Title: Current Status Summary on AIDC TCS Program


1
Current Status Summary onAIDC TCS Program
  • Drj Dar-Jen Sun,Joe Chen, YW Chen,Grand Jiang,
    Chia-Fa Ou, YIAO-TENG HO,YUNG-KUO CHIANG, David
    Ho, Marco Yao, Alan Hsu, Benjamine Lee, Camel
    Hsa,Steven Uong, Peter Tang, Max Yen, Andrew
    Shih, Chung-Jen Tsai, John Peng, Eric Hwang, DICK
    WANG

Aerospace Industrial Development Corp. Taiwan,
R.O.C.
2
Delivery status (1/2)
  • In the past, this July to October AIDC has
    delivered following items on schedule
  • Links 62 each
  • Upper/Mid Sliders for jig 2 sets/8 EA
  • Middle Brackets 2 sets/4 EA

3
Delivery status (2/2)
To-be DELIVERY items
PRODUCT DESCRIPTION QTY
SHIPPING DATE
1. PDS LINKS
6 EA 2008 March 2. LOWER
BRACKETS 8 EA
2007 December 3. TRACKER ROD BRACKETS
6 EA 2008/01/01 4. R/W TRACKER RADIATOR
PANEL 2 EA 2008/01/01 5. RAM
RADIATOR PANEL 1 EA
2008/02/15 6. WAKE RADIATOR PANEL
1 EA 2008/04/21
4
Mid Brackets (start from 4.5 thickness
Al-Alloy) tapes on these area used to protect the
ALODINE coating
5
? Current Major efforts on(1/3)
  • Panel sample de-bonding test
  • Team up with NSPO to conduct testing at AIDC
  • First as-run on Oct. 8 per NASA approved
    procedure
  • See NSPO/Steven test summary (20cm/75C)
  • Remaining test will be initiated on Oct.22 or 23
    at AIDC
  • Has postponed the bonding of the first tracker
    radiator before completing the test
  • Go-ahead order after discussion and agreement on
    the final result

6
? Current Major efforts on(2/3)
  • 1st set Tracker Panel Fabrication
  • We start the first set tracker panel production
    per last TIM decision (a conservative instead of
    parallel aggressive approach)
  • Completed the Bonding Fixture (BOF) design and
    manufacturing
  • Handle many RFW/D paper works with CGS
  • Skins, Rohacell core and inserts are ready
  • Pre-fit check with Heat pipe and other components
  • Pending de-bonding test result to continue
    bonding process

7
? Current Major efforts on(3/3)
  • Preparation on Jig Installation _at_ CERN
  • Prepare the pre-integration plan (ATS format per
    NASA) to support integration activity at CERN
  • Has submitted ATS document for review and
    received the comments and made the revision
  • Plan to conduct the activity on Nov 28 but maybe
    delay since the change of integration sequence by
    TRDUTOF to cause the impact on the original
    installation plan
  • This issue will be expected to discuss and decide
    the final approach during TIM

8
? Major Material need buy status
Well prepared no impact to production
9
Tracker panel BOF with Rohacell inserts
(pre-fit check)
10
  • Cover plate for Tracker panel BOF

11
Skins of Tracker panel in CMM
12
Remark
  • Until now, there are design changes for R/W
    panels in progress.
  • FM Panels DRW updated schedule
  • Assembly drawings for TRACKER radiator and
    ECO-00119(10/18)
  • RAM radiators (10/31) gtgtwill impact BOF design
    and manufacture
  • WAKE radiators (11/21)

13
  • Design DRW keeps changing did not allow us to
    have extension window to final delivery. AIDC
    always needs to allocate more resources to catch
    up the schedule but no reimbursement to
    compensate from AMS.