core measurements processing. - Refurbishment of the so-called modules M3, M4,
and M5, where those modules encompass - - primary circuit logic systems (i.e.
systems providing control of component states) - and process control systems,
- - turbines and generators control and
protection systems, and the unit safeguard - system,
- - secondary circuit logic systems and
process control systems. - Hence, modules M1 and M2 refurbishment project
will be implemented
first.
6Strategies of the IC modernization program
cont.
- Regarding the plant availability aspects
- Step-by-step implementation of the program at
each unit over a specified time span. - Performing dismantling of the old systems and
installation, testing, and commissioning of the
new systems during the planned standard and
extended refueling outages. - Performing, to the extent limited by plant safety
and operational constraints, various preparatory
activities between the outages. - Regarding the plant IC system concept,
functionalities and implementation. - Retaining the original protection and control
concept. - Retaining, as far as reasonable and practicable,
the existing plant IC system structure. - Retaining all the existing functionalities.
Modification of functions important to safety are
allowed, provided that they are adequately
substantiated and have been approved by the
regulatory authority. - Current systems will be replaced by new systems
on a one-by-one basis. - Regarding the technology platform the equipment
of the new systems is to be built of. - The new systems shall be based on an up-to-date
proven technology platform. - Where practicable and economical, functional
equivalents of the current systems equipment and
components may be used. - Most of the new systems should be digital
computer-based systems.
7Strategies for the licensing process
- As per the provisions of the Czech Republic
Atomic Act, reconstruction and/or implementation
of changes in nuclear facilities that affect
nuclear safety, radiation protection, emergency
preparedness and security fall into the category
of activities for which a permission (license)
must be granted by the State Office for Nuclear
Safety (SONS). - The one-step licensing process to be applied
for implementation of reconstruction or other
changes that affect nuclear safety, radiation
protection, emergency preparedness and security
of nuclear facilities, as stipulated by the
provisions of 9, (1), f) of the Atomic Act, was
felt to be not quite adequate for a large-scope
several-stage IC system refurbishment projects
8Strategies for the licensing process- cont 1
- Project specific licensing process has been
conceived in several rounds of discussions
between the plant operator and the regulatory
body. This process is copying to certain extent
the licensing process applied to new nuclear
power plant projects.
9Strategies for the licensing process- cont 2
- Project specific licensing requirements have been
set forth by the regulatory body. They relate to
the following areas - Classification of the IC functions, systems and
equipment important to safety - Acceptability of the digital computer-based IC
systems important to safety. - Software development process for the IC systems
important to safety. - Verification and validation of the software for
the IC safety systems. - Defense against common cause failures due to
errors in the software of IC safety systems. - Communications between sub-systems of the digital
computer-based IC safety systems. - Testability of the digital computer-based IC
safety systems during reactor operation. - Compliance to the single failure criterion.
- Equipment qualification.
- Reliability of the innovated IC systems
important to safety.
10Refurbishment of modules M1 and M2Installation
and commissioning of the refurbished modules
started at unit No.3 in March 2003, and was
completed in May 2005
- The following general technical guidelines were
adhered to - Reactor trip and engineered safety features
actuation functions are to be implemented in one
triple redundant system, namely the reactor
protection system. - Reactor power limitation functions are be
implemented in each of the reactor protection
system divisions, but functionally isolated from
the trip functions. - Number of sensors is to be reduced.
- Sensor sharing between the safety systems is
allowed. Limited sensor sharing between safety
systems and systems of lower safety grade may be
used. - Some functions of the safety systems can be
modified in correspondence with the plant
proposed and the regulatory authority approved
changes. - Post-accident monitoring is to be implemented as
a separate system. - The technical level and quality of core
monitoring should be significantly improved
through improved processing of the measurement
data provided by the existing reactor in-core
instrumentation. - Computerized functions of operator support should
be significantly extended, and the human-machine
interface should be improved - Only limited modifications to the main and
emergency control rooms are allowed. - The current structure of manual controls and
alarm displays should be kept. - Extended diagnostic functions should be provided
11Refurbishment of modules M1 and M2- cont. 1
- The design and implementation of the refurbished
systems is compliant with - the requirements for assurance of nuclear safety
set in the Czech Republic legislation (Atomic
Act, SONS regulations) - the project specific requirements set by SONS
- the individual IC systems specific requirements
set by the project team, which relate to the
assurance of functionality, reliability,
performance, environmental durability, and
quality - the provisions of the applicable standards.
12Refurbishment of modules M1 and M2- cont. 2
- Block diagram of the refurbished modules M1 and
M2 is depicted in Fig.1 - Photos of the modernized main control room of
unit No.3 and of the original and current ESFAS
equipment are presented in Fig.2 through 4. - The project implementation at unit No.1 is
nearing completion. Its implementation at units
No.2 and 4 is in progress. The project is to be
completed in 2009.
13Refurbishment of the NPP Dukovany IC System
Overall architecture Fig. 1
14 Reactor protection system Fig. 2
old new
15New MCRFig. 3
16Sometimes it wasnt easyFig. 4
17Refurbishment of modules M3, M4, and M5
- The following preparatory and initial activities
have been performed so far, or are being still in
progress - The so-called Coordination Design Phase 1 has
been elaborated. It defines the overall concept
of the refurbished IC systems, specifies
applicable requirements for their design and
implementation, specifies the hardware and
software technology platforms the refurbished IC
systems should be built of, and specifies a
breakdown of the project implementation into
seven stages. - Coordination Design Phase 2 has been
elaborated. It specifies the control algorithms
to be implemented in the refurbished systems. - Safety classification of the IC functions in
question has been performed to the guidance
provided in the technical standard CSN IEC 61226. - Elaboration of the so-called technological
control algorithms of the actuators. - Measurement of the electromagnetic environment
and interferences pertinent to the existing
cabling. - Measurement of the electromagnetic environment in
the locations of the new IC equipment. - Analyses of technical characteristics of the
interface devices, e.g. relays. - Analyses of the impacts of lightning and
short-circuit currents on the existing cabling. - Establishing photo-documentation of the current
state of the panels housing the IC equipment
18Refurbishment of modules M3, M4, and M5- cont. 1
- The main constraints imposed on the project
implementation are as follows - Replacement activities shall be performed during
the units planned outages. - 40 to 50 IC equipment panels will need to be
replaced and tested during each unit outage they
include approximately 1000 functions. - In contrary to the technique used during the
project T544 implementation, off-line
installation of the new equipment, i.e. equipment
installation during an outage without connecting
its outputs to the actuated devices and providing
those connections in the next outage, is not
possible for technical reasons. - The equipment cannot be refurbished on a
straightforward one by one basis since adequate
separation of the IC functions based on their
safety classification needs to be accomplished.
19Refurbishment of modules M3, M4, and M5- cont. 2
- The refurbished portion of the plant IC system
will consist of the following major parts - DIAG, RSBP, RSBS, RSBT
- System DIAG is a new system, which will provide
- - acquisition, time stamping processing,
display, and archiving of the operational and
diagnostic data generated by the refurbished
modules M3 through M5 - - transmission of a selected set of that
operational and diagnostic data to the unit
process computer system - - data acquisition from the unit process
computer system and their distribution to the
refurbished systems.
20Refurbishment of modules M3, M4, and M5- cont. 3
- System RSBP will
- provide monitoring and control functions of the
primary circuit components and processes,
including dedicated human-machine interfaces - be replacing the current relay logic systems and
control systems of the primary circuit - System RSBS will
- provide monitoring and control functions of the
secondary circuit components and processes,
including dedicated human-machine interfaces - be replacing the current relay logic systems and
control systems of the secondary circuit
21Refurbishment of modules M3, M4, and M5- cont. 4
- System RSBT will
- provide monitoring and control functions of the
units both turbine-generators, including
dedicated human-machine interfaces - be replacing the unit safeguard system, the
turbine-generators protection system, the turbine
control systems, and the electronic hard-wired
logic systems. - Refurbishment of the modules M3 through M5 is to
be completed by the year 2015.
22Distribution of IC functions in correspondence
with their safety classification - Fig. 5
1P10
1P11
1P12
1P15
1P13
1P16
A1
C2
C4
A5
N6
B3
The existing equipment and its safety classified
functions
Example of 6 cabinets
N2
B1
C6
A2
B4
C1
N3
N5
B2
N1
A6
A category
B category
C category Nonclassified
The new equipment
23Original IC Fig.6NSSS part
BOP part
24Dependability of digital computer-based IC
systems important to safety
- To ensure adequate level of dependability of
digital computer-based IC systems important to
safety the following measures were taken
regarding the hardware and software development
and manufacture - Requirements common to the development and
manufacture of computer hardware implementing IC
functions of any of the three safety category
functions, i.e. category A, B, or C as per the
provisions of the standard IEC 1226, have been
specified. - Specific graded requirements have been specified
for the development and implementation of
computer software, which provides safety category
A functions, or safety category B functions, or
safety category C functions. - Adherence to these requirements was monitored by
conducting technical audits at the suppliers of
digital computer-based IC systems for modules M1
and M2.
25Dependability of digital computer-based IC
systems important to safety cont.1
- These measures were aimed at getting high quality
hardware and as error free as possible
software, commensurate with safety significance
of the individual refurbished IC systems. - In parallel, measures were also taken to cope
with those situations when in spite of all the
efforts to avoid errors in software, common cause
failures might occur due to some residual
software errors. These measures consisted in - providing within the refurbished IC safety
systems two diverse lines of protection against
the so-called frequent design basis events, i.e.,
events with the estimated frequency of occurrence
higher than 10E-3/year - providing within the refurbished modules M1 and
M2 four lines of defense-in-depth, which are
mutually independent and to some extent diverse. - Detailed description of these measures is beyond
the scope of our paper hence, also beyond the
scope of this presentation.
26Dependability of digital computer-based IC
systems important to safety - cont.2
- The main requirements for the development and
manufacture of computer hardware were as follows - Development of hardware shall be divided into
formalized phases with specification of
activities pertinent to each phase. - Each phase shall be terminated by verification
and shall include generation of appropriate
documentation. - Verification, quality assurance, inspection and
test activities shall be performed to the
provisions of appropriate plans. - Sub-systems, modules and components to be used in
the computer system may be both dedicated
hardware products as well as off-the- shelf
products qualified for a particular application. - The proper working of the integrated computer
system shall be demonstrated.
27Dependability of digital computer-based IC
systems - SW category A
- The main requirements for the development of
computer software were as follows - Development process of software, which implements
category A functions shall be a well structured
and fully formalized process consisting of
planning and development activities. - Planning activities shall result in establishing
a set of planning documents, including - - Software quality assurance plan
- - Software verification and validation plan
- - Software configuration management plan
- - Software safety plan.
28Dependability of digital computer-based IC
systems - SW category A cont.
- Development activities shall include
- Requirement activities, i.e. software
requirements specification, followed by
performance of requirements safety
analysis, VV tasks, and CM tasks. - Design activities, i.e. software design
specification, followed by performance of design
safety analysis, VV tasks, and CM tasks. - Implementation activities, i.e. coding, followed
by performance of code safety analysis,
VV tasks, and CM tasks. - Integration activities, i.e. software
integration, followed by performance of
safety analysis tasks, VV tasks, and CM
tasks. - Validation activities, i.e. software testing,
performance of safety analysis tasks, VV tasks,
and CM tasks. - Installation activities, i.e. software
installation into the processing units,
performance of VV and CM tasks. - No third party independent VV activities need
to be performed provided that the VV team is
management and financial independent of the
development team.
29Dependability of digital computer-based IC
systems - SW category B
- Development process of software, which implements
category B functions shall be a well structured
and to large extent formalized process consisting
of planning and development activities. - Planning activities shall result in establishing
a set of planning documents similar to that of
the category A software development process but
for the software safety plan. - Development activities shall be basically the
same as those of the software category A
development process but for the software safety
activities. - Performance of the QA, VV, and CM activities
need not be documented to the same level of rigor
as for category A software.
30Dependability of digital computer-based IC
systems - SW category C
- Development process of software, which implements
category C functions shall be a structured and to
some extent formalized process consisting of
planning and development activities. - Planning activities shall result in establishing,
as a minimum, of the following plans - - Software quality assurance plan.
- - Software verification plan.
- Development activities shall be basically the
same as those of the software category B
development process but for integration and
validation activities, which may be viewed as a
part of the computer system integration and
validation. - Performance of the QA and VV may be documented
in a summary form.
31HW SW development process technical audits
- Regarding the conduct of technical audits, it was
required that they be focusing on - Auditing the planning documents generation
process. - Auditing the software and hardware requirements
setting and implementation processes. - Auditing the software and hardware design
processes. - Auditing the software and hardware manufacturing
and testing processes. - Auditing the implementation of the verification,
validation, configuration management and software
safety processes.
32HW SW development process technical audits
cont.
- The performed technical audits and the process of
audit findings and observations disposition
contributed significantly to the verification
that - The development of software and hardware
important to safety was adequately planned for by
the audited organizations. - A V-shaped model of the system, hardware and
software lifecycle, which is depicted in Fig.8,
was followed in the development process of
computer hardware and software important to
safety. The development activities as implemented
by the audited organizations were consistent in
all significant aspects with the above stated
main requirements as detailed by the provisions
of the planning documentation and by the
provisions of the applicable standards.
33HW SW LifecycleFig. 7
34Implementation at Unit B3
35Implementation and start of operation
- Step by step implemetation in the course of four
standard refueling outages - Validation in parallel operation (esp. step No.7)
- Specific test program for reactor start - up
(step No. 8) - Regulatory inspection and independent supervision
- Trial operation (12 months)
- Verification of guaranteed parameters
- Guarantee period operation (ended on 20th May
2007)
36Lessons learned(good practice)
- Careful preparation period
- (started in PHARE project with English NNC Ltd)
- Splitting in two phases M1,2 and M3-5
- (important for implementation during standard
refueling outages) - Conservative approach
- What has not to be changed - shall not be
changed - Use of the plant simulator
- (functional specification, test design
verification) - Training system (selected NPP personnel acted as
tutors) - NPP staff involvement
- (fundamental for implementation and
commissioning)
37Operational experience
- Advantages of the new IC systems
- Employment of advanced fuel due to new core
monitoring - More reliable and accurate rod control (RRCS)
- Better ex-core measurement ( fixed detectors,
comfortable calibration, ..) - New functions and better HMI of the process
computer (PCS) - - operators support (e.g. SPDS)
- - separated display of alarms
- - large and detailed screens
- - additional dedicated displays
- Powerful diagnostics
38Operational experienceresume
- The new, refurbished, IC systems
- are compliant with regulatory authority
requirements - facilitate plant service time extension
- meet the plant operator expectations
- The commissioning and operation in the course of
warranty period (24 months) have proved the
feasibility of large scale IC refurbishment
within standard refueling outages - The M1,2 refurbishment project at Dukovany Unit 3
- is viewed as a success
39IC Modernization at NPP Dukovany
- Thank you for your attention