Title: Use of modern technologies in the Paks NPP
1Use of modern technologies in the Paks NPP
- TÚRI Tamás
- Project manager
2Hungary
3Satellite picture of Paks and the NPP
4Aerial photograph of the NPP
5General view of the Paks NPP
6Hungarian Eletricity Production
7Total Electricity Production of the Paks NPP
8Cumulative Load Factor
9Content
- Life time extension and IC
- What to do?
- What have we done?
- Lessons learnt
10Life time extension and IC
- Tasks for the life time extension
- To prove that the non changeable components of
the plant can serve during the extended life time - To demonstrate that the performance of the
changeable components are maintainable during the
extended life time and to provide the way of this
maintenance
11Life time extension and IC contd
- IC is changeable and life time of IC systems is
much shorter than the extended life time of the
plant, therefore refurbishment is needed. - The architecture and even the functions of the
20-30 years old IC were determined by the
technologies available at that time. - Today technology gives us the chance to design
systems with soft technologies, offering higher
level of safety and availability with less volume
of equipment and with less cost of maintenance. - How much of the offered convenience of the new
technologies can be accepted? (Albert Einstein
Technological progress is like an ax in the hands
of a pathological criminal).
12Tasks of refurbishment preparation
What to do?
- To justify that the refurbishment is
- feasible,
- economical,
- Necessary for life time extension
- Establish a methodology
- Formal description of the functionality of the
Process Control System in a database - Definition of the ideal architecture
- Identification of the optimal scope of subsystems
to be refurbished in a single step - factor of physical conditions
- factor of importance
- factor of refurbishment (product of the previous
two) - Specification of equipment and tools to be used
(or to be not used) - Literature research
-
13Description of the Process Control System
Operational Procedures
- Funkcionális specifikáció
14What to do?
- Development environment
- The application SW should be exclusively in the
form of function blocks - The user wants to handle (independence from the
supplier) - The designer (process engineer) can create the SW
- ProfiSim development environment with simulation
- Editor dealing with the function blocks
- Simulation tests
- Multilevel structure
- Representation of the operating HW
- Automated, repeatable tests
- Multiprocessor, large system
- Handling the communications
- Handling failures
- Living documentation
- Open SQL database structure, output for other
systems
15What have we done? RPS refurbishment
- Contract with Siemens AG 1996
- Unit 1 commissioning 1999
- Unit 2 commissioning 2000
- Unit 3 commissioning 2001
- Unit 4 commissioning with new, Unit independent
SW 2002 - Unit 1,2, and 3 new, Unit independent SW 2003
16Safety IC reconstruction lifecycle (IEC 880)
The demands of users, corporate, national and
international regulations, outputs from the
establishing phase, proposals
Establishment
System requirements
Preparation
System specification
Conventional IC requirements
Computer hardware requirements
Software requirements
Software design
Computer hardware design
Conventional IC design
Software coding
Computer hardware manufacturing
Conventional IC manufacturing
System analysis
Computer system integration
Design and manufacturing
Factory acceptance testing
On-site installation and integration
System, I/O testing site acceptance test
Installation
Trial operation
Operation
17Architecture of the new RPS
18Representative Configuration
19Factory Acceptance Testing
MMI of the RPS
Representatives of the Supplier and the Customer
TEST COMPUTER
I/O INTER-FACE
RPS FULL CONFIGURATION
TEST CASES
AI
DI
TEST ORACLE
MMI
AO
DO
COMPA-RATOR
20RPS hardware or RPS model in the loop tests
FULL SCOPE SIMULATOR
PROCESS MODEL IC MODEL
RPS MODEL
MMI
21Reactor Pressure controller
22Reactor pressure with the original controller
23Reactor pressure with the new controller
24Lessons learnt
- The scope for a single step refurbishment was not
optimal - The actuator controllers were not refurbished,
therefore interface design was needed - The HMI was not refurbished, therefore interface
design was needed - The scope of the upgrade was too small, but the
administration and licensing was quite big,
therefore the efficiency of engineering was not
optimal - The specification was limited by the Russian
design because of routine. More modifications
should have been specified for the operational
transients. - The SW coding was conventional due to lack of
time. The automatic code generation should be
solved in the future.
25Thank you for your attention!
26(No Transcript)
27The reactor hall
28The turbine hall
29Old safety instrumentation and logic panels
30Old safety instrumentation and logic panels 2
31The neutron flux pre-amplifiers
32Start-up and periodic testing
33Safety cable tray installation
34Safety cable trays in the turbine hall
35Space preparation for the new cabinets
36Installed new safety IC cabinets
37The safety IC representative configuration
38The TS computer
39The consoles in the old and the new systems
40The panels in the old and the new systems
41Main control room installation
42Final arrangement in the main control room
43Back view of the new RPS panels in the MCR