Title: Current Status Summary on AIDC TCS Program
1Current Status Summary onAIDC TCS Program
- Drj Dar-Jen Sun,Joe Chen, YW Chen,Grand Jiang,
Chia-Fa Ou, YIAO-TENG HO,YUNG-KUO CHIANG, David
Ho, Marco Yao, Alan Hsu, Benjamine Lee, Camel
Hsa,Steven Uong, Peter Tang, Max Yen, Andrew
Shih, Chung-Jen Tsai, John Peng, Eric Hwang, DICK
WANG
Aerospace Industrial Development Corp. Taiwan,
R.O.C.
2Delivery status (1/2)
- In the past, this July to October AIDC has
delivered following items on schedule - Links 62 each
- Upper/Mid Sliders for jig 2 sets/8 EA
- Middle Brackets 2 sets/4 EA
3Delivery status (2/2)
To-be DELIVERY items
PRODUCT DESCRIPTION QTY
SHIPPING DATE
1. PDS LINKS
6 EA 2008 March 2. LOWER
BRACKETS 8 EA
2007 December 3. TRACKER ROD BRACKETS
6 EA 2008/01/01 4. R/W TRACKER RADIATOR
PANEL 2 EA 2008/01/01 5. RAM
RADIATOR PANEL 1 EA
2008/02/15 6. WAKE RADIATOR PANEL
1 EA 2008/04/21
4Mid Brackets (start from 4.5 thickness
Al-Alloy) tapes on these area used to protect the
ALODINE coating
5? Current Major efforts on(1/3)
- Panel sample de-bonding test
- Team up with NSPO to conduct testing at AIDC
- First as-run on Oct. 8 per NASA approved
procedure - See NSPO/Steven test summary (20cm/75C)
- Remaining test will be initiated on Oct.22 or 23
at AIDC - Has postponed the bonding of the first tracker
radiator before completing the test - Go-ahead order after discussion and agreement on
the final result
6? Current Major efforts on(2/3)
- 1st set Tracker Panel Fabrication
- We start the first set tracker panel production
per last TIM decision (a conservative instead of
parallel aggressive approach) - Completed the Bonding Fixture (BOF) design and
manufacturing - Handle many RFW/D paper works with CGS
- Skins, Rohacell core and inserts are ready
- Pre-fit check with Heat pipe and other components
- Pending de-bonding test result to continue
bonding process
7? Current Major efforts on(3/3)
- Preparation on Jig Installation _at_ CERN
- Prepare the pre-integration plan (ATS format per
NASA) to support integration activity at CERN - Has submitted ATS document for review and
received the comments and made the revision - Plan to conduct the activity on Nov 28 but maybe
delay since the change of integration sequence by
TRDUTOF to cause the impact on the original
installation plan - This issue will be expected to discuss and decide
the final approach during TIM
8? Major Material need buy status
Well prepared no impact to production
9 Tracker panel BOF with Rohacell inserts
(pre-fit check)
10- Cover plate for Tracker panel BOF
11Skins of Tracker panel in CMM
12Remark
- Until now, there are design changes for R/W
panels in progress. - FM Panels DRW updated schedule
- Assembly drawings for TRACKER radiator and
ECO-00119(10/18) - RAM radiators (10/31) gtgtwill impact BOF design
and manufacture - WAKE radiators (11/21)
-
13- Design DRW keeps changing did not allow us to
have extension window to final delivery. AIDC
always needs to allocate more resources to catch
up the schedule but no reimbursement to
compensate from AMS.